Flattening the Duck Dynamic Grid Solutions for Integrating Renewables. December 16, 2013. The California ISO Duck Chart (2012 – 2020). 13,100 MW 5-8pm. 5,300 MW 8-11am. Potential over-generation. CAISO Duck Chart (2020 Issues). 13,100 MW 5-8pm. 5,300 MW 8-11am. Potential - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: December 16, 2013

Making Clean Local Energy Accessible Now December 16, 2013

Flattening the DuckDynamic Grid Solutions for Integrating Renewables

Page 2: December 16, 2013

Making Clean Local Energy Accessible Now

2

The California ISO Duck Chart (2012 – 2020)

5,300 MW 8-11am

Potential over-generation

13,100 MW 5-8pm

Page 3: December 16, 2013

Making Clean Local Energy Accessible Now

3

CAISO Duck Chart (2020 Issues)

5,300 MW 8-11am Potential

over-generation

13,100 MW 5-8pm

Page 4: December 16, 2013

Making Clean Local Energy Accessible Now

4

Flatten the Duck – Import/Export

Import/Export

Page 5: December 16, 2013

Making Clean Local Energy Accessible Now

5

Flatten the Duck – Curtail Baseload GenerationRather than address over-generation with more natural gas generation, California can strategically plan maintenance on baseload plants during shoulder months.

Source: CAISO Summer Loads and Resources Assessment

CAISO planned outages ranged up to 7000 MW per weekday in the summer of 2012.

Page 6: December 16, 2013

Making Clean Local Energy Accessible Now

6

Flatten the Duck – Demand Response

Demand Response

Page 7: December 16, 2013

Making Clean Local Energy Accessible Now

7

Addressing the Duck Chart with Energy Storage

Energy Storage

Page 8: December 16, 2013

Making Clean Local Energy Accessible Now

8

Addressing the Duck Chart with Curtailment

Curtailment

Page 9: December 16, 2013

Making Clean Local Energy Accessible Now

9

Flattening the Duck: All Solutions

Page 10: December 16, 2013

Making Clean Local Energy Accessible Now

Back-up Slides

Page 11: December 16, 2013

Making Clean Local Energy Accessible Now

11

Import/Export Assumptions

Page 12: December 16, 2013

Making Clean Local Energy Accessible Now

12

Import/Export Assumptions

Source: CAISO 2013 Summer Loads & Resources Assessment (May 6, 2013)

2012 Peak Daily ISO Imports = ~11,500 MW

Page 13: December 16, 2013

Making Clean Local Energy Accessible Now

13

Demand Response Assumptions

Page 14: December 16, 2013

Making Clean Local Energy Accessible Now

14

Energy Storage Assumptions

Page 15: December 16, 2013

Making Clean Local Energy Accessible Now

15

Curtailment Assumptions

Page 16: December 16, 2013

Making Clean Local Energy Accessible Now

16

CAISO Duck Chart (2020 vs. 2013)

Lowest net load: 11,700 MW around

1pm

Highest net load: 25,000 MW at 8pm

Page 17: December 16, 2013

Making Clean Local Energy Accessible Now

17

Natural Gas Plants Have Integration CostsRenewables have predictable variability. Fossil fuel power plants often shut down unexpectedly, forcing energy consumers to foot the bill for reserves and frequency response.

Source: CAISO Summer Loads and Resources Assessment

More than half of the outages associated with conventional generation are unplanned.