CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

May 08, 2018

Download

Documents

hacong
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10
Page 2: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

i

CONTENT LIST

S. NO. CONTENTS PAGE NO.

1.0 EXECUTIVE SUMMARY 1

2.0 INTRODUCTION OF PROJECT/ BACKGROUND INFORMATION 3

(i) IDENTIFICATION OF PROJECT & PROJECT PROPONENT 3

(ii) BRIEF DESCRIPTION OF THE NATURE OF PROJECT 3

(iii) NEED FOR THE PROJECT & ITS IMPORTANCE TO THE COUNTRY

/REGION

4

(iv) DEMAND-SUPPLY GAP 5

(v) IMPORTS Vs. INDIGENOUS PRODUCTION 5

(vi) EXPORT POSSIBILITY 5

(vii) DOMESTIC/EXPORT MARKETS 5

(viii) EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE

PROJECT

5

3.0

PROJECT DESCRIPTION 6

(i) TYPE OF PROJECT INCLUDING INTERLINKED AND INDEPENDENT

PROJECTS, IF ANY

6

(ii) LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC

LOCATION, AND PROJECT BOUNDARY & PROJECT SITE LAYOUT)

WITH COORDINATES

6

(iii) DETAILS OF ALTERNATE SITES CONSIDERED 8

(iv) SIZE OR MAGNITUDE OF OPERATION 8

(v) PROJECT DESCRIPTION WITH PROCESS DETAIL 8

(vi) RAW MATERIAL REQUIRED ALONG WITH ESTIMATED QUANTITY,

LIKELY SOURCE, MARKETING AREA OF FINAL PRODUCTS, MODE OF

TRANSPORT OF RAW MATERIAL AND FINISHED PRODUCT

9

(vii) RESOURCES OPTIMIZATION/ RECYCLING AND REUSE ENVISAGED IN

THE PROJECT, IF ANY, SHOULD BE BRIEFLY OUTLINED

9

(viii) AVAILABILITY OF WATER ITS SOURCE, ENERGY /POWER

REQUIREMENT AND SOURCE

9

(ix) QUANTITY OF WASTE TO BE GENERATED (LIQUID AND SOLID) AND

SCHEME FOR THEIR MANAGEMENT/DISPOSAL

10

4.0 SITE ANALYSIS 10

(i) CONNECTIVITY 10

(ii) LAND FORM, LAND USE AND LAND OWNERSHIP 11

(iii) TOPOGRAPHY & DRAINAGE 11

(iv) EXISTING LAND USE PATTERN {AGRICULTURE, NON-AGRICULTURE,

FOREST, WATER BODIES (INCLUDING AREA UNDER CRZ)},

11

Page 3: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

ii

S. NO. CONTENTS PAGE NO.

SHORTEST DISTANCES FROM THE PERIPHERY OF THE PROJECT TO

PERIPHERY OF THE FORESTS, NATIONAL PARK, WILD LIFE

SANCTUARY, ECO SENSITIVE AREAS, WATER BODIES (DISTANCE

FROM THE HFL OF THE RIVER), CRZ. IN CASE OF NOTIFIED

INDUSTRIAL AREA, A COPY OF THE GAZETTE NOTIFICATION

(v) EXISTING INFRASTRUCTURE 14

(vi) SOIL CLASSIFICATION 14

(vii) CLIMATIC DATA FROM SECONDARY SOURCES 14

(viii) SOCIAL INFRASTRUCTURE AVAILABLE 14

5.0 PLANNING BRIEF 14

(i) PLANNING CONCEPT (TYPE OF INDUSTRIES, FACILITIES, AND

TRANSPORTATION ETC.) TOWN AND COUNTRY

PLANNING/DEVELOPMENT AUTHORITY CLASSIFICATION

14

(ii) POPULATION PROJECTION 14

(iii) LAND USE PLANNING 14

(iv) ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL & SOCIAL) 14

(v) AMENITIES/FACILITIES 15

6.0 PROPOSED INFRASTRUCTURE 15

(i) INDUSTRIAL AREA (PROCESSING AREA) 15

(ii) RESIDENTIAL AREA (NON PROCESSING AREA) 15

(iii) GREEN BELT DEVELOPMENT 15

(iv) SOCIAL INFRASTRUCTURE 15

(v) CONNECTIVITY 15

(vi) DRINKING WATER MANAGEMENT (SOURCE &SUPPLY OF WATER) 15

(vii) SEWERAGE SYSTEM 16

(viii) INDUSTRIAL WASTE MANAGEMENT 16

(ix) SOLID WASTE MANAGEMENT 16

(x) POWER REQUIREMENT & SUPPLY/SOURCE 16

7.0 REHABILITATION AND RESETTLEMENT (R & R) PLAN 16

(i) POLICY TO BE ADOPTED (CENTRAL/STATE)IN RESPECT OF THE

PROJECT AFFECTED PERSONS INCLUDING HOME OUSTEES, LAND

OUSTEES AND LANDLESS LABORERS (BRIEF OUTLINE TO BE GIVEN)

16

8.0 PROJECT SCHEDULE & COST ESTIMATES 16

(i) LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF

COMPLETION

16

(ii) ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS OF

ECONOMIC VIABILITY OF THE PROJECT

16

Page 4: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

iii

S. NO. CONTENTS PAGE NO.

9.0 ANALYSIS OF PROPOSAL 16

(i) FINANCIAL AND SOCIAL BENEFITS WITH SPECIAL EMPHASIS ON THE

BENEFIT TO THE LOCAL PEOPLE INCLUDING TRIBAL POPULATION IF ANY

16

LIST OF TABLES

TABLE NO. NAME PAGE NO.

