1 CONTRACT AND CONTRACT DOCUMENTATION COURSE WORK REVIEW OF DOCUMENTS NEEDED IN SITE ORGANISATION DATE: 28 MARCH 2012
Oct 30, 2014
1
CONTRACT AND CONTRACT DOCUMENTATION COURSE WORK
REVIEW OF DOCUMENTS NEEDED IN SITE ORGANISATION
DATE: 28 MARCH 2012
CTM 3
RAMAT SEGHOSIME 3262909
KELVIN BOATEY 3259409
LESLIE KOOMSON 3260409
ASUMADU-BOATENG GIDEON 3258809
DEREK NANA SAM- AMOAH 3262709
MOHAMMED SAYIBU 3261009
2
TABLE OF CONTENT
EXECUTIVE SUMMERY......................................................................................4
INTRODUCTION................................................................................................5
SETTING OUT OF SITE.......................................................................................5
a. SITE INVESTIGATION REPORT..............................................................5
b. SITE LAYOUT PLAN...............................................................................7
MANAGEMENT OF SITE...................................................................................7
a. WORKS PROGRAMME.........................................................................8
b. WORK SCHEDULE................................................................................9
c. SITE SECURITY.....................................................................................5
d. TIME KEEPER......................................................................................10
e. ACCOUNT MANAGMENT...................................................................11
f. CONTRACT DOCUMENT....................................................................12
g. STORE MANAGEMENT.......................................................................14
h. HEALTH AND SAFETY..........................................................................18
i. HEALTH AND SAFETY MANUAL..............................................20
ii. HEALTH AND SAFETY DIARY..................................................21
iii. ENVIRONMENTAL MANAGEMENT PLAN..............................22
BILL OF QUANTITIES..........................................................................23
INTERIM PAYMENT CERTIFICATES....................................................24
MATERIAL AND LABOUR SCHEDULES...............................................25
PROGRESS REPORT...........................................................................27
WORK MANAGEMENT..................................................................................29
a. COMFIRMATION OF VERBAL INSTRUCTIONS...................................31
b. VARIATION OF INFORMATION.........................................................31
c. REQUEST OF INFORMATION............................................................31
d. SITE DAILY REPORT...........................................................................32
e. WEATHER REPORT...........................................................................37
CONCLUSION...............................................................................................38
REFERENCES................................................................................................39
3
EXECUTIVE SUMMERY
WE WERE TASKED TO HIGHLIGHT ON THE DOCUMENTS NEEDED FOR THE ORGANIZATION OF A SITE TO ACHIEVE
EFFICIENCY IN PROJECT MANAGEMENT. IN THIS DOCUMENT ARE THE VARIOUS DOCUMENTS NEEDED FOR
SETTING OUT A SITE AS WELL AS MONITORING AND CONTROLING WORKS.
THE FIRST SECTION DESCRIBES THE DOCUMENTS NEEDED IN SETTING UP A SITE, HOW THEY ARE USED AND WHO
GETS TO USE IT. IT INCLUDES TEMPLATES TO FURTHER EXPLAIN ITS STRUCTURE.
THE SECOND PART HIGHLIGHTS ON THE DOCUMENTS NEEDED FOR THE CONTROL AND MONITOR OF SITE
ACTIVITIES TO ENSURE THE EFFICIENCY OF THE PROJECT.THIS SECTION ALSO INCLUDE TEMPLATES OF THE
MENTIONED DOCUMENTS.
WE ARE POSITIVE THIS DOCUMENT WILL BE UNDERSTANDABLE TO THE AVERAGE READER AND WILL ENLIGHTEN
YOU ON THE GENESIS AND REVELATION OF SITE ORGANIZATION.
REFERENCES HAVE BEEN PROVIDED AT THE END OF THE TEXT FOR FURTHER READING.
4
INTRODUCTION
A project is a temporary endeavour undertaken to create a unique project or service. All projects have
three common objectives namely scope, time and cost. One common feature of industrial project is the
actual work (fulfilment phase) must be conducted on a site that is exposed to public gaze, usually
remote from the contractors head office. Construction projects are example of individual projects. A
construction site could have a permanent location or mobile in the construction of linear structure e.g.,
railway, sewer, transmission line etc. in both instances the site organization is required. The main idea
behind the organization of a site is to ensure efficiency in production/construction to meet
stakeholder’s expectations of the time, cost, scope and quality.
A site is officially handed over to the contractor by the consultant after a contract has been
established thus after signing of the contract document. Site organization is in two main parts;
Setting out the site
Managing the site
Each stage of site organization requires a set of documents/information to facilitate its execution.
