SHORTAGE MATERIAL for SHIPMENT NO : T1-4 IMIR NO-104 For DECL Materials checked and recieved on behalf of BGRESL For TPCIL THERMAL POWERTECH CORPORATION 3X660MW - SUPERCRITICAL THERMAL POWER PROJECT, NELATU INCOMING MATERIAL INSPECTION & HANDING SUPPLIER'S NAME Donfeng Electric Corporation Limited IMIR No & Dt. P.O NO & Dt. TPCIL/DECL/WO-2744787 PACKAGE CONTRACTOR BGR Energy systems Ltd., Shop IR No. 4th SHIPMENT SHORTAGE MATERIAL SL NO Original Packing No DRAWING NO Description Quantity(Nos) Shipment no 1 114N5113-192 1 1 T1-8 2 114N5113-123 1 1 T1-8 3 114N5113-64 1 4 114N5113-39 1 1 T1-8 5 NUT M24 25 T1-9 6 NUT M22 5 T1-9 7 M24X120 25 T1-9 8 M24X110 2 T1-9 9 M24X100 25 T1-9 10 1000X484X30mm 1 T1-9 11 Bends 135°- Ø26.8 30 T1-9 12 Ø33.5 : L6000 2 T1-9 13 1203-013 M24×220 460 T1-9 14 1203-013 M24×220 460 T1-9 Shortage qty Receive d DECL-T-001-U1-114N5113- 55/120 BEAM, L-903 H396X199X7X11, DECL-T-001-U1-114N5113- 84/120 H700 X300X10X16, DECL-T-001-U1-114N5113- 33/120 H446X199X8X12, DECL-T-001-U1-114N5113- 76/120 BEAM, L- H582X300X12X17, DECL-T-001-U1-114N512- 29/41 DECL-T-001-U1-114N511- 6/16 DECL-T-001-U1-114N511- 14/16 DECL-T-001-U1-114N511- 16/16 DECL-T-001-U1-114N512- 37/41 DECL-T-001-U1-114N5631- 13/126 DECL-T-001-U1-114N5622- 29/36 DECL-T-001-U1-114N5622- 36/36
30
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: BTG Shortage

SHORTAGE MATERIAL for SHIPMENT NO : T1-4 IMIR NO-104

For DECLMaterials checked and recieved

on behalf of BGRESLFor TPCIL

THERMAL POWERTECH CORPORATION INDIA LTD.

3X660MW - SUPERCRITICAL THERMAL POWER PROJECT, NELATURE/PYNAMPURAM(V)

INCOMING MATERIAL INSPECTION & HANDING OVER REPORT

SUPPLIER'S NAME Donfeng Electric Corporation Limited IMIR No & Dt. TPCIL/IMIR/0104/04.08.2012

P.O NO & Dt. TPCIL/DECL/WO-2744787 PACKAGE BOILER STEEL STRUCTURE

CONTRACTOR BGR Energy systems Ltd., Shop IR No.

4th SHIPMENT SHORTAGE MATERIAL

Original Packing No DRAWING NO DescriptionQuantity(Nos) RECIEPT

REMARKSPacking no

1 114N5113-192 1 1 T1-8

2 114N5113-123 1 1 T1-8

3 114N5113-64 1

4 114N5113-39 1 1 T1-8

5 NUT M24 25 T1-9

6 NUT M22 5 T1-9

7 M24X120 25 T1-9

8 M24X110 2 T1-9

9 M24X100 25 T1-9

10 1000X484X30mm 1 T1-9

11 Bends 135°- Ø26.8 30 T1-9

12 Ø33.5 : L6000 2 T1-9

13 1203-013 M24×220 460 T1-9

14 1203-013 M24×220 460 T1-9

SL NO Shortage

qtyReceived

Shipment no

DECL-T-001-U1-114N5113-55/120

BEAM, L-903 H396X199X7X11,

DECL-T-001-U1-114N5113-

1/1

DECL-T-001-U1-114N5113-84/120

BEAM, L-1902 H700

X300X10X16,

DECL-T-001-U1-114N5113-1/1

DECL-T-001-U1-114N5113-33/120

BEAM, L-5480 H446X199X8X12,

DECL-T-001-U1-114N5113-76/120

BEAM, L- H582X300X12X17,

DECL-T-001-U1-114N5113-

1/1

DECL-T-001-U1-114N512-29/41

DECL-T-001-U2-114N512-45/45

DECL-T-001-U1-114N511-6/16

DECL-T-001-U2-114N512-45/45

DECL-T-001-U1-114N511-14/16

DECL-T-001-U2-114N512-45/45

DECL-T-001-U1-114N511-16/16

DECL-T-001-U2-114N512-45/45

DECL-T-001-U1-114N512-37/41

DECL-T-001-U2-114N512-45/45

DECL-T-001-U1-114N5631-13/126

DECL-T-001-U2-114N5611-136/242

DECL-T-001-U1-114N5622-29/36

DECL-T-001-U2-114N5622-31/36

DECL-T-001-U1-114N5622-36/36

DECL-T-001-U2-114N5622-36/36

DECL-T-001-U2-114N512-45/45

DECL-T-001-U2-114N512-44/45

Page 2: BTG Shortage

SHORTAGE MATERIAL for SHIPMENT NO : T1-5 IMIR NO-0105

For DECLMaterials checked and recieved

on behalf of BGRESLFor TPCIL

THERMAL POWERTECH CORPORATION INDIA LTD.

