Maximo Scheduler 7.6.1 and 7.6.2 2015 Releases Brian Downey, Maximo Designer & Architect

Page 2: Brian downey maximo scheduler

Please Note:

1

• IBM’s statements regarding its plans, directions, and intent are subject to change or withdrawal without notice at IBM’s solediscretion.

• Information regarding potential future products is intended to outline our general product direction and it should not be relied on in making a purchasing decision.

• The information mentioned regarding potential future products is not a commitment, promise, or legal obligation to deliver any material, code or functionality. Information about potential future products may not be incorporated into any contract.

• The development, release, and timing of any future features or functionality described for our products remains at our sole discretion.

• Performance is based on measurements and projections using standard IBM benchmarks in a controlled environment. The actual throughput or performance that any user will experience will vary depending upon many factors, including considerations such as the amount of multiprogramming in the user’s job stream, the I/O configuration, the storage configuration, and the workload processed. Therefore, no assurance can be given that an individual user will achieve results similar to those stated here.

Page 3: Brian downey maximo scheduler

Agenda

• What is Maximo Scheduler

• 7.6 Delivery Timeline

• Scheduler 2015 Focus – New Graphical Technology

– Usability

• New Applications – Repair Facility Graphical Assignment

– Repair Facility Capacity Planning

– Asset/Location Graphical Scheduling

• Scheduler 2016 Focus

2

Page 4: Brian downey maximo scheduler

What is Maximo Scheduler

Page 5: Brian downey maximo scheduler

What is Maximo Scheduler

4

Page 6: Brian downey maximo scheduler

7.6 Delivery Timeline

Page 7: Brian downey maximo scheduler

New applications built on a

new technical foundation

• Repair Facility Capacity

Planning

• Repair Facility Graphical

Assignment

Core Maximo PM costing

• Includes Nested Job Plans

“Scheduler” application name

change

• New name: “Graphical

Scheduling”

Usability enhancements

• Improved Gantt tools and

navigation

New Asset/Location scheduling

application built on a new

technical foundation

• Work Orders and PM forecasts

viewed by asset/location

hierarchy

Multi-tenancy support

Usability enhancements

• Improved Gantt tools and

navigation

Merging functionality to the new

technical foundation

• Graphical Scheduling

• Graphical Assignment

• Dispatch

• Crew Graphical Management

Usability enhancements

• Multi-column sort, search,

and filtering

• Multi-craft/skill display

• Undo / Redo

• Expand / Collapse

• Much more….

These releases address RFEs

7.6 Delivery Timeline

8

Page 8: Brian downey maximo scheduler

Scheduler 2015 Focus

Page 9: Brian downey maximo scheduler

New Graphical Technology

• Java applets are not used in our new applications

– No need to install and keep up to date the Java plug-ins for your browser

• Java script is now used therefore the user only requires a browser

– Significantly improves user experience

8

Page 10: Brian downey maximo scheduler

New features – Filtering – Sorting

9

• Quick filter - all columns searched

• multiple words found in different columns

• All conditions must be met in the filter result (“AND” condition)

• All columns are sortable

• Multi-column sort

• Default 3 with system property to increase

• Ascending/descending

• Press Shift-click for secondary sort column(s)

Page 11: Brian downey maximo scheduler

New features – Undo – Lock Durations

10

Undo and Redo

• Just like the functionality available

in most word processing

applications

• As long as the user is within a

Gantt view the action history will

be kept to undo and redo changes

10

Lock/Unlock Durations

• Unlocked is the state in current GA applet version allowing the user to change durations

• The Locked state does not allow the user to change the duration on any assignment bar in the work list

Page 12: Brian downey maximo scheduler

New features – Print – Columns

11

Dynamic Column

displayFlexible print options

Page 13: Brian downey maximo scheduler

New features – View all resource availability

• Each resource row now has a corresponding graphical row displaying the availability per shift

12

Page 14: Brian downey maximo scheduler

New features – More space to do assigning

13

Split into 2 tabs as most of the work is done in the Assignment view

Page 15: Brian downey maximo scheduler

New features – Tool Tip

• Tool tips can be viewed by holding down the ALT key and clicking on the work order bar

• Stays up until user clicks somewhere else on the screen

14

Page 16: Brian downey maximo scheduler

No Queries needed!

• Now the user can select schedule inputs

• SQL expert not requiredSiteid = (select defsite from maxuser where userid = :user) and status != ‘WAPPR’

and (targstartdate <= (sysdate+7) and targstartdate >= (sysdate))

15

Page 17: Brian downey maximo scheduler

New Applications

Page 18: Brian downey maximo scheduler

Asset/Location Graphical Scheduling

ALGS

17

Page 19: Brian downey maximo scheduler

Use Cases – ALGS

18

� The Scheduler or Planner requires the ability to view all work and/or

forecasted PMs for one or more Assets for a specified time frame.

