CanSat 2017 PFR: Team 2617 (Team SEDS VIT) 1 CanSat 2017 Vellore Institute of Technology Post Flight Review (PFR) Team # 2617 Team SEDS VIT
Team Logo
Here
(If You Want)
Team Logo
Here
CanSat 2017 PFR: Team 2617 (Team SEDS VIT) 1
CanSat 2017
Vellore Institute of Technology
Post Flight Review (PFR)
Team # 2617
Team SEDS VIT
Team Logo
Here
(If You Want) Presentation Outline
1. IntroductionI. Presentation Outline………………………………………………………………………….…..............2
II. Team Organization……………………………………………………………………....…………..…...5
2. Systems OverviewI. CanSat Overview.…………………………………………………………………………………….……7
II. CanSat Overall Cost…………...…………………………………………………………………………..9
III. Physical Layout…………………………………………………………………………………..…….....12
3. Concept of Operations and Sequence of EventsI. Comparison of planned and actual Con-Ops ..………………………………………...…………....14
II. Comparison of planned and actual Sequence of Events …………………………....……………..15
2Presenter: Akshay Girish Joshi CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
4. Flight Data Analysis
I. Payload Separation Altitude ..…………………………………………………………..………..…...20
II. Glide Duration …………………….……………………………………………………………………21
III. Payload sensor data plot ….…………………………………………………….……….…………....22
IV. Payload altitude plot …………………………………..………………………………………….…....23
V. Payload temperature sensor plot…………..........................................................................................24
VI. Pitot Tube data plot ..……………………………………………………………………………..........25
VII. 2 dimensional plot based on speed and heading ..……………………………………………........26
VIII. Payload solar power plot ……….…………..........................................................................................27
IX. Container pressure sensor plot …………………....……………………………………………........28
X. Container altitude plot ……….…………...............................................................................................29
XI. Container temperature plot ……….………….......................................................................................30
XII. Container battery voltage plot ….…………..........................................................................................31
XIII. Camera images ………………….…………..........................................................................................32
5. Failure AnalysisI. Identification of failures, root causes, and corrective actions..………………………………….....34
3
Presentation Outline
Presenter: Akshay Girish Joshi CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
6. Lessons LearnedI. Discussion of what worked and what didn't ………………………………………………………….36
II. Conclusions…….…………………………………………………………………………….……...…..37
4
Presentation Outline
Presenter: Akshay Girish Joshi CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
5
Akshay Girish Joshi (Team Leader)
Systems OverviewAkshay Girish Joshi Ases Akas Mishra
Sensor Subsystem Design
Aman Gupta
Descent Control Design
Roshan Murali Malhar Joshi
Mechanical Subsystem DesignKunal Pandey Ases Akas Mishra
CDH Subsystem Design
Rakshit Vig Kumar Yash
EPS DesignKumar Yash
FSW Design
Pranav NaiduRakshit Vig
GCS Design
Pranav Naidu Devesh Bajaj
CanSat Integration & Test
Roshan Murali Malhar Joshi
Mission Operations & Analysis
Ases Akas Mishra Aman Gupta
Requirements Compliance
Kunal Pandey
ManagementKunal Pandey
Pranav Naidu (Alternate Team
Leader)
Prof. Geetha
Manivasagam
(Faculty Coordinator)
Tony Mai,
Amazon Web
Services
(Team Mentor)
Presenter: Akshay Girish Joshi
Team Organization
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
Team Logo
Here
Systems Overview
Akshay Girish Joshi
Ases Akas Mishra
Presenter: Akshay Girish Joshi 6CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
7Presenter: Akshay Girish Joshi
Mission Summary
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
8Presenter: Akshay Girish Joshi
Mission Summary
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
Team Logo
Here
Presenter: Akshay Girish Joshi 9
CanSat Overview
110mm
28mm
1. Container descent control
apparatus(parachute)
2. Container with dimesions
3. Launch configuration of glider inside
container and parachute
attachment points
4. Physical layout of container with glider held
inside using rubber bands.