3X660MW - SUPERCRITICAL THERMAL POWER PROJECT, NELATURE/PYNAMPURAM(V)

INCOMING MATERIAL INSPECTION & HANDING OVER REPORT

SUPPLIER'S NAME Donfeng Electric Corporation Limited IMIR No & Dt. TPCIL/IMIR/0105/04.08.2012

P.O NO & Dt. TPCIL/DECL/WO-2744787 PACKAGE BOILER STEEL STRUCTURE

CONTRACTOR BGR Energy systems Ltd., Shop IR No.

5th SHIPMENT SHORTAGE MATERIAL

Original Packing No DRAWING NO DescriptionQuantity(Nos) RECIEPT

REMARKSPacking no

1 114N5161-133 1 1 T1-9 DECL-T-001-U1-114N5161-1/1

2 114N5123-29 1 1 T1-9 DECL-T-001-U1-114N5123-1/1

3 114N5123- 42 1 1 T1-9 DECL-T-001-U1-114N5123-1/1

4 114N5123-122 1 1 T1-9 DECL-T-001-U1-114N5123-1/1

5 114N5123-125 1 1 T1-9 DECL-T-001-U1-114N5123-1/1

6 114N5123-121 2 2 T1-9 DECL-T-001-U1-114N5123-1/1

7 114N5123-86 1 T1-9 DECL-T-001-U1-114N5123-1/1

8 114N5125-209 C10 1 1 T1-9 DECL-T-001-U1-114N5126-1/1

9

DECL-T-001-U1-114N5124

114N5124-76 H496X199X9X14 1

10 114N5124-120 H700X300X10X16 1

11 114N5124-108 H496X199X9X14 1

12 114N5124-169 HN446X199X8X12 1

13 114N5124-42 H396*199*7*11 1 T1-10 DECL-T-001-U1-114N5124-1a/1

14 114N5127-16 1 T1-9 DECL-T-001-U1-114N5127-1/1

15 114N5127-21 1 T1-9 DECL-T-001-U1-114N5127-1/1

16 114N5127- 127 1 T1-9 DECL-T-001-U1-114N5127-1/1

17 114N5127-79 1

18 114N5127-100 1

19 114N5127-43 1 T1-9 DECL-T-001-U1-114N5127-1/1

SL NO Shortag

e qtyReceived

Shipment no

DECL-T-001-U1-114N5161-10/12

MIDDLE HB(TIER-III) 2C25A

DECL-T-001-U1-114N5123-12/21

MIDDLE BEAM, H200X100X5.5X8

MIDDLE BEAM, H200X100X5.5X8

MIDDLE BEAM, H200X100X5.5X8

MIDDLE BEAM, H200X100X5.5X8

MIDDLE BEAM, H200X100X5.5X8

DECL-T-001-U1-114N5123- 7/21

MIDDLE BEAM, HN446X199X8X12

DECL-T-001-U1-114N5125 - 36/41

DECL-T-001-U1-114N5124 - 14/27

DECL-T-001-U1-114N5127-24/29

MIDDLE BEAM, H300X150X6.5X9

MIDDLE BEAM, H300X150X6.5X9

MIDDLE BEAM, H300X150X6.5X9

DECL-T-001-U1-114N5127-27/29

MIDDLE BEAM, H200X100X5.5X8

DECL-T-001-U1-114N5127-15/29

MIDDLE BEAM, H300X150X6.5X9

DECL-T-001-U1-114N5127-26/29

MIDDLE BEAM, H446X199X8X12

Page 3: BTG Shortage

SHORTAGE MATERIAL for SHIPMENT NO : T1-5 IMIR NO-0105

For DECLMaterials checked and recieved

on behalf of BGRESLFor TPCIL

5th SHIPMENT SHORTAGE MATERIAL

Original Packing No DRAWING NO DescriptionQuantity(Nos) RECIEPT

REMARKSPacking no

SL NO Shortag

e qtyReceived

Shipment no

20 114N5127- 35 1 T1-9 DECL-T-001-U1-114N5127-1/1

21 1 1 T1-10 DECL-T-001-U1-114N5128-1/1 For damage

22 114N5162-129 MIDDLE HB(TIER-II) 2C25A 1 1 T1-9 DECL-T-001-U1-114N5162-1/1

23 114N5126-170 1 1 T1-9 DECL-T-001-U1-114N5126-1/1

24 114N5126- 171 1 1 T1-9 DECL-T-001-U1-114N5126-1/1

25 114N5126- 196 1 1 T1-9 DECL-T-001-U1-114N5126-1/1

26 114N5126 - 139 1 1 T1-9 DECL-T-001-U1-114N5126-1/1

27 114N5123-133 1 T1-9 DECL-T-001-U1-114N5126-1/1

28 114N5123- 9 1 T1-9 DECL-T-001-U1-114N5126-1/1