SETTING OUT THE SITE
Site layout can be defined as site space allocation for material storage, working areas, units of accommodation,
plant positions, general circulation areas, and also access and egress for deliveries and emergency services. The
building site has to be carefully controlled so that:
The operatives of construction have the right machinery in the most advantageous position.
The materials stored with care so that they are readily available and not interfering with general
site circulation.
Adequate storage spacing for construction materials on site.
Site accommodation and complete facilities for construction workforce.
It is important to acquire the knowledge of the project site before setting out the site layout. The knowledge about the project site can be obtained from:
Site investigation
Contract Document
5
Information from Local Authority
SITE INVESTIGATION; Site investigation helps the Contractor to examine site conditions with regards to on-site
and off-site access, road and rail facilities, distances involved and bridge weight or height limitations on approach
routes. It also gives information on the topography and soil conditions to aid in the drawing of a layout plan.
Local vandalism and pilfering records need for night security and fencing hoarding requirements is sought to
prevent trespassing and to protect people in the vicinity. Availability of local trade and specialist contractors,
local rates of pay and facilities to be provided e.g. Site accommodation, catering, health and safety equipment,
availability and adequate power and water supplies together with rates of payment and services already
available on site, diversion required and the time involved in carrying out any necessary diversion.
CONTRACT DOCUMENTS; Information obtained include:
Plant Schedule: This can be prepared in the form of a bar chart and method of statements showing the
requirements and utilization on which will help in deciding the right equipment and the space for plant
accommodation will be needed on site.
Material Schedule: The basic data can be obtained from the bill of quantities. The contractor can predict
the delivery periods and the amount or size of the site space and/or accommodation required.
Labour Summary: Basic data obtained from the bill of quantities and pre-tender bar chart programmed
to establish the number of sub-contract trades required. Also the quantity and type of site personnel
accommodation required.
LOCAL AUTHORITY
The detail planning of construction application is necessary for authority approval from the planning, highways,
building departments, Permission to develop the project site.
The main items in a site layout design include;
Building/Structure under construction
Main equipments(cranes, concrete mixer)
Auxiliary plants, yards, workshops
Stores and deposits
Sanitary/ welfare rooms and buildings
6
Electric power and water supply
Storm-water drainage, dewatering
Waste/ contaminated water treatment sewer
Below is an example of a site layout plan.
The planning of a site layout in practice will depend upon a number of factors such as the time and money. The
need for careful site layout and site organization planning becomes more relevant as the size and complexity of
the construction operation increases, and especially where spare site space is very limited.
MANAGEMENT OF SITE
After the setting out of the site actual work commences. Several documents are needed for the purpose of
monitoring and control of project objectives thus time, scope and budget. Others rather spell out rules
and strategies to protect operatives, the environment and to ensure quality standards. Examples of some
of the documents which monitor and control scope include the following.
7
WORKS PROGRAMME
A works programme lists all project activities stating their respective start and finish time. It
communicates to stakeholders both internal and external what needs to be done at any given time. The
nature and amount of information provided in a works programme is dependent on the size of project
and group communicating to. Programmes are usually presented in the form of a Gantt chart for easy
communication. It easily indicates the milestones within the project as well as activity dependencies. An
example of a works programme can be seen below. Works programme is prepared by the estimator or
the planner and is used by all project participants. It requires regular updates as works progresses to
communicate work done and work yet to be completed. Programmes are also updated when variations
are made.
8
WORKS SCHEDULE
A plan becomes a schedule when resources are introduced. A works schedule is a document which lists
the various activities within a project with their respective start and finish time as well as the party
responsible for its execution. This is prepared by the Planner or the Estimator to communicate who
does what and when on site. Information provided here is dependent on what it is meant for.
WORKS SCHEDULE
Project Name: ____________________________________ Project Number: _______________
Prepared By: _____________________________________ Date: ________________________
ITEM ACTIVITY RESPONSIBLE
PARTY
START DATE COMPLETION
EARLIEST LATEST EARLIEST LATEST
APPROVED BY................................................ DATE...........................................
SIGNATURE..........................................
9
SITE SECURITYSite security is an important aspect of risk management on building sites. Security is required to prevent
theft and vandalism, and to keep unauthorised persons off the site. In the organisation of site, it
important to involve security due to materials that are being purchased and left on site, site security
usually contains the guards and other workers involved in the entrances of the site.