5. Stowed configuration dimensions
1 23
4 5
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
Team Logo
Here
Presenter: Akshay Girish Joshi 10
CanSat Overview
1. Top View of Deployed Payload(glider)
2. Base Plate (Wing deployment Mechanism)
1
2
All dimensions are in mm
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
11
Part Model Quantity Price($) Total($) Determination
Processor Arduino Pro Mini (5 V model) 2 9.95 19.9 Actual
Magnetometer, Pressure
sensor
10DOF Gyro Accelerometer Compass Altimeter
(L3GD20 LSM303D BMP180)1 9.95 9.95 Actual
Temperature sensor LM 35 2 1.05 2.10 Actual
Pitot tube(air speed sensor) HK pilot air speed sensor 1 26.03 26.03 Actual
Air pressure sensor
(container)BMP 180 1 2.66 2.66 Actual
Camera Adafruit TTL JPEG Camera 1 39.95 39.95 Actual
SD Card along with Shield 16gb SanDisk class 10 with SD Card Shield 2 7.34 14.68 Actual
XBee radios Xbee Pro S2B U.FL Connector 2 44.95 89.9 Actual
CanSat antenna FXP70 Freedom (patch antenna) 2 3.35 6.7 Actual
Audio Beacon Mini piezo buzzer 4 0.73 2.92 Actual
Altimeter( GPS) Adafruit Ultimate GPS 1 39.95 39.95 Actual
Micro DC motor Micro DC motor 1 2.94 2.94 Actual
Solar Panels(1) CIGS Solar Cloth 2 9.90 19.80 Actual
Solar panel(2) 0.6W Hard Solar Panel 1 2.14 2.14 Actual
Voltage regulator S18V20F6 1 14.95 14.95 Actual
Battery Duracell Ultra 223(CR-P2) 1 9.95 9.95 Actual
Total cost of electrical components 304.52
CanSat Overall Cost
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)Presenter: Akshay Girish Joshi
Team Logo
Here
(If You Want)
12
CanSat Overall Cost
Part Model/material Quantity Source Price($) Total($) Determination
Container (Extrusion
Molding)
Fibre Reinforced
Plastic1 Local Market 40 40 Actual
Fuselage
(Structure Material and
Fabrication via 3D Printing)
PLA 1
REALiz 3D
printers 180 180 Estimated
Parachute TARC-22 1 Fruity Chutes 35 35 Actual
Glider frame Carbon Fibre 2 Local Supplier 3 6 Actual
Sailcloth Dacron type 52 2 Local Supplier 11 22 Actual
Miscellaneous
(Hooks ,adhesives, rubber
band etc )
- - Local Supplier 50 50 Estimated
Total 333
Subsystem Price($)
Electrical 304.52
Mechanical 333
Exact Total 607.52
Margin (15%) 91.13
TOTAL 698.65
Hence the total budget of CanSat is well within the limit of
$1000 which is the competition requirement.
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)Presenter: Akshay Girish Joshi
Team Logo
Here
(If You Want)
13
Part Model Quantity Price ($) Total ($)Determinat
ion
Ground Control Station Costs
Processor Arduino Duo 1 57.90 57.90 Actual
Communication
Module Xbee Pro S2B 1 74.10 74.10 Actual
GCS Antenna HG2409PC 1 42 42 Actual
Laptop Lenovo Z50 1 620 620 Actual
Xbee Shield ModuleSain Smart 101-50-
1051 26 26 Actual
Total GCS Budget 820
Testing and Prototyping Costs
Prototyping - - 200 200 Actual
Testing- - 200 200 Actual
Total testing and prototyping cost 400
CanSat Overall Cost
Testing and
Prototyping cost
includes the
preliminary
mechanical
prototypes which
ever used for flight
test, determining
glider ratios, and
other experimental
data
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)Presenter: Akshay Girish Joshi
Team Logo
Here
(If You Want)
14
Physical Layout
Presenter: Akshay Girish Joshi CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
1
2
3
1. Container
Electronics
2. CanSat after
recovery
3. Container
PCB and
base plate
Team Logo
Here
(If You Want)
15
1. Glider with
panels
2. Glider base plate
3. Glider after
recovery
4. Glider fuselage
showing switch
button and
camera
Physical Layout
Presenter: Akshay Girish Joshi CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
1
2
3
4
Team Logo
Here
(If You Want)
Team Logo
Here
Concept of Operations and Sequence of
Events
Presenter: Akshay Girish Joshi 13CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
17
• CanSat will be inspected for
any surface abrasions,
scratches and damages.