29 25 T2-3 DECL-T-OP-02-U1-PHHB3-29/30

30 M24X145- 14Nos 14 T2-3 DECL-T-OP-02-U1-PHHB3-29/30

31 M24X110 - 22Nos 22 T2-3 DECL-T-OP-02-U1-PHHB3-29/30

32 M24X90-13Nos 13 T2-3 DECL-T-OP-02-U1-PHHB3-29/30

33 M24X140 - 14Nos 14 T2-3 DECL-T-OP-02-U1-PHHB3-29/30

34 M24X90-13Nos 13 T2-3 DECL-T-OP-02-U1-PHHB3-29/30

35 45 T2-3 DECL-T-OP-02-U1-PHHB3-29/30

36 25Nos washer 25 T2-3 DECL-T-OP-02-U1-PHHB3-29/30

37 20 T2-3 DECL-T-OP-02-U1-PHHB3-29/30

38 5 5 T1-9 DECL-T-001-U1-114N5621-1/1

39 2 2 T1-9 DECL-T-001-U1-114N5621-1/1

40 PF GRATING 114N5621-147-5 Nos 5 5 T1-9 DECL-T-001-U1-114N5621-1/1

41 8 8 T1-9 DECL-T-001-U1-114N5621-1/1

42 114N5621-482 : 1No 1 1 T1-9 DECL-T-001-U1-114N5621-1/1

43 PF GRATING 114N5621-507-8nos 8 8 T1-9 DECL-T-001-U1-114N5621-1/1

44 PF GRATING 80

DECL-T-001-U1-114N5127-26/29 MIDDLE BEAM,

H446X199X8X12

DECL-T-001-U1-114N5128-21/54

114N5128-75 (supplied for

5124-57)MIDDLE BEAM,

H446X199X8X12

DECL-T-001-U1-114N5162-3/9

DECL-T-001-U1-114N5126-18/44

MIDDLE BEAM, H200X100X5.5X8

MIDDLE BEAM, H200X100X5.5X8

MIDDLE BEAM, H200X100X5.5X8

DECL-T-001-U1-114N5126-28/44

MIDDLE BEAM, H300X150X6.5X9

DECL-T-001-U1-114N5123-14/21

MIDDLE BEAM, H300X150X6.5X9

MIDDLE BEAM, H300X150X6.5X9

DECL-T-OP-02-U1-PHHB1 - 1/22

HS BOLT 10.9S M24

M24X85-15Nos & M22X60-10Nos

DECL-T-OP-02-U1-PHHB1 - 2/22

HS BOLT 10.9S M24

DECL-T-OP-02-U1-PHHB1 - 3/22

HS BOLT 10.9S M24

DECL-T-OP-02-U1-PHHB1 - 8/22

HS BOLT 10.9S M24X90

DECL-T-OP-02-U1-PHHB1 - 9/22

HS BOLT 10.9S M24

DECL-T-OP-02-U1-PHHB1 - 10/22

HS BOLT 10.9S M24

DECL-T-OP-02-U1-PHHB1 - 14/22

HS BOLT 10.9S M24

M24X110 - 13Nos, M24X80-10Nos & M22X65-22Nos

DECL-T-OP-02-U1-PHHB1 - 16/22

HS BOLT 10.9S M24

DECL-T-OP-02-U1-PHHB1 - 22/22

HS BOLT 10.9S M24

M24X100-9NOS, M24X145-6NOS &

M16X50-5NOS

DECL-T-001-U1-114N5621-034/248

PF GRATING

5 Nos shortage (114N5621-57)

DECL-T-001-U1-114N5621-039/248

PF GRATING (9 items)

114N5621-68 & 71 : Each 1No

DECL-T-001-U1-114N5621-062/248

DECL-T-001-U1-114N5621-0137/248

PF GRATING (14 items)

114N5621-398, 402, 403, 405, 410 & 411(Each

1No), 399(2Nos)

DECL-T-001-U1-114N5621-145/248

PF GRATING (8 items)

DECL-T-001-U1-114N5621-150/248

DECL-T-001-U1-114N5621-240/248

114N5621-踏步 - 80Nos shortage.

Page 4: BTG Shortage

SHORTAGE MATERIAL for SHIPMENT NO : T1-5 IMIR NO-0105

For DECLMaterials checked and recieved

on behalf of BGRESLFor TPCIL

5th SHIPMENT SHORTAGE MATERIAL

Original Packing No DRAWING NO DescriptionQuantity(Nos) RECIEPT

REMARKSPacking no

SL NO Shortag

e qtyReceived

Shipment no

45 PF GRATING 4 4 T1-9 DECL-T-001-U1-114N5621-1/1

46 9 T1-9(6Nos) DECL-T-001-U1-114N5621-1/1

47 6 T2-3 DECL-T-OP-02-U1-PHSS5-24/24

48 12 T1-9

49 Embedded parts 4

9 T1-9(5Nos)

5 T1-9

34 T1-9

DECL-T-001-U1-114N5621-248/248

114N5621-踏步 -4Nos shortage.