The common document used in the entrances of the site is the visitor’s record book, which keeps track
Of all the non-employees going in and out of the site, this book consist of the name of the visitor, the
person been visited, time in and time out. In some cases where there are no appointment between the
visitor and the employee, some site tends to use a request form from the visitor in order to make sure
the employee has enough time to see the visitor.
Time Keeper
The work of a time keeper is to record the number of hours been spent by the employees, in this
department they make use of record books or attendance book, one of these book are for daily signing
in and out of workers which consist of their name and signature in and out, each worker has a book or a
card that document the number of hours spent in a day, which is cumulated to month. In some
companies the workers are been paid by the number of hours spent in a month, therefore this records
are needed by the account office in other to pay the workers monthly.
10
ACCOUNT MANAGEMENTThis department involves the accountant and other people involve with keeping record the money used
and kept at the site, these consist of the payment, petty cash used within and out of the site.
Some of the documents used in this department are payment vouchers books, receipts books, purchase
requisition books, cash requisition books, petty cash book, suppliers records etc.
The payment voucher is used to keep records of any payment made in the site;
the receipt is used to keep records of money receive within the site
the cash requisition books is used to request for any amount of money for the site for different
purpose, it also keep information about why the amount of money is needed. Petty cash book records
little money spent on site, for record purpose of details about every amount spent.
PAYMENT VOUCHER
Pay…………………………………………………………………………………………………………………………………………
Amount in words …………………………………………………………………………………………………………………
Debit account ……………………………………………………………………………… PV No…………………………….
DATE DETAIL OF SERVICE UNIT PRICE AMOUNT
TOTAL GH ȼ
Cash/cheque No: ………………………………………………………………………..
11
Passed for payment by: ……………………………………………………………… Received by
(Accountant)
Approved by: ……………………………………………………………………………… ……………………………
(Managing Director)
Date: …………………………………………………………………………………… Date: ………………………………
Contract Documents
After Bills of quantities has been priced and acceptance and agreement letter have been signed, a bid
document becomes a contract document. Construction contract documents are a group of document
mostly arranged in order of importance which forms the basis of a contract. These documents are the
main documents needed for the running of a project. Arranged in order of priority is as follows;
Cover page
Agreement letter
Letter of acceptance
Form to tender/Contractor’s tender
Contract data/Appendix to tender
Conditions of particular application
Conditions of contract
Special specifications and general specifications
Drawings
Bills of Quantities
Other relevant documents to the contract
Cover page: It bears the intentions of the Client and lists the stakeholders involved
Letter of Agreement: This document officially formalises a construction contract after signatures of the
parties has been signed. It also states the nature of work to be done as well as the agreed price for
execution.
12
Letter of acceptance: This is a letter written to the Contractor to inform him that his offer has been
accepted.
Form to tender: This document shows the amount the Contractor is willing to execute the project for.
The amount stated in this document is considered as the official construction cost. Note that this
amount is written and signed by the Contractor.
Contract data: It lists the key conditions/components and other important clauses binding on the
various stakeholders.
Conditions of particular application (COPA): These are the conditions applicable to that contract. It is a
revised general condition to suite existing conditions.
Conditions of contract: These are standardised conditions accepted for all construction projects.
Example is FEDERATION INTERNATIONALE DES INGENIEURS-CONSEILS (FIDIC) and PINK. FIDIC is for civil
works as PINK is to building works.
Special specifications: These are specifications applicable to the particular project.
General specifications: These are general specifications required for that category of projects.
Drawings: Drawings form part of construction documents. E.g. block plan structural drawings etc.
Bills of Quantities: This is the corrected bills of quantities of the successful bidder. This section is of two
parts-the Preliminaries and the measured works. The preliminaries section of the BOQ contains
particulars of the type of contract in use and details of general matters that affect the whole project.
The measured section contains items of work described and quantified in a manner to facilitate pricing.
Others
Under this section is relevant information relating to the contract mostly documents to be produced by
the Contractor. Examples are
Programme of works
Power of Attorney
Method statement
Copy of performance bank guarantee/insurance bond.
13
STORE MANAGEMENT
Store management is concerned with ensuring that all the activities involved in storekeeping and
stock control are carried out efficiently and economically by those employed in the store.
The various items and materials received into, housed in and issued from Stores are commonly
referred to as being ‘stock’ (or ‘inventory’).