1. SALIENT FEATURES OF THE PROJECT 1

2. DETAILS OF MANPOWER 6

3. DETAILS OF EXCAVATION 9

4. WATER REQUIREMENT 10

5. ENVIRONMENTAL SETTINGS DETAILS 11

LIST OF FIGURES

FIGURE NO. NAME PAGE NO.

1. MAP SHOWING GENERAL & SPECIFIC LOCATION OF THE

PROPOSED MINE SITE

7

2. MAP SHOWING 10 KM RADIUS STUDY AREA 13

ANNEXURES LIST

ANNEXURE NO. ANNEXURE PAGE NO

1 KHASRA MAP 18

2 LEASE DOCUMENTS 19-25

Page 5: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh

Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. UltraTech Cement Ltd. (Unit- Bela Cement Works) 1

PRE-FEASIBILITY REPORT

1.0 EXECUTIVE SUMMARY

M/s. UltraTech Cement limited (Unit: Bela Cement Works) has proposed a project of Bela Cement

Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production

Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh Cu.M Overburden at Village- Devra, Tehsil-

Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Table – 1

SALIENT FEATURES OF THE PROJECT

S. No. Particulars Details

A. Nature of the Project Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with

Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and

2.575 Lakh Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan,

and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

B. Size of the Project

1. Mining Lease Area 415.097 ha

2. Proposed Limestone

Production capacity

1.5 Million TPA (ROM)

C. Location Details

1. Villages Devra & Kothar

2. Tehsil Rampur Baghelan & Amarpatan

3. District Satna

4. State (Madhya Pradesh)

5. Latitude & Longitude Latitude - 24° 29’55” to 24° 31’ 33” N

Longitude - 81° 07’52” to 81° 09’ 26” E

7. Toposheet No. 63 H/2

D. Cost Details

1. Total Project Cost Rs 18 Crores /-

2. Cost for Environment

Protection Measures. Capital cost – Rs. 45 Lac /-

Recurring cost- Rs. 25 Lac per annum

E. Requirements of The Project

10. Water Requirement 90 KLD

Source- Ground Water through bore wells for drinking purpose and Rain

water harvested in mine pits as and when developed.

11. Power Requirement 180 KW per Day

12. Man Power Requirement Total: 74 Persons

Source: Approved Mining Plan and SOI Toposheet

Page 6: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh

Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. UltraTech Cement Ltd. (Unit- Bela Cement Works) 2

ENVIRONMENTAL MANAGEMENT PLAN

A. Air Quality Management

Drilling

Drilling machines will be provided with wet drilling arrangements to prevent dust from

being air borne.

Blasting

Controlled Blasting will be adopted with the optimum use of explosive energy which will

help in reducing air pollution.

Water spray on blasted muck pile.

Transportation

Regular water spraying on the haul roads will be done.

Regular maintenance of HEMMs & transportation vehicles.

Water sprinkling during loading unloading at transfer points.

Greenbelt Development & Plantation

Green belt development & Plantation will be carried out in & around mining lease area as

per guidelines.

Periodic air quality monitoring will be carried out.

B. Water Quality Management

No waste water will be discharged outside ML Area.

Waste water from workshop will be treated using Oil – Water separator and treated

water will be used in equipment washing, dust suppression, etc.

Domestic wastewater generated from mines office will be disposed off in soak pit via

septic tank.

Garland drain having siltation pits will be provided at the toe of the dumps, to channelize

the runoff water from dumps into the water reservoir (i.e. mined out pits) & around the

active pits to restrict rainy water from entering in to the working pit.

Retaining walls having water holes will be provided along the toe of the dumps to avoid

the soil wash out & around the active pit to prevent fall of human/animal in to the

working pit.

Periodical monitoring of Ground water level & quality will be carried out regularly.

Page 7: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh

Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. UltraTech Cement Ltd. (Unit- Bela Cement Works) 3

C. Noise Level Management

Controlled Blasting will be adopted. Blasting to be done during day hours only.

Use of sharp drill bits during drilling activities.

All mines employees will be provided with earplugs/earmuffs.

Proper maintenance, oiling and greasing of machines will be done to reduce generation

of noise at regular intervals.

Periodical monitoring of noise will be done.

Development of green belt &plantation around lease boundary, roads and other places

will be carried out.

D. Greenbelt/ Plantation

At conceptual stage total excavated area will be 300.214 ha, out of which 199.761ha will

be backfilled and reclaimed by plantation and rest 100.479 ha will be converted into water

reservoir.

Greenbelt will be developed on 7.5 m statutory barrier all along the lease boundary.

Plantation will be done on safety zone of roads, backfilled area etc.

Native species will be planted as per the advice of Forest Department, (M.P.)

