AIESEC Vietnam | Talent planning for dummies

Jan 27, 2015

Download

Business

Amy Phan

A brief guide to LCVPTMs abt how to do talent planning properly and ensure HR sustainability in AIESEC Vietnam.
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: AIESEC Vietnam | Talent planning for dummies

talent planning (n.) the process of calculatinghow many more dummies will come

to make AIESEC even dummier

Page 2: AIESEC Vietnam | Talent planning for dummies
Page 3: AIESEC Vietnam | Talent planning for dummies

1. Do SWOT (and optionally PEST) analysis for your LC;

2. Review key achievements, key bottlenecks and key learning points of last term/batch;

3. Create a vision of where you want to go;

4. Define LC exchange goal;

5. Break that goal down in 4 programs e.g.. oGCDP, oGIP, iGCDP, iGIP;

6. Break down the goal of each program’s into projects’:

– Define total number of projects in a 12-month basis;

– Allocate them into a 12-month timeline;

– Define exchange contribution of each project based on its project model;

7. Define exchange pipeline & key strategies for each program/project;

8. Define OC structure and JDs.

LCP

LCP

LCP

LCPLCP

LCP

LCP

VP function/OCP

Main role Supporting role

VPTM

VP function/OCP

VP function/OCP

Page 4: AIESEC Vietnam | Talent planning for dummies

• Talent review can only be done after OCP recruitment & LC reallocation.

• Look at database of the past 6-12 months to review:

– Age structure: refers to clustering members based on their year of study. In general, freshmen are passionate and energetic but inexperienced. Their learning capacity and commitment to AIESEC are high; however, chances are they cannot deal with difficult tasks due to lack of experience. Somophores and junior students, on the other hand, may probably be less “high” but certainly their social awareness and set of skills are much higher than freshmen’s. This cluster also has the highest chance of taking strategic leadership positions such as LCP and LCVP. Senior students, often in their final year, are quite busy with their graduation or internship outside; thus, they cannot devote much time to AIESEC any more. They are going to leave LC soon, to apply for MC or simply to start their post-AIESEC life. Therefore, among these clusters, the one of somophores and junior students should account for the largest portion (e.g.. 60-70% LC total population), while the one of freshmen should account for maximum 10%, and the rest goes to the other one.

Page 5: AIESEC Vietnam | Talent planning for dummies

– Member efficiency: counted over a particular period of time, e.g.. 6 months, 12 months, etc.

Member efficiency, based on past data, tells us the minimum number of people required to achieve exchange goal.

– 12-month retention rate: refers to number of members recruited same time last year who are still active. For example, there are 20 members recruited in Spring recruitment 2013. By the time of Spring recruitment 2014, 2 of them have already left and 1 is inactive. Thus, 12-month retention rate equals (20-2-1)/20 = 85%.

– Function-based talent allocation : Total number of members & leaders in supporting functions should NOT exceed 50% total number of members & leaders in eXchange functions.

Page 6: AIESEC Vietnam | Talent planning for dummies

Number of new members to recruit

Exchange goal

No of jobs already taken by current members (after

LC reallocation)

Member efficiency

Number of jobs required

Number of jobs required

No of job vacancies

No of job vacancies

No of members inactive/LLC in the

next 6 months

No of members / leaders pipeline for prospective projects & positions in

the next 6 months

Number #A

Number #A 12-month functional retention rate 1.1

Number of EP reintegrated in next 6 months

1

2

3

4

General principles:

Page 7: AIESEC Vietnam | Talent planning for dummies

• Define competency profile required for each position.• Based on the desired LC age structure, define how many new members in each year-of-study

cluster to recruit. Note that LC age structure is different in spring and in autumn.• Define target universities and/or majors to ensure a good and diverse mixture of talent.• Calculate total number of members and leaders in each function to see whether function-based

talent allocation criteria is satisfied or not. If not, consider an adjustment in talent planning of either exchange/supporting teams.

• Collect relevant documents, e.g.. written JDs for new members, competency profile for each position, etc.

• Set expectation in EB about the priority order in allocating new members to avoid conflicts later. Priority should be given to programs/functions of focus or of urgent needs. This step should be taken charge by LCVPTM and facilitated by LCP. Besides, predict solutions for the case of attracting lower number of candidates than expected and the case of exceeding number of potential candidates than planned.

• Done! Congratulations

Page 8: AIESEC Vietnam | Talent planning for dummies

• Q: Why 1.1?• A: After calculating based on facts and data, we add 10% more to the goal to prevent unexpected

problems which leads to leak-out.• Q: How long does talent planning take?• A: Maximum 2-3 weeks, including 1 week for strategic exchange planning & 1 week for TMP/TLP

planning.• Q: I have recruited enough number of newbies as planned. I expect they perform right after

recruitment, but they do not. Why is it?• A: It takes at least 1 month for induction and 2-3 months for newbies to adapt, learn and start

performing. Thus, please do NOT expect that new members can perform right after recruitment. If you need well-performing members, recruit them at least 4 months in advance.