The need for a store as far as effective site organization is concerned is they ensure accurate records
and prevent unnecessary losses due to pilfering, theft, damage or deterioration. They also hold
reserves of goods until they are required for use. A construction company or industry must hold
stocks of all the items (materials, tools, equipment and components): which are used in the
organization
The success of an enterprise depends to a large extent on the efficient management of its Store and
stocks. Efficient store management involves receiving materials in to the store, ensuring the safety
of all items and materials whilst in the Store - that is, protecting them from pilfering, theft, damage
and deterioration; as well as issuing items and materials, including their inspection, monitoring
those movement and maintaining full records of the items in the Store;
The following documents are used in efficient store management;
The stock in book – for receiving materials into the store
14
NAME OF MATERIAL: MONTH: 200313
EXCESS/ SHORTAGE IN QUANTITY DELIVERED
SOURCE/SUPPLIERDRIVERS
NAME
THIS SHORTAGE SHOULD BE CLEARLY INDICATED UNDER THE REMARKS COLUMN OF THAT PARTICULAR TRANSACTION.
DATE
NB:IN THE EVENT THAT THERE IS EXCESS OR SHORTAGE IN THE QUANTITY DELIVERED OF ANY MATERIAL THE STORE KEEPER MUST NOTIFY THE APPROPIATE AUTHORITY BY MEANS OF A MEMO
DRIVERS SIGNATURE
OPENNING STOCK
CUMULATIVE QUANTITY
NAME OF RECIPIENT
SIGATURE OF RECIPIENT
REMARKWAY BILL/
INVOICE No.VEHICLE
No.QUANTITY AS PER WAYBILL
ACTUAL QUANTITY RECEIVED
STOCK IN LEDGER
The stock out book – for issuing materials out of the store
NAME OF MATERIAL: MONTH: 100313
REMARK
NB:IN THE EVENT THAT THERE IS EXCESS OR SHORTAGE IN THE QUANTITY DELIVERED OF ANY MATERIAL THE STORE KEEPER MUST NOTIFY THE APPROPIATE AUTHORITY BY MEANS OF A MEMO
DATE REQUISITION NO. PURPOSE OF ISSUE/USAGEACTUAL QUANTITY
ISSUED SIGNATURE OF
ISSUERCLOSING
STOCKNAME OF
ISSUEROPENNING
STOCKNAME OF RECIPIENT
SIGATURE OF RECIPIENT
STOCK OUT LEDGER
15
Waybill – for transferring goods from one site to another
WAYBILL NO:
Name: Date:
Address:
Vehicle No: Driver's Name:
QTY DESCRIPTION REMARKS
Received in good order and conditions:
Dispatched by By………………………
Driver's
signature Signature:
Date Date:
A waybill or consignment note is a document issued by a carrier giving details and instructions
relating to the shipment of a consignment of goods. Typically it will show the names of the
16
consignor and consignee, the point of origin of the consignment, its destination, route, and method
of shipment, and the amount charged for carriage
Contract name: Inspection Date:
Completion to satisfaction Comment/ Signature of Signature of of client Yes/No Remark Contractor Client
Defects List prepared by:
Contractor's representative(name and signature):
Client's representative(name and signature):
DEFECTS LISTBVL 061
Location Description of defect
Document №
17
HEALTH AND SAFETY
Occupational health should aim at: the promotion and maintenance of the highest degree of
physical, mental and social well-being of workers in all occupations; the prevention amongst
workers of departures from health caused by their working conditions; the protection of workers in
their employment from risks resulting from factors adverse to health; the placing and maintenance
of the worker in an occupational environment adapted to his physiological and psychological
capabilities; and, to summarize, the adaptation of work to man and of each man to his job-WHO.
The documents used to ensure the health and safeties of workers on site are:
HEALTH AND SAFETY MANUAL
This is a manual provided by a firm, listing its ways and means of tackling any related health and
safety issues on site .It varies from one firm to the other .It is used on each project undertaken by a
particular firm. This forms part of the administration of the firm on site. It draws down the safety
measures and procedures the firm takes on site. It serves as a guidebook that shows who is in
charge and what to do when related issues are encountered on site. It includes precautions workers
18
Material Consumable Report
BVL 005Weekly report from site
from Saturday
to Friday
Reference Description
Date Sitein out
W/bill RMN
Code UnitQ.ty
Amount Remarks
may take to ensure their safety.eg putting on helmets in site. The H&S manual applies to every
person involved in the construction be it on site or in an office.
The purpose of an H&S manual is to prepare individuals involved in case of any emergency.
A typical H&S manual outlines the following task for individuals involved:
Contractor:
Are to follow Contractor Control procedures;
Must adhere to the firm’s emergency procedures;
Must attend to any training required to ensure a safe and healthy environment exists for all;
Must apply all emergency training, equipment and information supplied for relevant tasks;
Must know emergency routes;
Must report any emergency control problems to the firm’s management.