2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION

(i) IDENTIFICATION OF PROJECT AND PROJECT PROPONENT

IDENTIFICATION OF PROJECT

M/s UltraTech Cement limited (Unit: Bela Cement Works) has proposed a project of Bela Cement

Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production

Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh Cu.M Overburden at Village- Devra, Tehsil-

Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

IDENTIFICATION OF PROJECT PROPONENT

• UTCL is the largest Cement producer in India with the production capacity of 93 Million TPA.

Its operations span across India, UAE, Bahrain, Bangladesh and Sri Lanka.

• It has 18 Integrated cement plants, 1 clinkerisation plant, 31 grinding units, one white cement

plant and 7 bulk terminals in India.

• The Premium Brands comprise of - UltraTech Cement, Birla Super, UltraTech Concrete, Birla

super ready mix concrete, Birla white & Birla wall care putty.

Page 8: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh

Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. UltraTech Cement Ltd. (Unit- Bela Cement Works) 4

(ii) BRIEF DESCRIPTION OF THE NATURE OF PROJECT

M/s. UltraTech Cement limited (Unit: Bela Cement Works) has its existing Integrated Cement

Plant of 2.5 Million TPA Capacity located at Jaypee Puram, District- Rewa (Madhya Pradesh).

In order to meet the raw material requirement (limestone) for their existing Cement plant,

M/s UTCL has proposed a captive mine i.e. Bela Cement Limestone Mine – 01 (BCLM – 01), (ML

area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and

2.575 Lakh Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar,

Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Mining Lease Status

The Letter of Intent of Bela Cement Limestone Mine – 01 (BCLM – 01) (ML area 415.097 ha) at

village- Devra Tehsil- Rampur Baghelan and village- Kothar, Tehsil- Amarpatan, District - Satna

(Madhya Pradesh) was issued in the favor of M/s Jayprakash Associates Limited vide letter no

F - 3-25/2016/12-1 dated 28.12.2016 by Dept. of Mineral Resources, M.P. Government.

Mining Plan with Progressive Mine Closure Plan approved from IBM vide letter no

MP/Satna/Limestone/MPLN/G-16/16-17/744 dated 23.02.2017.

Mining lease was granted in favor of M/s Jaiprakash Associates Limited Vide order no. F-3-

25/2016/12/1 dated 13.04.2017.

In the meantime, Jaiprakash Associates Ltd (“JAL”) and Jaypee Cement Corporation Ltd.

(“JCCL”) Business was transferred to UltraTech Cement Ltd (UTCL) by National company Law

Tribunal Bench (NCLTB) at Mumbai on 15.02.2017 in case of UTCL and NCLTB at Allahabad on

02.03.2017 in case of Sellers.

Henceforth, the Jaypee Bela Plant and Mines of M/s Jaiprakash Associates Ltd and M/s Jaypee

cement Corporation Ltd. along with all the contracts, deeds, approvals, schemes etc have

been transferred to UltraTech Cement Ltd (Unit: Bela Cement Works).

An order regarding transfer of lease from M/s Jaiprakash Associates Ltd. to UltraTech Cement

Ltd. was issued dated 08.06.2017 by Dept. of Mineral Resources, M.P. Government.

Subsequently, a deed for transfer of mining lease has been registered dated 13.07.2017 from

State Govt in favor of M/s UltraTech Cement Ltd (Unit: Bela Cement Works) for Bela Cement

Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) at Village- Devra, Tehsil- Rampur

Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh). The

relevant documents regarding the same are enclosed as Annexure II.

Page 9: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh

Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. UltraTech Cement Ltd. (Unit- Bela Cement Works) 5

Screening category of Project

As per EIA Notification dated 14th September, 2006 as amended from time to time, the project

falls under Category “A”, Project or Activity 1(a) – 3.

(iii) NEED FOR THE PROJECT & ITS IMPORTANCE TO THE COUNTRY AND OR REGION

M/s. UltraTech Cement limited (Unit: Bela Cement Works) has its existing Integrated Cement Plant

of 2.5 Million TPA capacity located at Jaypee Puram, District- Rewa (Madhya Pradesh).Therefore,

in order to meet the raw material requirement (limestone) for their existing Cement plant M/s

UTCL has proposed a new project Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area

415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575

Lakh Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil-

Amarpatan, District-Satna (Madhya Pradesh).

The proposed project will prove beneficial in terms of socio-economic development as it will

create employment opportunities to locals. Further, the average income level, which is the

indicator of socio – economic status of households is expected to increase, which will ultimately

result in better standard of living of the local people. With respect to the importance of the

project to the nation, it can be well said that in a developing nation like India, cement makes a

backbone for infrastructural development. Thus, keeping in mind this requirement, mining of

limestone is necessary for the nation’s growth.

(iv) DEMAND – SUPPLY GAP

Limestone produced from the limestone mine will meet the requirement/demand of limestone for

the Cement Plant of M/s UltraTech Cement Ltd. (Unit- Bela Cement Works)

(v) IMPORTS VS. INDIGENOUS PRODUCTION

Limestone produced from the Bela Cement Limestone Mine – 01 (BCLM – 01) will be used for

captive purpose in the existing Cement Plant of Bela Cement Works.