DECL-T-001-U1-114N5123-13/21

PLANTS (JOINT PLANTS)

JP57-4Nos, JP23-3Nos, JP51-2Nos

JP57-2Nos, JP23-1Nos

DECL-T-OP-02-U1-PHSS1-357/357

PLANK - 14 ITEMS

Pl. 14X670X710 - 6Nos shortage.

DECL-T-001-U1-114N5126-42/44

PLANKS ( 36 ITEMS)

Pl.8X140X170-2Nos(JP-27), Pl.8X210X260-

6Nos(JP-54) & Pl.10X210X420-4Nos(JP-

72)

DECL-T-001-U2-114N5129-32/32

DECL-T-OP-02-U1-PHEP1-22/34

4Nos shortage (A3074a-DJ-015-BP10-

1)

DECL-T-001-U1-114N5125-37/41

JP80-1No, JP82-4Nos, JP83-2Nos,JP72-2Nos

DECL-T-001-U2-114N5129-32/32

DECL-T-001-U1-114N5125-38/41

JP27-2Nos, JP11-1No, JP153-2Nos,

DECL-T-001-U2-114N5129-32/32

DECL-T-001-U1-114N5125-39/41

JP73-4Nos, JP11-4Nos,JP17-8Nos, JP80-10Nos & JP-89-8Nos

DECL-T-001-U2-114N5129-32/32

Page 5: BTG Shortage

SHORTAGE MATERIAL for SHIPMENT NO : T1-6 IMIR NO-0106

For DECLMaterials checked and recieved

on behalf of BGRESLFor TPCIL

THERMAL POWERTECH CORPORATION INDIA LTD.

3X660MW - SUPERCRITICAL THERMAL POWER PROJECT, NELATURE/PYNAMPURAM(V)

INCOMING MATERIAL INSPECTION & HANDING OVER REPORT

SUPPLIER'S NAME Donfeng Electric Corporation Limited IMIR No & Dt. TPCIL/IMIR/0106/04.08.2012

P.O NO & Dt. TPCIL/DECL/WO-2744787 PACKAGE BOILER STEEL STRUCTURE

CONTRACTOR BGR Energy systems Ltd., Shop IR No.

6th SHIPMENT SHORTAGE MATERIAL

Original Packing No DRAWING NO DescriptionQuantity(Nos) RECIEPT

REMARKSPacking no

1 114N543 - 48 3 3 T1-9 DECL-T-001-U1-114N543-1/1

2 H300X150X6.5X9: L2341 1

3 114N5137-126 H446X199X8X12: L511 1 1 T1-9 DECL-T-001-U1-114N5137-1/1

4 114N5137- 25 H446X199X8X12: L550 1 1 T1-9 DECL-T-001-U1-114N5137-1/1

5 114N5137- 43 H300X150X6.5X9: L1505 1 T1-9 DECL-T-001-U1-114N5137-1/1

6 3 3 T1-9 DECL-T-001-U1-114N5137-1/1

7 1 1 T1-9

8 JP 39(Pl.20mm) - 2Nos 2 T1-10 DECL-T-001-U1-114N542-1/1

9 9 10 T1-10 DECL-T-001-U1-114N542-1/1

11 (Rib 275-1No) 1 1 T1-9

12 M22X140 30 30 T1-9

13 M24X110-11Nos 11 11 T1-9

14 PL.1mm & 2mm - 397Nos 397 158 T1-9 250

15 19 16 T1-9

SL NO Shortag

e qtyReceived

Shipment no

DECL-T-001-U1-114N543-37/39

TOP BEAM - C30A 6 ITEMS

DECL-T-001-U1-114N5137-45/52

114N5137-31 ( 114N5137-21 Extra)

DECL-T-001-U1-114N5137-48/52

DECL-T-001-U1-114N5137-51/52

JP141-1No & JP232-2Nos

DECL-T-001-U1-114N541-6/12

PL. 323, 16X200X600-1No

DECL-T-001-U1-114N5133-1/1

DECL-T-001-U1-114N542-56/57

DECL-T-001-U1-114N542-57/57

(JP243-2Nos, JP240-2Nos, NP1962-2Nos, NP2269-1No,NP2274-2Nos)

DECL-T-001-U1-114N5131-33/39

DECL-T-001-U1-114N5133-1/1

DECL-T-001-U1-114N5131-38/39

DECL-T-001-U1-114N5133-1/1

DECL-T-001-U1-114N5131-39/39

DECL-T-001-U1-114N5133-1/1

DECL-T-001-U1-114N5133-1/1

DECL-T-001-U1-114N5133-31/33

(JP-124-4Nos, JP221-6Nos, JP105-3Nos, Rib278-1 No, JP36-1No)

DECL-T-001-U1-114N5133-1/1

Page 6: BTG Shortage

SHORTAGE MATERIAL for SHIPMENT NO : T1-6 IMIR NO-0106

For DECLMaterials checked and recieved

on behalf of BGRESLFor TPCIL

6th SHIPMENT SHORTAGE MATERIAL

Original Packing No DRAWING NO DescriptionQuantity(Nos) RECIEPT

REMARKSPacking no

SL NO Shortag

e qtyReceived

Shipment no

Page 7: BTG Shortage

SHORTAGE MATERIAL for SHIPMENT NO : T1-7 IMIR NO-0107

For DECLMaterials checked and recieved

on behalf of BGRESLFor TPCIL

THERMAL POWERTECH CORPORATION INDIA LTD.