Supervisory Staff/Site Engineer
Must ensure comprehension of, and adherence to, all emergency regulations relevant to the
site;
Emergency training is to be carried out so as to empower the site's personnel to work as a
team in an emergency procedure;
Must gather feedback from the employees on emergency controls;
Must ensure reciprocal feedback from management to employees is given within a
reasonable time;
Must ensure grievance and disciplinary procedures regarding emergency controls are
adhered to;
Must consult with firm’s General Manager if emergency control issues are out of the
supervisor's control.
Employees/labourers19
Must apply all emergency training, equipment and information supplied for relevant tasks;
Must know emergency routes;
Must be able to locate and use emergency equipment relevant to their department;
Must assist the firm’s management to meet regulation, standards and codes of practice;
Must ensure grievance and disciplinary procedures regarding emergency control hazards are
adhered to;
If any emergency control problems are identified, the employee must bring these to the
attention of their supervisor.
One major aspect of an H&S manual is training. This is used to equip the personnel involved with
the necessary skills on how to tackle H&S issues that occur at the workplace. E.g. of training include
the timely identification of need for first aid assistance, and location of first aid trained personnel
and first aid kits.
A typical training aspect of an H&S outlines the following:
All employees shall be appraised in emergency control competencies on induction to their
job. At induction and refresher training, all the employees shall receive training covering the
following areas:
Overview of emergency problems in industry generally;
The effect of emergencies on the body and mind;
Explanation of the risk factors;
Summary of the legislative approach;
Hierarchy of control measures and options for control of risk;
Emergency programmes;
Specific emergency control requirements/procedures in their work area, and their work in
general.
Such training will take into account any emergency issues identified in the work method
statements relevant to the job description;
Special note will be made of any emergency exposure already identified as being of a high risk nature,
especially exposure involving high-risk individuals (for example: fire in the kitchen);
20
All personnel must be made aware of grievance and disciplinary procedures regarding H&S
manual, and emergency controls in particular;
All employees shall receive training appraisal at least annually, and where identified, receive
refresher and/or additional training to meet any changed circumstances.
HEALTH AND SAFETY DIARY/RECORDS
This is a site document used in keeping records of all health and safety issues that have occurred on
site such as accidents, injuries, fire etc. This is in a format, which is filled with short detailed notes
on H&S issues that occur on site. This is a private document since they can be medical reports of the
staff.
SITE ACCIDENT REPORT-MONTHLY
PREPARED FOR_____________
PREPARED BY______________
SITE/CONTRACT____________ DATE____________
1 NUMBER OF PERSONNEL(average on site) THIS PERIOD OVERALL
2 NUMBER OF ACCIDENTS REPORTED(requiring an employee to be absent from work for more than 3days)Accident types:a)Persons falling-from scaffolds ,ladders ,roofs etcb)Fall of materials onto personsc)Excavations or tunnel collapsed)Cranes ,hoists ,transport or other plante)Powered hand toolsf)Ordinary hand toolsg)Strains, twisth)Striking or abrasions on objectsi)Burns, scalds or electric shocksj)Others
FATAL NON FATAL
FATAL NON-FATAL
…………….. …………….. …………….. ……………..
…………….. …………….. …………….. ……………..
…………….. …………….. …………….. ……………..
…………….. …………….. …………….. ……………..
3 NUMBER OF MINOR ACCIDENTS(where employees did not have to stay off work more than 3 days)
…………………………………………………………………………
21
4 NUMBER OF SITE MAN-HOURS WORKED …………………………………………………………………………
5 NUMBER OF HOURS LOST BECAUSE OF ACCIDENTS
…………………………………………………………………………
SIGNED: _______________
SITE SUPERVISOR________
NOTE: Accident numbers extracted from the ACCIDENT BOOK.FORM 31510 and from ACCIDENT
ENVIRONMENTAL MANAGEMENT PLAN (EMP)
EMP provides a systematic framework and approach to minimize risks and control environmental
aspects (i.e. activities that cause impacts) and impacts (i.e. effect of change to the environment
resulting from an activity).
The EMP provides a description of the methods and procedures for reducing and monitoring
environmental impacts. The EMP also contains environmental objectives and targets which the
project proponent or developer needs to achieve in order to reduce or eliminate negative impacts.
The EMP document can be used throughout the project lifecycle. It should be regularly updated to
remain aligned with the project as it progresses from construction to operation and, finally to
decommissioning.