• The solar panels will be
cleaned.
• All the on-board electrical
circuits will be verified .
• The sail material will be
checked for any rips.
• The GCS will be initiated and
the software will be checked
for proper functioning of each
sub process and the initial
FSW state will be shown on
the GCS .
• Radio communication and
sensors will be tested.
• The glider will be folded and
slid into the container and the
ejection mechanism will be set
in place.
• The parachute will be folded
and placed in the closed end of
the container opening for easy
release.
• The CanSat will be switched
ON and will start transmitting
telemetry data.
• The CanSat will be placed into
the payload section of the
rocket.
• A final system check will be
conducted through telemetry.
• The FSW state will be updated
on GCS.
• FSW will initiate its next state
and the same will be updated
on the GCS.
• CanSat will be deployed from
the rocket at 1000m and the
parachute will be inflated to
aid its descent.
Pre-Launch Activities Loading of CanSat Rocket Deployment
Presenter: Akshay Girish Joshi
Concept of Operations and Sequence of
Events(Planned)
Launch Operations
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
18
• As the CanSat attains an
altitude of 400m+/- 10m , the
FSW will go into detachment
state.
• At 400m+/- 10m the ejection
mechanism will be activated
and the glider will eject from
the container.
• If the automatic ejection
mechanism is not activated
until the glider reaches
400m+/- 10m , ejection
mechanism will be forced by
the GCS.
• The container will continue to
transmit the telemetry data for
2 seconds after the release of
the glider.
Glider Descent LandingDetachment
• Glider descent state will be
initialized on the FSW and
updated on the GCS.
• The glider wings will be fully
deployed.
• The solar panels will start
supplying sufficient power to
the system.
• The glider will start
descending in a helical path of
diameter 96.46 m.
• The FSW state will be updated
to landing. Buzzer will be
turned ON.
• Telemetry will be stopped
Presenter: Akshay Girish Joshi
Concept of Operations and Sequence of
Events(Planned)
Descent Operations
Post launch recovery
• Glider and container will be
tracked using GPS, buzzer and
fluorescent colour.
• Power will be turned off
Post flight data analysis
• Data will be retrieved from the
glider and checked for
correctness
• Corrections are made if
required
• Report is made for judges
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
19
Loading of CanSat
Presenter: Akshay Girish Joshi
Concept of Operations and Sequence of
Events(Actual)
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Pre Launch Activities
• All operations were completed as planned.
• We forgot to switch on the glider before placing it into the rocket payload section. Hence we had to
open the rocket payload again to switch the glider on(with the judge’s permission).
• The container telemetry was switched on 45min prior to the launch. Hence we received large number
of telemetry packets before launch
Launch
• The solar panels were fixed on the sail cloth using adhesive because of which the surface of the
sailcloth got hardened and it’s folding became a little difficult than how it was planned.
• All other launch operations worked as planned
Descent
• Glider wings did not fully unfold due to deformation of the spring because of its constant compression
• The helical path of the Glider couldn’t be observed due to low visibility. We couldn’t verify it using
sensor data
• Glider ejected at an altitude of 404m
• Glider telemetry stopped after 81.69sec
• Glider flight time was 81.69sec until the last telemetry data was received
• 5 images were captured but none of the images are clear. We couldn't keep a count of the images
• Telemetry packets were not received at a frequency of 1 hertz
• Apart from the specified telemetry packet, we also obtained latitude and longitude of the container
• All other operations worked as planned
Team Logo
Here
(If You Want)
20
Landing
• Because of no telemetry after 81.69sec we couldn’t track where the glider landed(although the
recovery crew recovered it afterwards).