� The Scheduler or Planner requires the ability to view all work and/or

forecasted PMs for one or more locations for a specified time frame. (Location Shutdown)

� The Scheduler or Planner requires the ability to view specific work and/or forecasted PMs for a specified time frame. (traditional graphical scheduling

functionality)

Page 20: Brian downey maximo scheduler

Gantt View

19

Work

Resources Load & Availability

Time based view

Page 21: Brian downey maximo scheduler

Wotrack Actions

20

Page 22: Brian downey maximo scheduler

New Time based background option

21

• By default the background will display the Maintenance and Operational schedules of the Asset or Location

• If flag not checked the calendar shifts available times will be displayed

Page 23: Brian downey maximo scheduler

Create constraints Graphically

22

Select multiple rows of related tasks and click the Create constraints icon

Constraints created and CPM performed on selected related tasks

Page 24: Brian downey maximo scheduler

Filter work orders based on selected resources

23

Select the craft or crew type in the resource section and then click on the filter icon in the resource tool bar

Filters work orders to only those that require the resources selected

Page 25: Brian downey maximo scheduler

PM Forecast Cost

24

For all PMs in the Scheduler the costs are calculated

Grouped weekly, monthly and yearly

Routes and nested job plans will be included in the costing of Labor, Materials, Tools and Services

Page 26: Brian downey maximo scheduler

Repair Facility Capacity Planning

RFCP

25

Page 27: Brian downey maximo scheduler

Repair Facility

• Garages, sheds, hangars are typical types of Repair Facilities

– Parent/Child Locations

• Multiple slots or bays can make up a repair facility

26

Page 28: Brian downey maximo scheduler

Use case – RFCP

The Facility Manager requires the ability to graphically view and assign

work orders for mobile asset to a Repair Facility for a given period of

time.

– What work orders require Repair Facilities?

– What Repair Facility are available?

• Assign work(asset) to a repair facility/location

27

Page 29: Brian downey maximo scheduler

Repair Facility - Work Orders assignments

28

• Work Order selection is limited to work orders that require a Repair Facility

• The functionality was inherited from the Labor assignment rules

Page 30: Brian downey maximo scheduler

Work Order Tracking – Assign to Repair Facility

29

• Work order tracking – Assignment tab – allows the user to assign the work to one or more Repair Facilities

Page 31: Brian downey maximo scheduler

RFCP - Creating a Work List

30

No Queries are needed!

This work list will include all parent work orders for current day plus 14 days with a Repair Facility Required flag set and all Location Repair Facilities with a Day calendar and a shift of 24HR, COMP1 or DAY that his user has access to

- Group all work to be completed for a Mobile Asset in one Parent Work Order

Page 32: Brian downey maximo scheduler

RFCP - Assignment View

• The Assignment view lists all the Repair Facility in a hierarchical list on the

left side of the screen and the assigned work orders on the right side

• Unassigned work will be displayed in orange and assigned in green

31

Page 33: Brian downey maximo scheduler

RFCP - Work View

Work View lists all the work orders brought into this project

32

Page 34: Brian downey maximo scheduler

RFCP – Assigning to multiple locations

A Truck may require two bays in a garage where a sedan only requires one

33

Page 35: Brian downey maximo scheduler

RFCP - Validation

Schedule Window requirement is not met

34

Double booking of a location will show the conflict

Page 36: Brian downey maximo scheduler

Repair Facility Graphical Assignment

RFGA

35

Page 37: Brian downey maximo scheduler

Use case - RFGA

The Facility Manager requires the ability to graphically view and assign all the work orders for mobile assets assigned to the Repair Facility and resources available for a given period of time

The Technician supervisor requires the ability to graphically assign work for mobile assets coming into his/her location to resources available within that location

36

Page 38: Brian downey maximo scheduler

RFGA - Assignment View

• The Assignment view lists all

the labor requirements as

orange bars to be assigned to

available labor/crew. Drag

and drop to a labor/crew row;

assigned is green.

• The hours of availability for

each labor and crew will

appear with a white back

ground based on their

calendar and shift – blue

shade marks time away during

shift

37

Page 39: Brian downey maximo scheduler

Work View- RFGA

• Dependencies and schedule windows now displayed

38

Page 40: Brian downey maximo scheduler

RFGA - Multiple Skill selection

• New multi-skilled indicator.

• Select an assignment bar and the perfect matched labor/crew

are highlighted in dark blue.

• Possible acceptable matches

are a lighter blue shade

– Same craft with higher ranked

skills

– Secondary craft/skill match

39

Page 41: Brian downey maximo scheduler

RFGA - Validations

Double booked assignment for a labor/crew

40

Assigned Labor does not meet the

Craft/skill requirement

• Schedule Window requirement is not met

Page 42: Brian downey maximo scheduler

RFGA – Mass Modify Availability

41

Modify several People or crews on the same shift

Select multiple days to modify

Page 43: Brian downey maximo scheduler

RFGA - Work View Other Resources

• Asset and Location operation and maintenance schedule

• Item store room availability

• Tool rotating asset availability42

Page 44: Brian downey maximo scheduler

Yes you Can!

