Top Banner
Chapter 9 Chapter 9 Estimating, scheduling Estimating, scheduling and budgeting and budgeting
30

Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Mar 31, 2015

Download

Documents

Deanna Hayhurst
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Chapter 9Chapter 9Estimating, scheduling and Estimating, scheduling and

budgetingbudgeting

Page 2: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Learning objectivesAfter reading this chapter, you should be able to:• explain the importance of project scheduling and budgeting• describe the main techniques used in estimating the duration and

cost of activities• construct and analyse project networks• draw Gantt charts and comment on their value for project control• use simple techniques to help optimise a schedule• explain the differences between top-down, bottom-up and

iterative budgeting• construct a cost breakdown structure from a knowledge of the

work breakdown structure and organisation breakdown structure• construct a time-phased project budget from a knowledge of the

project schedule, cost estimates and the cost breakdown structure• draw S-curves to graphically illustrate project cash flows

Page 3: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

The project schedule

• About sequencing project activities and milestones into a sensible and logical order to aid project execution and control

Page 4: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Estimating activity durations

• There are three ways to estimate activity durations:– Use historical data– Time the activity– Use a probabilistic method

Page 5: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Weighted average technique

• Based on three estimates of the duration of an activity, often arrived at by expert judgment:

1) Most optimistic (a) – the minimum time this activity would take to complete if everything went exactly as expected without any difficulties or problems whatsoever.

2) Most likely (m) – the most likely duration assuming normal conditions.

3) Most pessimistic (b) – the expected duration if major difficulties are encountered.

Page 6: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.
Page 7: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Defining activity dependencies and creating a project network– Sequencing activities in parallel or in a series

Page 8: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

The network diagram

A network diagram not only shows the relationships between activities but can be used to reveal which activities are time-

critical, and so warrant greater management attention

Page 9: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Activity boxes• Each activity has seven attributes:

– The activity code and name (middle row)– The estimated duration of the activity

(top row, middle)– Earliest start and finish times (top

row, left and right respectively)– Latest start and finish times (bottom

row, left and right respectively)– Float or slack (bottom row, middle)

Page 10: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.
Page 11: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Activity relationships

There are four basic relationships that can be expressed between two activities (A and B):

1. Finish-to-start

2. Start-to-start

3. Finish-to-finish

4. Start-to-finish

Page 12: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.
Page 13: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Creating a network• The most challenging aspect of creating a network is

getting the relationships between the activities defined correctly

• To begin, write out the activities on cards of Post-it notes and start arranging them to reflect the logical relationships

• Or, if you have planned similar projects before, you may have historical records that contain information about the activities you will need to perform and how they should relate to each other

Page 14: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

A network is a special chart to show the relationships between project activities.

Page 15: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

The logical relationships in a project can also be expressed in the form of a

dependency table.

Page 16: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Analysing the network to determine the critical path

• The critical path is defined as the path through the network having the longest duration

• The critical path defines the expected duration of a project

• If a critical activity overruns, the project will also overrun (unless special action is taken)

Page 17: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Activity floats

• Activities that are not critical are said to have float (or slack)

• Float = LFT – EFTor

• Float = LST – EST

• Critical activities have zero float

Page 18: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Importance of network analysis• Knowing which activities lie on the critical path

is important for the project manager and other stakeholders

• These are the activities that are most likely to cause a delay to the project schedule

• Identifying the critical path helps the project manager concentrate his or her time on areas of the project that are most likely to cause delays

• The critical path is also used to help plan and schedule resources for the project

Page 19: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Gantt charts

• Another way of representing scheduling information

• Intuitively easier to interpret than networks

• Note that:– activities are arranged from top to bottom– time is plotted to scale from left to right– activity bars begin at their earliest start

time– critical activities are highlighted

Page 20: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.
Page 21: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Milestones• Special events in the life of a project to which you

want to draw added attention to

• Events rather than activities, so they take up no time

• Normally represented on Gantt charts as a diamond and in network diagrams as elements with zero duration

Page 22: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Methods available for shortening the duration of a project:

• Project crashing

• Network re-evaluation

• Fast tracking

• Rescoping

• Increased procurement

• Lean thinking

Page 23: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Project budgeting

• Used by managers to fix in advance the resources that a project will use

• Budgets represent the planned cost of a project at inception

• Is all about allocating resources to a project– How much money (or other resources, e.g. labour)

– How much detail

• The progress status of a project cannot be determined without reference to both schedule and budget

Page 24: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

The building blocks of a budget

• Expenditures

• Revenues

• Cash flow

• A time-phased plan

Page 25: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Approaches to budgeting

• Top-down budgeting

• Bottom-up budgeting

• Iterative budgeting

• Risk and management reserve

Page 26: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Tools and techniques for cost estimating

• Analogous estimating (or top-down estimating)

• Parametric estimating

• Definitive estimating (or bottom-up estimating)

Page 27: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Cost budgeting

• Relating cost estimates to schedule and producing time-phased cost and cash flow projections– Payment milestones can be used to produce projections

of cash flow

• The WBS and OBS can be combined to form a cost breakdown structure (CBS)– The CBS forms the basis of the cost reporting structure

for the project– The building blocks for the CBS are called ‘control

accounts’

Page 28: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

The cost breakdown structure (CBS)

Page 29: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

S-curves

• Show cumulative project cost against time

Page 30: Chapter 9 Estimating, scheduling and budgeting. Learning objectives After reading this chapter, you should be able to: explain the importance of project.

Cash flow projections

• With the creation of project S-curves, cash flow analysis can be performed and the feasibility of the budget tested

• If the resulting cash flow is not acceptable, it is possible to modify the schedule– For example: by delaying or bringing forward

activities that have float