• Q: Who are the key people involved in talent planning in EB level?• A: Talent planning requires a mutual effort of LCVPTM & LCP. For instance, LCVPTM is responsible for

(i) training LCVPs and OCPs how to write JDs and how to calculate the number of new members needed for their team, (ii) collecting and storing written JDs of all functions, (iii) giving feedback to team leaders regarding their talent plan (e.g.. whether the proposed number is reasonable, whether they should recruit more or less new members to serve their goal, etc.), and (iv) do final check (Step #4 above) to ensure HR sustainability. Meanwhile, LCP plays the facilitating role by giving insights from exchange plan and supervising the process in general.

Page 9: AIESEC Vietnam | Talent planning for dummies

• Job Description library:– Version for EWA (En & Vi);– Version for TMP/TLP (En);

• Talent planning template;• Local TMP/TLP database;

Page 10: AIESEC Vietnam | Talent planning for dummies

Please, conduct the talent planning for 12 months and plan strategies to have the right people on the right positions throughout the term, basing on the data:

• Every OC team in oGCDP and oGIP has 5 OC members and 1 OCP. There are 2 marketing responsible, 2 exchange process responsible and 1 logistics responsible.

• Every OC team in iGCDP has 1 OCP and 5 OC members responsible for: ERx1, eXchange x1, Marketing x2, Finance & Logistics x1.

• Every OC team in iGIP has 1 OCP and OC members responsible for: Sales x3, Matching x2.

• It's January 2014 now. Retention rate (calculated from the beginning till the end of the OC team duration) is 85%. Currently, you have 4 projects running in iGCDP, 2 in iGIP, 3 in oGCDP and 1 in oGIP. You also have 5 senior members working with LCVP Marketing directly. Expected retention rate until May 2014 is 50%. You have 2 senior members working with LCVP Finance. They finish their studies in May and will leave. You have 5 senior sales members. The expected retention rate in that team until June 2014 is 60%. You have 3 senior members working with your VP TM. 1 will leave in April and 1 will leave in June. Productivity in oGCDP is 6X per member, 2X per member in oGIP, 6X per member in iGCDP, 2X per member in iGIP.

Page 11: AIESEC Vietnam | Talent planning for dummies

• You want to maintain the current number of members in the supporting function teams by allocating new people after leak out. In Winter you organize a national conference. New EB election happens in November. In September you plan to start 3 new SUs.

• Do the talent planning to achieve the goals stated below:– oGCDP: 100 realizations in the summer peak, 40 realizations in the autumn

(Sept-Nov), 60 realizations in the winter peak (Dec-Feb);– iGCDP: 80 re in the summer peak, 40 re in the autumn, 70 re in the winter peak;– iGIP: 30 re in the March-April wave, 30 re in the autumn wave;– oGIP: 15 re in Q1+Q2, 25 re in the winter peak;

Page 12: AIESEC Vietnam | Talent planning for dummies
Page 13: AIESEC Vietnam | Talent planning for dummies

• Assume that we have done with OCP recruitment and LC reallocation.• Step #1: Analyze exchange goals.

Exchange goals: oGCDP: 100 realizations in the summer peak, 40 realizations in the autumn (Sept-Nov), 60 realizations in the winter peak (Dec-Feb); iGCDP: 80 re in the summer peak, 40 re in the autumn, 70 re in the winter peak; iGIP: 30 re in the March-April wave, 30 re in the autumn wave; oGIP: 15 re in Q1+Q2, 25 re in the winter peak.Key steps for each program:1. Create exchange pipeline for each program.2. Break down program goal into projects’ contribution.3. Analyze OC structure, JDs and competency profile required for each position.

Page 14: AIESEC Vietnam | Talent planning for dummies

• Create exchange pipeline for oGCDP:

– We start with oGCDP:

Page 15: AIESEC Vietnam | Talent planning for dummies

• Break down into oGCDP projects:

Page 16: AIESEC Vietnam | Talent planning for dummies

• Analyze OC structure, JDs and competency profile required for each position:

• Each OC team in oGCDP has 1 OCP & 5 OC members, including 2 OC Marketing, 1 OC IR, 1 OC Customer service & 1 OC Finance & logistics.

• There is 1 SU for oGCDP. SU has 1 SUP, 1 SUVP Marketing, 1 SUVP OGX and 3 OGX members, including 2 OC Customer service & 1 OC Finance & logistics.