• Received telemetry data indicate that other functions worked as planned
Post Launch Recovery
• The recovery site was deemed a dangerous zone because of the presence of poisonous snakes
hence the organizers didn’t allow us to recover the CanSat.
• We do not know if the audio beacon was activated because recovery was done by the CanSat
organisers and not our recovery crew.
• When we received the CanSat, the electronics was switched off. When we switched it on all the
electronics were working fine
Post flight data analysis
• 661 packets of container telemetry data and 35 packets of glider telemetry data were received
• Telemetry data(in csv file) and all the images were submitted to the judges in a pendrive.
Concept of Operations and Sequence of
Events(Actual)
Presenter: Akshay Girish Joshi CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
CanSat 2017 PFR: Team 2617 (Team SEDS VIT) 21
Mission Sequence of Events(Planned)
• Ground station is set up.
• Communication devices are
connected.
• Assign different roles to the
team members.
• Final inspection of all the sub
systems of CanSat.
• Measure solar intensity for
power estimates.
• Measure wind speed and
direction for landing
estimates.
• Go through pre-flight checklist
and make sure every pre-
launch requirement is met.
• Ensure that the ground station
is operational and check its
functioning.
• Check orientation of antenna
and check telemetry
transmission.
• Estimate the CanSat landing
zone.
• Seal all the electronic payload
of the glider inside the
fuselage.
• The hang glider is folded and
placed inside the container and
the ejection. mechanism is
initiated
• The CanSat is powered on.
• The CanSat is installed in the
designated payload section of
the launching rocket.
Arrival at Launch Site Pre-launch ChecksIntegration into
Rocket
Launch Day sequence of events
Presenter: Akshay Girish Joshi
Team Logo
Here
(If You Want)
22
Mission Sequence of Events(Planned)
Landing
- The telemetry is stopped after the landing of the glider
- The audio beacon is activated for detection.
- FSW state updated to Landed.
Separation & Descent
- At a height of 400m, the glider is ejected from the container and glide
within a diameter of 1000m.
- Telemetry is started and Data is received at GCS.
- The camera starts capturing images. The images are stored on the SD card
- FSW State updated to descent.
Deployment
- With the deployment of the CanSat, parachute is deployed.
- At deployment, the FSW State is updated.
Rocket Launch
- According to the information given by the sensors, the flight software state is updated when each action takes place.
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)Presenter: Akshay Girish Joshi
Team Logo
Here
(If You Want)
23
Mission Sequence of Events(Planned)
Recovery Post Flight Reporting
• Recovery of the Glider and the Container done with the help of buzzers and fluorescent colour.
• Both of them are examined for any possible damage during flight or landing.
• The SD card is retrieved from the electronic section.
• The telemetry data and images are analyzed.
• The data obtained is utilized for making a presentation.
• A presentation is given on the following day to the judges
• Telemetry data file is delivered to field judge for review
DataAnalysis
Post Launch Sequence of Events:
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)Presenter: Akshay Girish Joshi
Team Logo
Here
(If You Want) Mission Sequence of Events(Actual)
24
Arrival at launch site
• Modifications were made to the container so that edges were round and smooth and also to reduce
the weight further to stay within the safe weight limit.
• Telemetry was rechecked and it was made sure that electronics was working fine
• Weight check verified that the weight of our CanSat was 502g. The CanSat passed the fit test. The
tests were done in time.
• The power bus of the solar panels were tested and verified
Pre launch checks
• All crews successfully proceeded with the sequences
• The GPS got fix after 23 sec
Integration into rockets
• CanSat was powered on and placed into the rocket payload section.