(vi) EXPORT POSSIBILITY

Limestone produced from Bela Cement Limestone Mine – 01 (BCLM – 01) will be used for captive

purpose in the Cement Plant of Bela Cement Works. There is no possibility of export of mineral

from the proposed mining project.

(vii) DOMESTIC/EXPORT MARKETS

Limestone produced from Bela Cement Limestone Mine – 01 (BCLM – 01) will be utilized for

captive use in the cement plant. Thus, there will be no other users for the limestone produced

from this mine.

Page 10: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh

Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. UltraTech Cement Ltd. (Unit- Bela Cement Works) 6

(viii) EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT

The total manpower for this mining project will be 74 persons. Preference for employment will be

given to locals as per their eligibility & qualification. However, the project will also generate

indirect employment opportunities for the locals.

Table -2 Details of Manpower

S .No Particulars Proposed

1 Managerial 08

2 Supervisory 06

3 Skill Operators 31

4 Maintenance 12

5 Semiskilled 06

6 Unskilled 08

7 Secretariat and General 03

Total 74

Source: Approved Mining Plan and PMCP

3.0 PROJECT DESCRIPTION

(i) Type of Project Including Interlinked And Independent Projects, If Any:

M/s. UltraTech Cement Limited has a proposal for Bela Cement Limestone Mine – 01 (BCLM – 01)

with proposed Production capacity of 1.5 Million TPA (ROM) and 2.575 Lakh Cu.M Overburden at

village- Devra Tehsil- Rampur Baghelan, and village- Kothar, Tehsil- Amarpatan, District - Satna

(Madhya Pradesh).

Interlinked Project: M/s. UltraTech Cement limited (Unit: Bela Cement Works) has its existing

Integrated Cement Plant of 2.5 Million TPA capacity located at Jaypee Puram, District- Rewa

(Madhya Pradesh).

(ii) Location (map showing general location, specific location, and project boundary &project site

layout) with coordinates

Location details

Villages: Devra & Kothar

Tehsil: Rampur Baghelan & Amarpatan

District: Satna

State: Madhya Pradesh

Latitude: 24° 29’55” to 24° 31’ 33” N

Longitude: 81° 07’52” to 81° 09’ 26” E

Toposheet no. : 63 H/2

Page 11: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh

Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. UltraTech Cement Ltd. (Unit- Bela Cement Works) 7

LOCATION MAP

Figure 1: Location Map showing general location, specific location, project boundary & project site layout

Page 12: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh

Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. UltraTech Cement Ltd. (Unit- Bela Cement Works) 8

(iii) Details of alternate sites considered

As this is a site specific mining project and the lease has been granted by State Govt after detailed

prospecting. No alternative sites are considered.

(iv) Size or Magnitude of Operation

Proposed Limestone Mining Project (Area: 415.097 ha) with Production capacity of 1.5 Million TPA

(ROM) at village- Devra, Tehsil - Rampur Baghelan and village - Kothar, Tehsil- Amarpatan, District-

Satna (Madhya Pradesh).

(v) Project Description with Process Detail

A. Local Geology

Bela Cement Limestone Mine – 01 (BCLM – 01) falls in Bhander series of Upper Vindhyan System.

The limestone deposit of area belongs to Nagod Limestone Formation

Rock types of the study area

The sequence of rock types found in the mining lease area is as follows:

Overburden soil

SirbuShale

Upper Magnesium Shale (Cap Rock)

Upper grey limestone

Middle Shale

Nodular Shale

Lower grey limestone

Cherly Limestone

Lower Magnesium Limestone.

On the basis of field observation made during course of geological traverses it can be inferred that:

The limestone band which occurs in area forms a part of slightly elevated land mass as UGL.

The UGL formation is mostly concealed beneath the soil and UMS formation.

The older rocks like shale etc are not exposed in area & are covered under thick overburden.

B. Details of Mining

The Method of Mining will be Open Cast Working with formation of benches by fully mechanized

means by deploying Heavy Earth Moving Machineries. The formations encountered in the area

comprise of soil, Upper Magnesium Shale (UMS), Upper grey Limestone (UGL), Middle Shale

(MSH), Nodular Shale (NDS), Lower grey Limestone (LGL), Cherty limestone (CHL) and Lower

Page 13: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh

Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. UltraTech Cement Ltd. (Unit- Bela Cement Works) 9

Magnesium Limestone (MGL). Out of these formations, UGL formation has been considered

under the category of reserves at this stage. The overlying formations such as Soil & Upper

Magnesium Shale (UMS) have been treated under the category of overburden. It is planned to

operate each formation separately as an independent unit. The OB will be handled in the form of

Soil and UMS by developing two separate benches.

The OB soil cover is soft in nature and will be handled by Dozer but UMS is hard in nature so will

be handled separately by drilling and blasting. The limestone thickness at proposed pit location is

10 to 15.5 m which will be mined out by developing two benches.

During initial mine opening, mine development will be taken up and OB will be removed to expose

limestone formation. During five year of mining OB bench will be developed in OBS & UMS. The

OB removed from the area shall be put as temporary dump for first five years of mining.

The material will be loaded into dumpers with the help of Hydraulic Excavators and then will be

transported to Crusher (located at Cement plant), stockyard through well maintained haul roads.

The total excavation details are given in Table No-3.

Table -3

Excavation Details

Year Total tentative

Excavation (Cu.m.)