3X660MW - SUPERCRITICAL THERMAL POWER PROJECT, NELATURE/PYNAMPURAM(V)

INCOMING MATERIAL INSPECTION & HANDING OVER REPORT

SUPPLIER'S NAME Donfeng Electric Corporation Limited IMIR No & Dt. TPCIL/IMIR/0107/04.08.2012

P.O NO & Dt. TPCIL/DECL/WO-2744787 PACKAGE BOILER STEEL STRUCTURE

CONTRACTOR BGR Energy systems Ltd., Shop IR No.

7th SHIPMENT SHORTAGE MATERIAL

Original Packing No DRAWING NO DescriptionQuantity(Nos) RECIEPT

REMARKSPacking no

1 FRAME BEAM 3

2 3

3 BRACINGS 3

4 6Nos BRACINGS 6

5 5

6 FRAME BEAM 3

7 FRAME BEAM 2

87

9 2

10 43

11 87

12 50

13 M24X180-2Nos 2

14 M24X95-11SETS 11

15 M24X70 - 9 SETS 9

SL NO Shortage

qtyReceived

Shipment no

DECL-T-OP-02-U1-PHSS2-228/448

A3074a-0595-FB-223 - 3Nos

DECL-T-OP-02-U1-PHSS2-237/448

A3074a-0862-SB-476 - 3Nos

SECONDARY BEAM

DECL-T-OP-02-U1-PHSS2-242/448

A3074a-0942-SC-167 - 3Nos

DECL-T-OP-02-U1-PHSS2-243/448

DECL-T-OP-02-U1-PHSS2-277/448

A3074a-0968-VB-53 - 5Nos

VERTICAL BRACING

DECL-T-OP-02-U1-PHSS2-428/448

A3074a-0603-FB-250 - 3Nos

DECL-T-OP-02-U1-PHSS2-431/448

A3074a-0661-FB-439 : 2Nos

DECL-T-OP-02-U1-PHSS2-434/448

VB129-2Nos, VB204-5Nos

VERTICAL BRACING

DECL-T-OP-02-U1-PHSS2-435/448

A3074a-0965-VB-40 -2 Nos

VERTICAL BRACING

DECL-T-OP-02-U1-PHSS2-26/26

F279-4Nos, F34-1No, F38-3Nos, F52-10Nos, F59-2Nos, F87-2Nos, X15-

4Nos, X37-1No, X38-2Nos, F161-2Nos, F182-2Nos, F184-4Nos, F198-2Nos, F227-1No, F220-2Nos, F232-

1No.

DECL-T-OP-02-U1-PHSS2-294/448

X28(9Nos), F541(2Nos), F368(2Nos), X27(12Nos), X20(2Nos), X19(4Nos),

X18(7Nos), X5(12Nos) & EXTRA : X6(7Nos) &

X16(30Nos).

DECL-T-OP-02-U1-PHSS2-295/448

A3074-F40(15Nos), F230(13Nos), F434(21Nos) & F251(1No)

DECL-T-OP-02-U1-PHHB2-2/25

DECL-T-OP-02-U1-PHHB2-7/25

DECL-T-OP-02-U1-PHHB2-18/25

Page 8: BTG Shortage

SHORTAGE MATERIAL for SHIPMENT NO : T1-7 IMIR NO-0107

For DECLMaterials checked and recieved

on behalf of BGRESLFor TPCIL

7th SHIPMENT SHORTAGE MATERIAL

Original Packing No DRAWING NO DescriptionQuantity(Nos) RECIEPT

REMARKSPacking no

SL NO Shortage

qtyReceived

Shipment no

16 M24X80 - 2 SETS 2

17 Pl.20X100X870-24Nos 24

18 PL16X330X750 - 1No 1

19 Pl.12X270X330 - 1No 1

20 1

DECL-T-OP-02-U1-PHHB2-19/25

DECL-T-OP-02-U1-PHSS2-292/448

DECL-T-OP-02-U1-PHSS2-293/448

DECL-T-OP-02-U1-PHSS2-298/448

DECL-T-OP-02-U1-PHSS2-300/448

Pl.25X80X430-1No short

Page 9: BTG Shortage

SHORTAGE MATERIAL for SHIPMENT NO : T1-8 IMIR NO-0108

For DECLMaterials checked and recieved

on behalf of BGRESLFor TPCIL

THERMAL POWERTECH CORPORATION INDIA LTD.