• FSW 0 state was initiated
Rocket launch
• The launch took place approximately 45min after placing the CanSat into the rocket payload section
Deployment
CanSat separation was successful from the rocket and the parachute was successfully deployed
FSW state was updated
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)Presenter: Akshay Girish Joshi
Team Logo
Here
(If You Want) Mission Sequence of Events(Actual)
25
Separation and descent
• GCS crew was able to collect telemetry
• Telemetry plotting was shown to the judges
• FSW state was updated
Landing
• Telemetry stopped before landing because of which we couldn’t track the location of the CanSat
Post Launch
---Recovery
Recovered by CanSat organizers
---Data Analysis
SD card was retrieved from the fuselage and the telemetry data was submitted to the judges in a pen
drive
---Post flight reporting
The data obtained is used to analyse the failures and prepare the PFR.
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)Presenter: Akshay Girish Joshi
Team Logo
Here
(If You Want)
26
Concept of Operations and Sequence of
Events
Presenter: Akshay Girish Joshi
Sr.
NoName Position/Role(on launch day)
1 Akshay Girish Joshi Allocating tasks to the crew members and overseeing all operations
2 Pranav Naidu GCS Setup. Post flight recovery and analysis of flight data
3 Ases Akas MishraFinal mechanical systems check before loading the CanSat in the
rocket payload section
4 Roshan Murali Descent Control Module inspection
5 Kumar Yash Antenna construction on the launch day
6 Aman GuptaTelemetry data transmission check. Electrical systems check before
launch
7 Malhar JoshiCanSat recovery and extraction of SD card and submission to the
ground control
Team Members roles and responsibilities on launch day
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
Team Logo
Here
Flight Data Analysis
27CanSat 2017 PFR: Team 2617 (Team SEDS VIT)Presenter: G Pranav Naidu
Team Logo
Here
(If You Want)
28
Payload Separation Altitude
Presenter: G Pranav Naidu CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
The ejection took place at 404m. The microcontroller on the container was coded in such a way
that the container telemetry stops as soon as ejection takes place
Hence we can assume that last telemetry value of the container is where the ejection took place,
i.e. 404m
Team Logo
Here
(If You Want)
29
Glide Duration
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Although we were able to get the glider telemetry successfully at first, however as the glider
descended, a gradual decrease in the solar intensities were observed. Hence as result at the
height of 281.3m the glider could not transmit anymore telemetry data due lack of power.
Therefore only 81.692 seconds of glide time could be observed.
Presenter: G Pranav Naidu
Team Logo
Here
(If You Want)
30
Payload Sensor Data Plot
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
The Pressure observed was almost
constant at 235 Pascal
Hence very less increase with
respect to height was observed
Presenter: G Pranav Naidu
Team Logo
Here
(If You Want)
31
Payload Altitude Plot
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
A clear decrease in the height is evident as the glider descends.
Presenter: G Pranav Naidu
Team Logo
Here
(If You Want)
32
Payload Temperature Sensor Plot
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
The Temperature observed was
between 26-28 Celsius.
A clear increase in the
temperature was observed as
the glider descended.
Presenter: G Pranav Naidu
Team Logo
Here
(If You Want)
33
Pitot Tube Data Plot
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
The pitot tube value was
consistently between 4-5 m/sec
Presenter: G Pranav Naidu
Team Logo
Here
(If You Want)
34
2 Dimensional Plot Based On Speed And
Heading
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)Presenter: G Pranav Naidu
The heading data was inaccurate
because of which we couldn’t properly
locate the position of the glider on the
field.
Team Logo
Here
(If You Want)
35
Payload Solar Power Plot
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
The voltage reading was
almost consistent at 5V
with minimum variation in
the voltage reading
Presenter: G Pranav Naidu
Team Logo
Here
(If You Want)
36
Container Pressure Sensor Plot
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
The Pressure observed was
almost constant at 235 Pascal
Hence very less increase with
respect to height was observed
Presenter: G Pranav Naidu
Team Logo
Here
(If You Want)
37
Container Altitude Plot
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
The clear and sharp
increase in the height of
the altitude can be
observed as the rocket
ascends upwards.
Presenter: G Pranav Naidu
Team Logo
Here
(If You Want)
38
Container Temperature Plot
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
The Temperature
observed was between
26-28 Celsius.