Top Soil (Cu.m.)

OB/SB/IB (Cu.m.)

ROM ROM: Waste ratio

Ore (Cu.m.)

Mineral Reject

(Cu.m.)

Total ROM (MT)

ROM after 15% recovery loss

1st 30000 30000 0 0 Nil 0 0 Nil

2nd 130000 30000 0 100000 Nil 250000 212500 1:0.12

3rd 240000 40000 0 200000 Nil 500000 425000 1:0.08

4th 557500 100000 157500 300000 Nil 750000 637500 1:0.35

5th 747000 48000 99000 600000 Nil 1500000 1275000 1:0.10

Total 1704500 248000 256500 1200000 Nil 3000000 2550000 1:0.17

Source – Approved Mining Plan along with Progressive Mine Closure Plan; Page No. 29

(vi) Raw Material required Along With Estimated Quantity, Likely Source, Marketing Area ofFinal

Products, Mode of Transport of Raw Material and Finished Product

This is a Limestone mining project hence no raw material will be required.

Limestone will be used in captive cement plant, so no marketing area of final product will be

required.

Excavated limestone will be transported to crusher (located at cement plant), stockyard

through well maintained haul roads by dumpers.

(vii) Resources Optimization/ Recycling and Reuse Envisaged in the Project, if any, should be briefly

Outlined.

No waste water is being/ will be discharged outside the Mining Lease Area.

Page 14: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh

Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. UltraTech Cement Ltd. (Unit- Bela Cement Works) 10

Oil – Water separator will be provided at the workshop and treated water is being re-cycled

for equipment washing and dust suppression, etc.

Top soil will be utilized in land reclamation and for plantation purpose.

(viii) Availability of Water, Its Source, Energy /Power Requirement and Source

A. Water Requirement

The total water requirement will be 90 KLD. Out of which the drinking & sanitation water

requirement of 10 KLD will be met from ground water (borewells) and remaining requirement of

80 KLD from rain water stored in mine pit as and when developed.

Table -4

Water Requirement

S.

No. Water Requirement

Total

Requirement

(KLD)

Source

1. Dust suppression 30 Rain water

harvesting pit as

and when

developed.

2. Workshop – HEMM

washing 10

3. Greenbelt 40

4. Drinking & Sanitation 10 Ground water

from Bore wells

Total 90

Source: Approved Mining Plan and PMCP

B. Power Requirement

Total Power requirement for proposed limestone mining will be 180 KW which will be sourced

from Captive Power Plant & MPEB.

(ix) Quantity of Waste to Be Generated (Liquid and Solid) And Scheme for Their

Management/Disposal

A. Liquid

Domestic Waste water generated from mine office will be disposed off in soak pits via septic

tank.

Oil – Water separator will be provided at the workshop and treated water will be re-cycled for

equipment washing and dust suppression etc.

B. Solid

The proposed working area is covered by soil and hard overburden.

During first five years of mining operations the estimated quantities of generation of OBS

(Soil) and Hard OB (UMS) are 248000 m3 and 256500 m3 respectively.

Topsoil will be stacked separately and will be utilized for plantation.

Page 15: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh

Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. UltraTech Cement Ltd. (Unit- Bela Cement Works) 11

Hard O.B. will be temporarily dumped at earmarked sites as per approved mining plan and will

be backfilled in the mined out area and reclaimed by plantation.

No external dumps are proposed in the area.

4.0 SITE ANALYSIS

(i) Connectivity

The site is well connected with nearest town/city Rewa. NH-75 is about ~0.5 km in SSW direction

from mine site. NH- 7 is about ~2.1 km in SE direction from mine site. Nearest Town/city is Rewa

about~10 km in ENE direction from mine site. Nearest railway station is Turki road at ~ 3.8 km in

NNW direction. The nearest airport is Allahabad at ~120 km in NE direction. The site is well

connected with the communication facilities such as telephone, telefax and internet.

(ii) Land Form, Land Use and Land Ownership

The total Mining lease area is 415.097 ha, out of which Government land is 14.204 ha and Private

Agricultural Land is 400.893 ha.

(iii) Topography& Drainage

The terrain is sloppy with some gentle undulations. In general area is flat topography and

elevation of the area varies from 310 to 328 MRL. The general RL of the area is 319 MSL.

The area is drained by seasonal & small streams located in the area. They are charged in rainy

season and flows towards downstream and meet Kariari Nadi and Bihara Nadi both flowing

towards North and ultimately meet River Tons.

(iv) Existing Land Use Pattern {Agriculture, Non-Agriculture, Forest, Water bodies (Including Area

Under CRZ)}, Shortest Distances From The Periphery Of The Project To Periphery Of The Forests,

National Park, Wild Life Sanctuary, Eco Sensitive Areas, Water Bodies (Distance From The HFL Of

The River), CRZ. In Case Of Notified Industrial Area, A Copy Of The Gazette Notification.

There is no National Park, Wild Life Sanctuaries, Biosphere Reserves, Tiger Reserves, and Wildlife

Corridors etc. within 10 km radius of the mining lease area.