• Can users currently using Graphical Scheduling start using Asset/Location Graphical Scheduler?

– Yes – if you are not using Optimization

• Can users currently using Graphical Assignment start using Repair Facility Graphical Assignment?

– Yes – if you are not using Optimization or Dispatching

43

Page 45: Brian downey maximo scheduler

Scheduler 2016 Focus

Page 46: Brian downey maximo scheduler

Scheduler 7.6.3 – 4 Applications

• Graphical Scheduling

– Merge GS and ALGS

• Graphical Assignment

– Merge GA and RFGA

• Graphical Crew Management

– New technology

• Repair Facility Capacity Planning

45

Page 47: Brian downey maximo scheduler

Notices and Disclaimers

46

Copyright © 2016 by International Business Machines Corporation (IBM). No part of this document may be reproduced or transmitted in any form without written permission

from IBM.

U.S. Government Users Restricted Rights - Use, duplication or disclosure restricted by GSA ADP Schedule Contract with IBM.

Information in these presentations (including information relating to products that have not yet been announced by IBM) has been reviewed for accuracy as of the date of initial publication and could include unintentional technical or typographical errors. IBM shall have no responsibility to update this information. THIS DOCUMENT IS DISTRIBUTED "AS IS" WITHOUT ANY WARRANTY, EITHER EXPRESS OR IMPLIED. IN NO EVENT SHALL IBM BE LIABLE FOR ANY DAMAGE ARISING FROM THE USE OF THIS INFORMATION, INCLUDING BUT NOT LIMITED TO, LOSS OF DATA, BUSINESS INTERRUPTION, LOSS OF PROFIT OR LOSS OF OPPORTUNITY. IBM products and services are warranted according to the terms and conditions of the agreements under which they are provided.

Any statements regarding IBM's future direction, intent or product plans are subject to change or withdrawal without notice.

Performance data contained herein was generally obtained in a controlled, isolated environments. Customer examples are presented as illustrations of how those customers have used IBM products and the results they may have achieved. Actual performance, cost, savings or other results in other operating environments may vary.

References in this document to IBM products, programs, or services does not imply that IBM intends to make such products, programs or services available in all countries in which IBM operates or does business.

Workshops, sessions and associated materials may have been prepared by independent session speakers, and do not necessarily reflect the views of IBM. All materials and discussions are provided for informational purposes only, and are neither intended to, nor shall constitute legal or other guidance or advice to any individual participant or their specific situation.

It is the customer’s responsibility to insure its own compliance with legal requirements and to obtain advice of competent legal counsel as to the identification and interpretation of any relevant laws and regulatory requirements that may affect the customer’s business and any actions the customer may need to take to comply with such laws. IBM does not provide legal advice or represent or warrant that its services or products will ensure that the customer is in compliance with any law

Page 48: Brian downey maximo scheduler

Notices and Disclaimers Con’t.

47

Information concerning non-IBM products was obtained from the suppliers of those products, their published announcements or other publicly available sources. IBM has not tested those products in connection with this publication and cannot confirm the accuracy of performance, compatibility or any other claims related to non-IBM products. Questions on the capabilities of non-IBM products should be addressed to the suppliers of those products. IBM does not warrant the quality of any third-party products, or the

ability of any such third-party products to interoperate with IBM’s products. IBM EXPRESSLY DISCLAIMS ALL WARRANTIES, EXPRESSED OR IMPLIED, INCLUDING BUT NOT LIMITED TO, THE IMPLIED WARRANTIES OF MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE.

The provision of the information contained h erein is not intended to, and does not, grant any right or license under any IBM patents, copyrights, trademarks or other intellectual property right.

IBM, the IBM logo, ibm.com, Aspera®, Bluemix, Blueworks Live, CICS, Clearcase, Cognos®, DOORS®, Emptoris®, Enterprise Document Management System™, FASP®, FileNet®, Global Business Services ®, Global Technology Services ®, IBM ExperienceOne™, IBM SmartCloud®, IBM Social Business®, Information on Demand, ILOG, Maximo®, MQIntegrator®, MQSeries®, Netcool®, OMEGAMON, OpenPower, PureAnalytics™, PureApplication®, pureCluster™, PureCoverage®, PureData®, PureExperience®, PureFlex®, pureQuery®, pureScale®, PureSystems®, QRadar®, Rational®, Rhapsody®, Smarter Commerce®, SoDA, SPSS, Sterling Commerce®, StoredIQ, Tealeaf®, Tivoli®, Trusteer®, Unica®, urban{code}®, Watson, WebSphere®, Worklight®, X-Force® and System z® Z/OS, are trademarks of International Business Machines Corporation, registered in many jurisdictions worldwide. Other product and service names might be trademarks of IBM or other companies. A current list of IBM trademarks is available on the Web at "Copyright and trademark information" at: www.ibm.com/legal/copytrade.shtml.

Page 49: Brian downey maximo scheduler