3X660MW - SUPERCRITICAL THERMAL POWER PROJECT, NELATURE/PYNAMPURAM(V)

INCOMING MATERIAL INSPECTION & HANDING OVER REPORT

SUPPLIER'S NAME Donfeng Electric Corporation Limited IMIR No & Dt. TPCIL/IMIR/0108/04.08.2012

P.O NO & Dt. TPCIL/DECL/WO-2744787 PACKAGE BOILER STEEL STRUCTURE

CONTRACTOR BGR Energy systems Ltd., Shop IR No.

8th SHIPMENT SHORTAGE MATERIAL

Original Packing No DRAWING NO DescriptionQuantity(Nos) RECIEPT

REMARKSPacking no

1 2Nos 2 **

2 B75 & B76 - Each 2Nos 4

3 B26-1No 1

4 B106 - 1No 1

5 7

6 114N5112 : 160 -2Nos 2

7 114N5113-175 1

8 B50, B58 - Each 1No 2

9 114N5114 - 18: 2Nos HOR. BRACING - 2C20A 2

10 114N5114-23 - 1NO HOR. BRACING - 2C20A 1

11 B3 - 1No HOR. BRACING - 2C20A 1

12 HOR. BRACING - 2C20A 2 **

13 114N5114 : B58 -2no HOR. BRACING - 2C25A 2

14 114N5114-39 & 44 HOR. BRACING - 2C25A 2 **

15 HOR. BRACING - 2C25A 2

16 B127-1NO HOR. BRACING - 2C25A 1 **

17 B110-1No shortage. 1

18 B172 - 1No 1

SL NO Shortag

e qtyReceived

Shipment no

DECL-T-001-U2-114N5112-19/46

LOWER BEAM H446X199X8X12

DECL-T-001-U2-114N5112-31/46

LOWER BEAM H300X150X6.5X9

DECL-T-001-U2-114N5112-32/46

LOWER BEAM H300X150X6.5X9

DECL-T-001-U2-114N5112-36/46

LOWER BEAM H200X100X5.5X8

DECL-T-001-U2-114N5112-37/46

114N5112 - 109, 129, 164 (EACH 1No) & 86-4Nos

LOWER BEAM H200X100X5.5X8

DECL-T-001-U2-114N5112-46/46

LOWER BEAM H200X100X5.5X8

DECL-T-001-U2-114N5113 - 25/68

LOWER BEAM H396X199X7X11

DECL-T-001-U2-114N5113 - 40/68

LOWER BEAM H200X100X5.5X8

DECL-T-001-U2-114N5114 - 2/24

DECL-T-001-U2-114N5114 - 3/24

DECL-T-001-U2-114N5114 - 5/24

DECL-T-001-U2-114N5114 - 6/24

DECL-T-001-U2-114N5114 - 9/24

DECL-T-001-U2-114N5114 - 16/24

DECL-T-001-U2-114N5114 - 21/24

114N5114- 113, 115 -1No each

DECL-T-001-U2-114N5114 - 24/24

DECL-T-001-U1-114N5136-2/29

UPPER STRUCTURE HN200X100X5.5X8

DECL-T-001-U1-114N5134-8/35

Upper steel structure H596X199X10X15

Page 10: BTG Shortage

SHORTAGE MATERIAL for SHIPMENT NO : T1-8 IMIR NO-0108

For DECLMaterials checked and recieved

on behalf of BGRESLFor TPCIL

8th SHIPMENT SHORTAGE MATERIAL

Original Packing No DRAWING NO DescriptionQuantity(Nos) RECIEPT

REMARKSPacking no

SL NO Shortag

e qtyReceived

Shipment no

19 B24, B44-1No each 2

20 114N5134 - 43 - 1NO 1 **

21 2 B18 - To be checked **

22 114N5134 - 190 1

23 114N5134-67 1 DEC SPARE

24 B9 - 1No shortage. 1

25 114N5138- 113 1

26 B18 - 1NO. 1

27 B47, B131 & EACH 2

47

28 19

29 18

30 17

31 5

32 1

33 32

34 2

35 PF Gratings 114N5621 -590 1

36 17

37 15

38 100

39 GB/T6170-2000 Nut M10 190

40 69

41 9

42 GB/T6170-2000 Nut M10 29

43 NUT - 25 Nos shortage HS BOLT M24X7525