Three broad categories of EMPs can be recognized in the project lifecycle. They are the construction
phase EMP, the operational phase EMP and the decommissioning phase EMP.
The objectives of these EMPs are all the same, namely to:
* identify the possible environmental impacts of the proposed activity; and
* develop measures to minimize, mitigate and manage these impacts.
The difference between these EMPs is related to the difference in mitigation actions required for
the different stages of the project cycle.
22
BILL OF QUANTITIES
A quantity surveyor prepares the bill of quantities and manages all costs relating to the building
projects, from the initial calculations to the final figures. Surveyors seek to minimize the costs of a
project and enhance value for money, while still achieving the required standards and quality. Many of
these are specified by statutory building regulations which the surveyor needs to understand and
adhere to.
A quantity surveyor may work for either the client or the contractor, working on site or in an office.
Purpose of a Bill of Quantities
Once a contract is awarded, the priced bill of quantities provides:
1. The means by which the works can be valued and paid for during construction.
2. Materials schedule are prepared from the BOQ as well as labour schedule.
3. Depending upon the form of contract that is used, the basis for determining the changes in
prices arising from changes to the scope of work or delays and disruptions.
4. Basis for the preparation of certificate of payment.
Below is an example of the measured section of the Bills of Quantities.
ITEM DESCRIPTION QUANTITY UNITRATE(¢)
AMOUNT(¢)
INTERIM PAYMENT CERTIFICATES
The INTERIM PAYMENT CERTIFICATES are documents stating the amounts which shall be paid to
the Contractor in a period of time stated in the contract other than the final payment certificates. They
23
are called interim because they can be revised in any other future INTERIM PAYMENT CERTIFICATE up
until the Final Payment Certificate.
APPLICATION AND ISSUE OF INTERIM PAYMENT CERTIFICATES
The INTERIM PAYMENT CERTIFICATES are the certificates issued by the consultant, based on the
Contractor's Interim Payment Applications. The contractor’s application for an intern payment
certificate must be accompanied by such evidence of the work done as the client or client’s
representative or consultant may require. As the consultant will need to satisfy itself as to whether the
amount applied for is fair and reasonable in all the circumstances, it should specify in advance what
documentary and other evidence it will require to accompany the application in order that it may be
certified. This may include copies of invoices, detail of hours worked by the various grades of
employees, etc. If the contractor by its application is making a claim for additional payment, then it
must provide the particulars necessary to enable the consultant to assess the claim. The consultant is
entitled to satisfy itself that the payment is in fact due. E.g. the consultant is entitled to reimbursement
by the consultant of import duties paid for importation of a plant into the country where the site is
located. Receipts for the payments made must be provided.
Within each contract there will be clauses which set out the criteria under which interim
payments will be made and the timing of these payments. Paying the INTERIM PAYMENT CERTIFICATES
after this period stated in the contract entitles the contractor to be paid financial charges for the
amount not paid. This period of time in which the INTERIM PAYMENT CERTIFICATES are to be paid is
included, usually, in the Appendix to Tender or in Contract Data, and is named, in some forms of
contracts, the PERIOD FOR HONOURING CERTIFICATES. Basically construction contracts commonly
provide for “progress payments”, based on “interim payment certificates” issued by an agent of the
employer (often an architect, engineer or other professional) as the work proceeds.
It is a matter of fact whether payment for work carried out is a statement of acceptance or
approval. Most contract provisions for interim certification and payment are based on cumulative
valuation of work done, and are only for payments on account. They are neither binding nor conclusive
of acceptance of the work. In other words, it certifies the value of the work done; it doesn’t prove that
the contractor has complied with all the terms of the contract. The employer is still free to raise issues
of defective work or any other breach of contract.
24
LABOUR AND MATERIAL SCHEDULES
This process requires constant monitoring to ensure efficient work practices. It is important to record
and track costs as they are incurred.
Labour and material schedules can be used for ordering as part of monitoring of a building project.
The building contract is the starting point for finding information about materials and labour to be used
on a project.
The information in the contract provides details of what is needed for the project. Everything is written
down so that the client and the builder are both clear about the expected outcome of the project. This
reduces the chance for uncertainty or disputes which can lead to delays.
Theses schedules can be used to track materials and labour required for each task. Too much
information on the schedule would make it too difficult to read. Information on when labour and
materials are needed is critical to the success of a project. This kind of information is often tracked on
call forward sheets.