Details of Environmental settings around the project site are given in the table below:

Page 16: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh

Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. UltraTech Cement Ltd. (Unit- Bela Cement Works) 12

Table -4

ENVIRONMENTAL SETTINGS DETAILS

S.No. Particulars Details

1. National Park, Wild Life

Sanctuaries, Biosphere Reserves,

Tiger Reserves, Wildlife Corridors

There is no National Park, Wild Life Sanctuaries, Biosphere

Reserves, Tiger Reserves, and Wildlife Corridors etc. within 10 km

radius of the mining lease area.

2. Reserved/ Protected Forests Sathari RF (~7.8 km in NNW direction)

3. Water bodies There is no perennial water body flowing through ML Area.

Kariari Nadi (~3.2 km in North direction)

Canal (~5.2 km in North direction)

Dharm Sagar (~3.2 km in East direction)

Chanduwa Nala (~6.3 km in East direction)

Dhirma Nala (~6.1 km in NE direction)

Rani Talab (~8.3 km in East direction)

Semar Talab (~3.7 km in ESE direction)

Lilji Nadi (~5.2 km in SE direction)

Juru Nallah (~7.0 km in WSW direction)

Guru Talab (~6.2 km in SW direction)

Rani Talab (~7.1 km in SSW direction)

Kollaha Talab (~4.2 km in SW direction)

4. Nearest Town/ City Nearest Town/city: Rewa (~10 km in ENE direction).

5. Nearest Highway NH-75 (~0.5 km in SSW direction)

NH – 7 (~2.1 km in SE direction)

Panna Khajurao Road passing through the lease area.

One village road between Devra and Narora is also passing

through the area.

6. Nearest Railway Station Turki Road railway station (~ 3.8 km in NNW direction)

7. Nearest Airport Allahabad Airport (~120 km in NE direction)

Khajuraho Airport (~128 km in WNW direction)

9. Seismic Zone Zone – II as per IS: 1893 (Part-I) : 2002

Page 17: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar,

Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. Ultra Tech Cement Ltd. (Unit- Bela Cement Works) 13

Figure -2: Map showing Environmental Settings of the study area

Page 18: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh

Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. UltraTech Cement Ltd. (Unit- Bela Cement Works) 14

(v) Existing Infrastructure

The site is well connected with nearest town/city Rewa. NH-75 is about ~0.5 km in SSW direction

from mine site. NH- 7 is about ~2.1 km in SE direction from mine site. Nearest Town/city is Rewa

about~10 km in ENE direction from mine site. Nearest railway station is Turki road at ~ 3.8 km in

NNW direction. The nearest airport is Allahabad at ~120 km in NE direction. The site is well

connected with the communication facilities such as telephone, telefax and internet.

(vi) Soil Classification

The area mainly consists of Black Cotton Soil.

(vii) Climatic Data from Secondary Sources

The area is having Tropical climate with maximum temperature 45° C and minimum 2.5° C. Rainfall

starts from mid-June to mid-September. The dry wind blows NW & NE with high velocity at times.

Humidity varies from 30-70 %.

(viii) Social Infrastructure Available

Nearest town is at Rampur Baghelan. The area has good network of public roads. Telephone,

Electric connections, Medical facilities and Telegraph facilities are available in the area.

5.0 PLANNING BRIEF

(i) Planning Concept (Type of Industries, Facilities, and Transportation etc.) town and country

planning/development authority classification

This is a proposed limestone mining project. This is a captive mine of existing Bela Cement plant of

UTCL. Blasted limestone will be transported to crusher located at Cement plant by dumpers.

(ii) Population Projection

Temporary influx of people will be there as the managerial and supervisory staff will generally be

from outside the area.

(iii) Land Use Planning

The total Mining lease area is 415.097 ha, out of which 14.204 ha is Govt. land and 400.893 ha is

Pvt. Agricultural land. Proposed production of limestone will be in the granted mining lease area.

Land use planning for proposed project will be as per the approved mining plan.

(iv) Assessment of Infrastructure Demand (Physical & Social)

UTCL has assessed the demand of infrastructure (Physical & Social) in nearby area of the mine

site and same will be developed under ESC programmes including infrastructure development is

involved during commencement of mining.

Page 19: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh

Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. UltraTech Cement Ltd. (Unit- Bela Cement Works) 15

(v) Amenities/Facilities

UTCL (Unit: BCW) will develop Amenities/Facilities in the nearby area of the proposed mine site as

per requirement of local people of the nearby area under ESC programmes.

6.0 PROPOSED INFRASTRUCTURE

(i) Industrial Area (Processing Area)

The proposed limestone mining project involves some of the essential mining establishment like

Mine office, workshop building, explosive magazine, rest shelters etc

(ii) Residential Area (Non- Processing Area)

The residential area is already provided in the plant.

(iii) Green Belt Development

At conceptual stage total excavated area will be 300.240 ha, out of which 199.761 ha will be

backfilled and reclaimed by plantation and rest 100.479 ha will be converted into water

reservoir.

Greenbelt will be developed on 7.5 m statutory barrier all along the lease boundary.

Plantation will be done on safety zone of roads, backfilled area etc.

Native species will be planted as per the advice of Forest Department, (M.P.)

(iv) Social Infrastructure

Proposed project will result in growth of the surrounding areas by increased indirect employment

opportunities in the region and also infrastructure development will enhance trade and

communication.