DECL-T-001-U1-114N5134-15/35

Upper steel structure HN300X150X6.5X9(7),

DECL-T-001-U1-114N5134-16/35

Upper steel structure HN300X150X6.5X9

114N5134 - 18 & 146 : 1No each

Upper steel structure H446X199X8X12

DECL-T-001-U1-114N5134-17/35

Upper steel structure HN596X199X10X15

DECL-T-001-U1-114N5134-19/35

Upper steel structure HM582X300X12X17

DECL-T-001-U1-114N5134-23/35

Upper steel structure HN300X150X6.5X9

DECL-T-001-U1-114N5138-3/25

UPPER STRUCTURE HN200X100X5.5X8

DECL-T-001-U1-114N5138-9/25

UPPER STRUCTURE HN446X199X8X12

UPPER STRUCTURE HN300X150X6.5X9

DECL-T-001-U2-114N5111 - 35/39

JOINT PLATES, JP27 - 19NOS

DECL-T-001-U2-114N5111 - 36/39

JP39-16Nos, JP5-1No & JP13-1No

DECL-T-001-U2-114N5111 -37/39

JP49-16Nos & JP11-1No

DECL-T-001-U1-114N5611-020/242

PF Grating 114N5611- 16

DECL-T-001-U1-114N5611-148/242

PF Grating 114N5611 - 225

DECL-T-001-U1-114N5611-236/242

PF Grating 114N5611-踏步

DECL-T-001-U2-114N5621-095/248

PF Gratings 114N5621 - 269,

800X994X30

DECL-T-001-U2-114N5621-188/248

DECL-T-001-U2-114N5621-236/248

PF Grating 114N5621-踏步

800X214X30

DECL-T-001-U2-114N5621-248/248

PF Grating 114N5621-踏步

800X214X30

DECL-T-001-U1-114N562-2/2

GB/T5783-2000 Bolt M10X35 Gr8.8

GB/T95-2002 Washer Ø16

DECL-T-001-U2-114N562-2/2

GB/T5783-2000 Bolt M10X35 Gr8.8

DECL-T-001-U1-114N54-3/17

Page 11: BTG Shortage

SHORTAGE MATERIAL for SHIPMENT NO : T1-8 IMIR NO-0108

For DECLMaterials checked and recieved

on behalf of BGRESLFor TPCIL

8th SHIPMENT SHORTAGE MATERIAL

Original Packing No DRAWING NO DescriptionQuantity(Nos) RECIEPT

REMARKSPacking no

SL NO Shortag

e qtyReceived

Shipment no

44 HS BOLT M24X80

213

45 BOLT M24X90-1No HS BOLT M24X90 1

46 HS BOLT M24, M22 105

47

HS BOLT M16, M22 71

48

** indicates the material is received in good condition as packed.

DECL-T-001-U1-114N54-5/17

BOLT - 169NOS, NUT - 201NOS & WASHER-213NOS

DECL-T-001-U1-114N54-10/17

DECL-T-001-U1-114N54-16/17

BOLT M24X65-105Nos, NUT M24 - 95Nos, Washer M24-100Nos

DECL-T-001-U1-114N54-17/17

BOLT M22X65 - 44 NOS, NUT M22 - 51 NOS & WASHER -55 NOS

BOLT M16X50 - 3 NOS, NUT M16 - 3 NOS & WASHER -16 NOS

Page 12: BTG Shortage

SHORTAGE MATERIAL for SHIPMENT NO : T1-8 IMIR NO-0108

For DECLMaterials checked and recieved

on behalf of BGRESLFor TPCIL

THERMAL POWERTECH CORPORATION INDIA LTD.

3X660MW - SUPERCRITICAL THERMAL POWER PROJECT, NELATURE/PYNAMPURAM(V)

INCOMING MATERIAL INSPECTION & HANDING OVER REPORT

SUPPLIER'S NAME Donfeng Electric Corporation Limited IMIR No & Dt. TPCIL/IMIR/0108/04.08.2012

P.O NO & Dt. TPCIL/DECL/WO-2744787 PACKAGE BOILER STEEL STRUCTURE

CONTRACTOR BGR Energy systems Ltd., Shop IR No.