Material Schedules
The material schedule contains information on the supplier, quantity and cost of materials needed for
the project. This is important for preparing purchase orders. The basic data can be obtained from the
bill of quantities. The contractor can predict the delivery periods and the amount or size of the site
space and/or accommodation required
Specialised material such as doorknobs from Italy may take weeks to arrive. Call forward sheets can be
used to show when materials need to be ordered to make sure they are on-site when required.
The timing of the delivery of materials is important to avoid too much material cluttering the site and
making it difficult to work, but on the other hand material schedules makes sure materials are there
when they are needed.
MATERIALS SCHEDULE/REQUISITION
25
Contract: No:
Job no: Date:
Prepared by:
Bill/programme
ref.
Description Quantities Delivery Remarks/Diagrams
Labour Schedules
A labour schedule shows the timing of the physical working hours of staff and sub-contractors.
The information about sub-contractors may be included in the labour schedule to ensure it is quickly
and easily accessible. It also helps to identify if workers for any specific work needed to be done on site.
PLANT AND EQUIPMENT SCHEDULE/REQUISITION
Contract: No:
Job no: Date:
Prepared by:
Plant type and
equipment
Dates Required Plant hire
firm/supplier
Remarks
Date on-site Date off-site
26
PROGRESS REPORT
This is a written document unleashing the work accomplished in a construction project during a specific
period of time. It could be a daily report, monthly report etc. depending on the requirements of the
contract and organizations associated with the project.
In short this is a document that records everything that has to do with job progress on site so that work
on site will be conducted properly to ensure that it is completed at the right time, quality and the within
the accepted budget.
The document is consequential piece which communicates to other stakeholders on the advancement
made i.e. whether work is on course or behind schedule. It could also be an important piece in tracking
activities and making references.
27
Project Status Report BVL 053
Period under review Start End
Site
Site Sup: Site Manager's Name
Task under review
-from project construction programmer-Ref.
Schedule
Previous Actual Schedule
Task….
Issues:
Prepared by: Signed by:
28
WORK MANAGEMENTThis part of the site is consist of the site engineers, mason, and labours and the document used within
themselves as record and documentation of work done for a certain period of time
CONFIRMATION OF VERBAL INSTRUCTION
Under the JCT 2005 Standard Building Contract there is the facility for instructions to be issued
orally by the architect/contract administrator as well as in writing. In this situation the contractor is to
confirm the oral instruction (more commonly referred to as a verbal instruction) to the
architect/contract administrator within seven days of receiving the verbal instruction. If the
architect/contract administrator does not dissent from that confirmation within seven days from
receipt of the written confirmation, the instruction then takes effect. Oral confirmation sheets (also
referred to as confirmation of verbal instruction, or CVI sheets) are frequently used by contractors
operating under this (and similar forms of contract. When the Contractor requests confirmation of
agreements and instructions developed in negotiation with the Owner. Agreements must be able to be
quantified using existing contract procedures and will, in the vast majority of cases, not impact contract
time and cost. When time and/or cost are impacted, they must be clearly spelled out in the COVI.
29
VARIATION OF INFORMATION30
COMPANY NAME
Confirmation of Verbal
Instruction (CVI)NO_
Project No.
Project Name
CVI number
Work section
Date
Detail of Verbal Instruction given
Oral Instruction Issued By:
Sketch here if required
Signed on Behalf of Client: …………………………………
Signed on behalf of consultant …………………………………
Variations to a contract may be additions to or deductions from the works to be executed.
Variations are generally requested by the client or the architect but may be generated by the builder
due to unforeseen circumstances or at the request of the principal certifying authority. It is preferable
to have variations approved prior to their execution. Variation may in two forms either minor or major.
A minor variation is a minor modification, addition, or variation to a building consent that does deviate
significantly from the plans and specifications to which the building consent relates. A Major variation is
one which makes major modifications to the building, there increasing the cost significantly. Keep track
of any variations that might occur whether major or minor variations are made. This might have an
enormous effect on the cost of the structure. As they say “little drops of water make a mighty ocean”.
Variations are submitted by the contractor to the client who in turn approves it for work to proceed.
REQUEST FOR INFORMATION
The construction documents (agreement, drawings and specifications) developed by the Engineer,
document the conditions agreed upon between the Owner and the Contractor. These documents
reflect the understanding that each party has with regard to constructing the Project they represent. If
every set of Construction Documents were clear, unambiguous, and complete, interpretation would be
unnecessary, as the intent and understanding of the parties would be self-evident. Unfortunately, this is
not always the case. In most Construction Documents, it is inevitable that the agreement, drawings, and
specifications will not adequately address every single matter. There may be gaps, conflicts, or subtle
ambiguities. The goal of the Request for Information (RFI) is to act as a partnering tool to resolve these
gaps, conflicts, or subtle ambiguities during the bidding process or early in the construction process to
eliminate the need for costly corrective measures. Should the response to the RFI lead to additional
work during the construction process that represents added value, which cannot be reasonably worked
out in the early stages of the performance of the work, than a formal claim can be made? The general
contractor submits the request and the architect responds to the request.