A clear decrease in the
temperature was
observed as the rocket
ascended.
Presenter: G Pranav Naidu
Team Logo
Here
(If You Want)
39
Container Battery Voltage Plot
CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
The voltage reading
was almost consistent
at 4-5V with minimum
variation in the voltage
reading
Presenter: G Pranav Naidu
Team Logo
Here
(If You Want)
40
Camera Images
Presenter: Akshay Girish Joshi CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
Team Logo
Here
Failure Analysis
Presenter: Akshay Girish Joshi 33CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
Identification Of Failures, Root Causes,
And Corrective Actions
42
Failures Root Cause Corrective Actions
The folding of the glider was
difficult.
The solar panels were fixed on the
sail cloth using adhesive because
of which the surface of the
sailcloth got hardened
The flexible solar panels should
have been stitched
Glider wings did not fully unfold The spring used for folding got
deformed because of its constant
compression
A coil spring with greater angle
should have been used to
accommodate the compression.
The helical path of the Glider
couldn’t be observed
Due to low visibility. We couldn’t
verify it using sensor data
The sensor(magnetometer) should
have been properly calibrated
Glider telemetry stopped after
81.69 seconds
The glider didn’t fully unfold
because of the compression of the
spring and the hardening of the
sailcloth. Hence the flexible solar
panels couldn’t fully unfold and
perform to its full capacity
Proper unfolding should have
been ensured
Presenter: Akshay Girish Joshi CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
Identification Of Failures, Root Causes,
And Corrective Actions
43
Failures Root Cause Corrective Actions
Telemetry packets were not
received at a frequency of 1
hertz
Due to difference in sampling
rate of sensors we couldn’t give
a proper delay interval in our
code
A sensor specific delay should
have been implemented instead
of a fixed delay
We couldn’t track where the
glider landed
Because of no telemetry after
81.69sec
Proper unfolding should have
been ensured to receive
telemetry till the end
We do not know if the audio
beacon was activated
Because recovery was done by
the CanSat organisers and not
our recovery crew.
We should have enquired if the
buzzer was working
5 images were captured but
none of the images are clear.
We couldn't keep a count of the
images
Fluctuation of voltage and
improper serial communication
between the primary and the
secondary arduinos(Arduino for
camera)
Proper unfolding of the glider
should have been ensured for
maximum solar power output.
Presenter: Akshay Girish Joshi CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
Team Logo
Here
Lessons Learned
Presenter: Akshay Girish Joshi 35CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Team Logo
Here
(If You Want)
45
Discussion Of What Worked And What
Didn't
Presenter: Akshay Girish Joshi CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
What worked
All components were properly sized for release and operations.
• Glider was deployed properly
Ejection of glider took place within the specified altitude
• Glider had a controlled descent; it did not lose its stability and maintained a
steady descent till 81.69 sec(observed)
• Sensors mostly worked as planned with data logged and telemetry transmitted
successfully.
• CanSat was recovered
What didn’t work
Optimum solar power output was not obtained because of improper unfolding
Telemetry of the glider wasn’t obtained till the end
Camera count wasn’t updated
Helical path couldn’t be observed
Glide duration couldn’t be calculated
Heading data was not updated
Team Logo
Here
(If You Want)
46
Conclusions
Presenter: Akshay Girish Joshi CanSat 2017 PFR: Team 2617 (Team SEDS VIT)
Launch was a success. The CanSat worked almost as expected. The team could reason out the
problems faced and understood what went wrong and how to correct them.
More thorough testing is required to ensure reliable operation. Since some testing
may be difficult or expensive to perform, more detailed mathematical analysis
could be done.
Manufacturing processes must be repeatable and fast enough to allow for thorough,
frequent, and possible destructive testing.
Greater effort spent in the initial design phase contributed to good performance of
the CanSat system despite less than optimal testing.
Because of early research all the work was completed in proper deadline. Though availability of
some parts posed a great challenge in our country, we somehow managed to arrange for all the
parts in the required time.