8th SHIPMENT SHORTAGE MATERIAL

Original Packing No DRAWING NO DescriptionQuantity(Nos) RECIEPT

REMARKSPacking no

1 2Nos 2 **

2 B75 - 2Nos 2

3 B26-1No 1

4 B106 - 1No 1

5 7

6 114N5112 : 160 -2Nos 2

7 114N5113-175 1

8 114N5114 - 18: 2Nos HOR. BRACING - 2C20A 2

9 B3 - 1No HOR. BRACING - 2C20A 1

10 HOR. BRACING - 2C20A 2 **

11 114N5114 : B58 -2no HOR. BRACING - 2C25A 2

12 114N5114-39 & 44 HOR. BRACING - 2C25A 2 **

13 HOR. BRACING - 2C25A 2

14 B127-1NO HOR. BRACING - 2C25A 1 **

15 B110-1No shortage. 1

16 B172 - 1No 1

17 B24, B44-1No each 2

18 0 **

SL NO Shortag

e qtyReceived

Shipment no

DECL-T-001-U2-114N5112-19/46

LOWER BEAM H446X199X8X12

DECL-T-001-U2-114N5112-31/46

LOWER BEAM H300X150X6.5X9

DECL-T-001-U2-114N5112-32/46

LOWER BEAM H300X150X6.5X9

DECL-T-001-U2-114N5112-36/46

LOWER BEAM H200X100X5.5X8

DECL-T-001-U2-114N5112-37/46

114N5112 - 109, 129, 164 (EACH 1No) & 86-4Nos

LOWER BEAM H200X100X5.5X8

DECL-T-001-U2-114N5112-46/46

LOWER BEAM H200X100X5.5X8

DECL-T-001-U2-114N5113 - 25/68

LOWER BEAM H396X199X7X11

DECL-T-001-U2-114N5114 - 2/24

DECL-T-001-U2-114N5114 - 5/24

DECL-T-001-U2-114N5114 - 6/24

DECL-T-001-U2-114N5114 - 9/24

DECL-T-001-U2-114N5114 - 16/24

DECL-T-001-U2-114N5114 - 21/24

114N5114- 113, 115 -1No each

DECL-T-001-U2-114N5114 - 24/24

DECL-T-001-U1-114N5136-2/29

UPPER STRUCTURE HN200X100X5.5X8

DECL-T-001-U1-114N5134-8/35

Upper steel structure H596X199X10X15

DECL-T-001-U1-114N5134-15/35

Upper steel structure HN300X150X6.5X9(7),

DECL-T-001-U1-114N5134-16/35

Upper steel structure HN300X150X6.5X9

Page 13: BTG Shortage

SHORTAGE MATERIAL for SHIPMENT NO : T1-8 IMIR NO-0108

For DECLMaterials checked and recieved

on behalf of BGRESLFor TPCIL

8th SHIPMENT SHORTAGE MATERIAL

Original Packing No DRAWING NO DescriptionQuantity(Nos) RECIEPT

REMARKSPacking no

SL NO Shortag

e qtyReceived

Shipment no

19 1 B18 - To be checked **

21 114N5134-67 1 DEC SPARE

23 114N5138- 113 1

24 B18 - 1NO. 1

25 B131-1No 1

37

28 19

29 18

30 17

31 5

32 1

33 32

34 2

35 PF Gratings 114N5621 -590 1

36 17

37 15

38 100

39 GB/T6170-2000 Nut M10 190

40 69

41 9

42 GB/T6170-2000 Nut M10 29

43 NUT - 25 Nos shortage HS BOLT M24X7525

44 HS BOLT M24X80

213

45 BOLT M24X90-1No HS BOLT M24X90 1

46 HS BOLT M24, M22 105

DECL-T-001-U1-114N5134-16/35 114N5134 - 18 -1No

eachUpper steel structure

H446X199X8X12

DECL-T-001-U1-114N5134-19/35

Upper steel structure HM582X300X12X17

DECL-T-001-U1-114N5138-3/25

UPPER STRUCTURE HN200X100X5.5X8

DECL-T-001-U1-114N5138-9/25

UPPER STRUCTURE HN446X199X8X12

UPPER STRUCTURE HN300X150X6.5X9

DECL-T-001-U2-114N5111 - 35/39

JOINT PLATES, JP27 - 19NOS

DECL-T-001-U2-114N5111 - 36/39

JP39-16Nos, JP5-1No & JP13-1No

DECL-T-001-U2-114N5111 -37/39

JP49-16Nos & JP11-1No

DECL-T-001-U1-114N5611-020/242

PF Grating 114N5611- 16

DECL-T-001-U1-114N5611-148/242

PF Grating 114N5611 - 225

DECL-T-001-U1-114N5611-236/242

PF Grating 114N5611-踏步

DECL-T-001-U2-114N5621-095/248

PF Gratings 114N5621 - 269,

800X994X30

DECL-T-001-U2-114N5621-188/248

DECL-T-001-U2-114N5621-236/248

PF Grating 114N5621-踏步

800X214X30

DECL-T-001-U2-114N5621-248/248

PF Grating 114N5621-踏步

800X214X30

DECL-T-001-U1-114N562-2/2

GB/T5783-2000 Bolt M10X35 Gr8.8

GB/T95-2002 Washer Ø16

DECL-T-001-U2-114N562-2/2

GB/T5783-2000 Bolt M10X35 Gr8.8

DECL-T-001-U1-114N54-3/17

DECL-T-001-U1-114N54-5/17

BOLT - 169NOS, NUT - 201NOS & WASHER-213NOS

DECL-T-001-U1-114N54-10/17

DECL-T-001-U1-114N54-16/17

BOLT M24X65-105Nos, NUT M24 - 95Nos, Washer M24-100Nos

Page 14: BTG Shortage

SHORTAGE MATERIAL for SHIPMENT NO : T1-8 IMIR NO-0108

For DECLMaterials checked and recieved

on behalf of BGRESLFor TPCIL

8th SHIPMENT SHORTAGE MATERIAL

Original Packing No DRAWING NO DescriptionQuantity(Nos) RECIEPT

REMARKSPacking no

SL NO Shortag

e qtyReceived

Shipment no

47

HS BOLT M16, M22 71

48

** indicates the material is received in good condition as packed.

DECL-T-001-U1-114N54-17/17

BOLT M22X65 - 44 NOS, NUT M22 - 51 NOS & WASHER -55 NOS

BOLT M16X50 - 3 NOS, NUT M16 - 3 NOS & WASHER -16 NOS