31
DAILY SITE REPORT
Day–to-day records of Project activity and progress are extremely important. The Project Manager
(PM) is responsible for ensuring Project Records are kept, and that they are accurate and adequate
records of the progress of the Project. It is very important to record each day. Work and the resources
used for activities especially those that are impacting the Project schedule. This needs to be done daily.
It is often beneficial to augment the record of events or situations with sketches, pictures, videotape
recordings, or other methods. On large Projects, each Inspector assigned to a major operation must
keep a separate General Daily Progress Report or diary. The PM and other key Project personnel must
record Project information, including:
Weather, Contractor personnel, and Equipment (including a list of Equipment down time and
Subcontractors).
Location and description of the Work and estimated quantities performed that day.
Arrivals and departure of major Equipment.
Condition of traffic control and Roadway. Also record significant changes or problems with
traffic control and devices.
Significant communications with the Contractor, especially those pertaining to Work schedule,
Work methods, Materials, or payment.
Orders and directives given the Contractor. The PM must also send a memo or letter to confirm
significant verbal instructions or agreements.
References to significant letters, minutes of meetings and attendees, reports, photographs,
telephone conversations, etc.
Disagreements with the Contractor over Work quality or performance, including rejected Work
or Materials. List reasons for disagreement, and specific reasons why Work and/or Materials
were rejected.
Delays, difficulties, accidents, Utility damages, and other unusual conditions. Describe factors or
conditions that may hinder the Contractor’s operations and cause delays. Also include the time
of suspending or resuming Work and explanations.
Comparison between scheduled Work activities (from Contractor’s schedule) and actual Work
activities. Explain differences.
32
Significant visits or communications within Agency or with FHWA, Utilities, local officials, or
property owners.
Days or periods when no Work is in progress or no Work was accomplished and reasons why.
The diaries and daily or other reports are meant to supplement each other and do not need to contain
identical information. The daily diaries and reports are considered public records. Include only factual
information in them. Do not include personal remarks and opinions regarding operations and/or
personnel on the Project.
Submit the original General Daily Progress Reports and Project Manager Diaries with the final Project
documentation. Arrange the reports in chronological order and assemble them into pads.
33
34
Site Diary BVL 007
Project No. Weather
Project Name Morning Afternoon
Client
Labour Force BVL SUBs Delays, Hindrances, Disruption encountered today
Foremen
Headmen
Masons
Carpenters
Steel benders Alterations or additions requested (stated by Whom)
Labourers
Plant opt and mates
Drivers
Painters
Plumbers Other relevant recordings for the day
electricians
Security
Office staff
Description of Work Commenced
Description of Work Completed
Instruction
From
Drawings
From
DAILY SITE REPORT 1000051
LOCATION
:DATE:
STOPPIN
G TIME
NO_ OF
WORKERS
MATERIAL
USED
PLANT/
EQUIPMENT USED WEATHE
R
COMMENT
SCATEGORY
NO
_
TYP
E
QT
YTYPE HOURS
35
OFFICE
USE
ONLY
CHECKED BY
………………………………………………. REMARKS ………………………………………………………………….
(PE/QS) (PM)
WEATHER CHART
Weather is one major concern during construction. It can make or break a project. If the project will be
on going during the rainy season here in Ghana, one must be very careful when mixing concrete,
because the concrete might end up with higher moisture content than needed. Which is not good for
36
concrete, this is where the weather chart comes into play. The weather chart will be able to forecast
the type of weather that is expected maybe for the coming month. This will help the engineers to plan
as to how they are going to go about doing the work. They will be able to know which days it will not
rain so that if any concrete work must be down it might be done on that day.
CONCLUSION
Relay of information is very important in projects and therefore effective communication is essential in
its organization. To reduce the risk of litigation within contracts, all information is to be documented
and the above documents exist to check that.
REFERENCES
Modern Construction management. By; Frank Harris and McCaffer 5th Edition
Construction Technology. By; Roy Chudley, Roger Greeno. 3rd edition
PMP Project Management Professional Study Guide. by Joseph Phillips
37