(v) Connectivity

The site is well connected with nearest town/city Rewa. NH-75 is about ~0.5 km in SSW direction

from mine site. NH- 7 is about ~2.1 km in SE direction from mine site. Nearest Town/city is Rewa

about~10 km in ENE direction from mine site. Nearest railway station is Turki road at ~ 3.8 km in

NNW direction. The nearest airport is Allahabad at ~120 km in NE direction. The site is well

connected with the communication facilities such as telephone, telefax and internet.

(vi) Drinking water management (source & supply of water)

The total water requirement will be 90 KLD. Out of which the drinking & sanitation water

requirement of 10 KLD will be met from ground water (borewells) and remaining requirement of

80 KLD from rain water stored in mine pit when developed.

Page 20: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh

Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. UltraTech Cement Ltd. (Unit- Bela Cement Works) 16

(vii) Sewerage system

The domestic wastewater generated from mine office will be disposed off in soak pits viaseptic

tanks.

(viii) Industrial Waste Management

Oil – Water separator will be provided at the workshop and treated water will be re-cycled for

equipment washing and dust suppression etc. There is no discharge of waste water outside the

mine site.

(ix) Solid Waste Management

Wastes comprise of Topsoil, O.B. (hard and soft in nature). Topsoil will be stacked separately and

will be utilized for plantation. The O.B. will be dumped at earmarked sites as per approved mining

plan and will be backfilled at the end of life of mine.

(x) Power Requirement & Supply/Source

Total Power requirement for limestone mine will be 180 KW per day which will be sourced from

Captive Power Plant and MPEB.

7.0 REHABILITATION AND RESETTLEMENT (R & R) PLAN

(i) Policy To Be Adopted (Central/State) In Respect Of The Project Affected Persons Including Home

Oustees, Land Oustees And Landless Laborers (Brief Outline To Be Given)

The total Mining lease area is 415.097 ha. No forest land is involved. This is a proposed mining

project.

8.0 PROJECT SCHEDULE & COST ESTIMATES

(i) Likely Date of Start Of Construction And Likely Date Of Completion

The project will be executed after obtaining all statutory clearances and consents from the

respective authorities.

(ii) Estimated Project Cost Along With Analysis In Terms Of Economic Viability of the Project

Capital Cost of the Project: Rs. 18 Crores /-

Cost for Environment Protection for the Project:

Capital cost –Rs. 45 Lac /-

Recurring cost- Rs. 25 Lac per annum/-

9.0 ANALYSIS OF PROPOSAL

Proposed Limestone Mining project will result in growth of the surrounding areas by increased

indirect employment in the region including ancillary development and supporting infrastructure.

Page 21: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Bela Cement Limestone Mine – 01 (BCLM – 01), (ML area 415.097 ha) with Proposed Limestone Production Capacity of 1.5 Million TPA (ROM) and 2.575 Lakh

Cu.M Overburden at Village- Devra, Tehsil- Rampur Baghelan, and Village-Kothar, Tehsil- Amarpatan, District-Satna (Madhya Pradesh).

Pre-Feasibility Report

M/s. UltraTech Cement Ltd. (Unit- Bela Cement Works) 17

Development of social amenities will be done in the form of medical facilities, education to

underprivileged children and creation of self-help groups. No major adverse effect on

environment is envisaged as the required mitigation measures are inbuilt in the project.

Page 22: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

ANNEXURE -I

KHASRA MAP

Page 23: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

18

Page 24: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

ANNEXURE -II

MINING LEASE DOCUMENTS

Page 25: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

-q-

qqqtsr gtr{f4

rilhil gT€lEr ftarrarEiTmq

,r gfl?gt :t

B+qrd Faio oB lo Gtl+pqim gtr a--25/20r6/12/1:- +*-d Eqq-rQr E-{n. ftfu. t qeT d fudr ?r?r=nd dF{ft-d ?T4gr qa,dla wi srq{q-.a' d urq -}<-u uti o-tdru d gd r+ET 415.

'er a. *s qr TilFrce'u shf, fu d-ad sfrq-sr srgifim 3mfu- 0s.0s.2017* 04.0s.206i En ftrrf srqrb rftfu frh. d qqT d ainror ftE+ qra d ft.}sB-q (+fu' q"ilq-aref ffi d anqa $ 31-ar?n 3rgq-d Trer4 !-gr a'T 3ia-{ET)Bera, 2016 + Grs-q s + Jqhqq (r) + 3rdda- furio 08.os.2orz +l6-frffi, fual woln d saeT sn*{a trqd fu-qr arqr t r

T{gd sntq-d w q'fftror}rnia efrq-g frt e)q BrqfEr eg dfrE s-qtq-areffrzrd srqrtm rft+-c frfu d qar d siol"i of srgah qEra- qff wrfr B r qasidr"t' fr-q erd d srfia *an,-

r. BrErEr dffi @-{e eg arol frbq] + si€fta +{ft sruqil o1 qr}, z+eftq+EqFrqt, slgat<a, 3rsf,rw, eftilqfuqi srlt ffi si.rt-6 drur qrq fu-qraTerT, 3{Tcrcq?F qffi z{Ed, sinfr& o} siafta d wr$-uft r

2" sidfu-s i aes-rq rqd ftF-{ft fi Efb t srfio zrsft erff s*{ aftkq} 6}ffidTr b-qr B, ffi ti g-aq q-fl d zftiE d eiazo srrqlft4 *,u-+aqgT fr sia-q"r rht dfts * fr sidtrft g{dr{gl ri6is ffi s}z zraftETfudT d ddq fr ffiq rr{-6t-{ s}E zr-q rd&Fn S sffi frry r

3idFfi w trfrRqo Etqr fu, &EtEr trgr d ffid frdqlr 3rekn tftia-s3{emr Fr+fr 3{qilr sq s}R qgq Eft riqjf flr-{r m sq*ur 3rrara: +fuEe-+ftrrd fuqr Er+drT sfu E$ ffid s{at-il GTqFd a-s fu-fl qr}anr

sidtre uqdrgr t sioEq Eft drfi-e t fr srlshqq silz g+r$ srpftq e-l}rr+ M + sqEiEl anr sffi dun I

En sIr*er d ql-$ de d F4i6 * ls F4 d 3ie-{ udqq} d srgarftra?igr€rd] d qcq * s{o-aa * slrqru qs aiafrtr srgnrEro ?+erera1 + "p

4.

t

6.

D:\ORDER 2\ORDER 2.DOCX

19

Page 26: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

Y.

+ 0.s0 qfrem t qrrqr +1 erq qfrr (upfront payment) s{fuq eq dqfl o-ga fu qiui q* odffii, fuar srqT Ara ifua of qrffirfu€ Effi6 - o fr qo B-cafu-d qiur q-+ Eft *k ft--i6 s 30 fr-d-$ +aftas si?rfrft trl{T u6 ged F+rT o1 qrffi

I

Jof€ srRr ffirrT *e + Bqrid r s Fd-$ + eiiil{ s{r{.r ?i=-6-,., Br=rai-Trmq trRI e{rrd d zroq* fuq.|o o2.or.2o1s d arrur u.D 4,us _ r d*S. q* fr ura fuors Ed sil'"d mz* o-&wc fr zner e-rareTFd fu-qrUT|eIdII I

rqlc* 6rdTer{ Bq?id 1 s fd-fi + #.,. 3idtrfi sE,. (dfrE rd-ddTefd-dileft d areqa^t *'T* $-gq-d- @rd q'r or si?,=or) ft++, 2o1G Efisrgqs - 2 * F+ ar$ qq-*..tr€'. srgtrrtr{d d{nerdl d qe-d o.soqfterd d mrq +t era sr€r d fr+ +* ,'s& d uq fr iio-* sfr+rfrqor d *s qE 6A-ffi 61 ffqTqa qftslfr Fffd qEtrTT r ?16 En_fA *_,ft-6rs Ed scnftT o-tru d Fqail E .r-T + args* diilr. ft1 GrT zrduft rft*"^- qft+& d' r&6 qiE ed d .,qdd; fu-o, qr+-4T r ffisgqrFd ?+rHT€rdT + g-daeioa qe 6; o.so qfrerd t a-.sqra qff *rfug o-oio - 7, :, s +t gF sq-tia stasaF. rr?i aidftft enr rqFq (+fuErfrq-"'af ffi s qre+a s srq?il srg{d aqq qgr ,ur gidz"T) fiqfl,2ot6 d 3Er.* - e fr qftfu qr{ fr ?f*flEf, ftres 6+ffi # oEootil r

$ ft€ 6di6 r 0 d =-dfu* ffitd ffi 6-a-ffi ai" u-qa a-fiftrqi qmr B, dq rf*r {e'.,-u grfl ft-.q.r d** eqEIqEr sidJur sT srg'}eaqrfr-d wi elq frm e-+gr Br+d,r, 'siil{"i ffi + qreaT Efl drfts rd ffi, ffi 1Md eianor ftils"frTma

gsr t r

fu€ dffin - ro fr eaaqs d sia-s"r A ftil+ ffis + ffuuwr 6; soFd fr aiq-{ sh-q (rrrang ?ren arg*+rda g.qf sffi d frr-) ftqrq_dftqa{, 2016 o1 srgqff - i a B+ dT+ qq{ d sffifi d srer ErqqqETfute h-#€z dnr lMa fo-qr qrlunr

10.

11.

12.

r3.

a.r

D3\ORDER 2\ORDER 2TDOCX

20

Page 27: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

14' sffift 6) shq .*frE r=i"T{ ffi d *y * srqer 3rg.dT EcrqRi#RP' 2016 + a#.;;*" (t). (z), i.), (+) ei

qqq*fl-d il-qqrd S arer *aor enterrgsru

f

O.e. #umeleras gF+Eqolro ffi, gfuq +rrqq f,{srTur

ailqrd, Fai6-_ o8/o c.lt+

\4.

gtvd fteilTr

D:\oRDER z\oRDER 2.DOCX

21

Page 28: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

22

Page 29: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

23

Page 30: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

24

Page 31: CONTENT LIST - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/Online/TOR/31_Dec_2017...CONTENT LIST S. NO. CONTENTS ... SCHEME FOR THEIR MANAGEMENT/DISPOSAL 10

25