• Competency profile required:

• Marketing: Innovation, Detail orientation, Commitment to results

• IR: Detail orientation, Analytical thinking, Commitment to results

• Customer service: Communication, Emotional intelligence, Stakeholder focus

• Finance & logistics: Detail orientation, Analytical thinking, Communication

Page 17: AIESEC Vietnam | Talent planning for dummies

• Create exchange pipeline for iGCDP:

– After that, we move to iGCDP:

Page 18: AIESEC Vietnam | Talent planning for dummies

• Break down into iGCDP projects:

Page 19: AIESEC Vietnam | Talent planning for dummies

• Analyze OC structure, JDs and competency profile required for each position:

• There are 2 SUs for iGCDP.

• Each SU/OC team in iGCDP has 1 SUP/OCP and 5 SU/OC members, including 1 OCER, 1 OC eXchange, 2 OC Marketing and 1 OC Finance & logistics.

• Competency profile required:

• ER: Stakeholder focus, Influence & negotiation, Commitment to results

• Marketing: Innovation, Detail orientation, Commitment to results

• Exchange: Communication, Emotional intelligence, Stakeholder focus

• Finance & logistics: Detail orientation, Analytical thinking, Communication

Page 20: AIESEC Vietnam | Talent planning for dummies

• Create exchange pipeline for iGIP:

– Then, we move to iGIP:

Page 21: AIESEC Vietnam | Talent planning for dummies

• Break down into iGIP projects:

Page 22: AIESEC Vietnam | Talent planning for dummies

• Analyze OC structure, JDs and competency profile required for each position:

• Each OC team in iGIP has 1 OCP and 5 OC members, including 3 OCER and 2 OC Matching.

• Competency profile required:

• ER: Stakeholder focus, Influence & negotiation, Commitment to results

• Matching: Commitment to results, Innovation, Communication

Page 23: AIESEC Vietnam | Talent planning for dummies

• Create exchange pipeline for oGIP:

– Then, we move to oGIP:

Page 24: AIESEC Vietnam | Talent planning for dummies

• Break down into oGIP projects:

Page 25: AIESEC Vietnam | Talent planning for dummies

• Analyze OC structure, JDs and competency profile required for each position:

• Each OC team in oGIP has 1 OCP & 5 OC members, including 2 OC Marketing, 1 OC IR, 1 OC Customer service & 1 OC Finance & logistics.

• Competency profile required:

• Marketing: Innovation, Detail orientation, Commitment to results

• IR: Detail orientation, Analytical thinking, Commitment to results

• Customer service: Communication, Emotional intelligence, Stakeholder focus

• Finance & logistics: Detail orientation, Analytical thinking, Communication

Page 26: AIESEC Vietnam | Talent planning for dummies

– Finally, we will host National conference in winter (e.g.. January 2015).

• OC is formed at May 2014.

• OC structure:

• Competency profile required:

• ER: Stakeholder focus, Influence & negotiation, Commitment to results

• EPD/IPD: Innovation, Commitment to results, Communication, Stakeholder focus

• Finance / Logistics: Detail orientation, Analytical thinking

• Agenda manager: Innovation, Stakeholder focus, Influence & Negotiation

OCP

1 OCVP Y2B

1 Y2B Agenda manager

3 OCER

1 OC EPD1 OC IPD

1 OC Finance

1 OC Logistics

Page 27: AIESEC Vietnam | Talent planning for dummies

• Step #2: Review talent pool

Page 28: AIESEC Vietnam | Talent planning for dummies

• Step #2: Review talent pool– Retention rate of X teams is acceptable (85%) but retention rate of S(upporting)

teams is low (0-60%).– Total number of people working in X teams (58) equals 3.87 times total number

of people working in S teams (15), which indicates good resource allocation.– Member efficiency:

Page 29: AIESEC Vietnam | Talent planning for dummies

• Step #3: Calculate number of new members to recruit.– As assumed, we have done with OCP recruitment & LC reallocation. We now

proceed to calculate talent needs only for TMP positions.– For simplification, assume that all OCs serving summer peak will start in January

2014 and end in July 2014, and all OCs serving autumn and/or winter peak will start in July 2014 and end in Feb 2015.

– We calculate talent needs for X teams based on member efficiency and exchange goal, while for S teams based on the given assumption that “You want to maintain the current number of members in the supporting function teams by allocating new people after leak out”. Thus, we will separate calculation for X teams and for S teams.

Page 30: AIESEC Vietnam | Talent planning for dummies

• Step #3: Calculate number of new members to recruit.– For summer peak:

• oGCDP: We need 18 people (15 members + 3 OCPs) for 3 OCs serving summer peak (e.g.. oGCDP 1, oGCDP 2, oGCDP 3). 3 current projects provides 18 people, indicating that we have enough people for oGCDP.

• iGCDP: Giving the same reasoning as oGCDP, we have enough people for iGCDP summer peak (Summer camp, GPC 1, Vietnam 3D & NPO 1).

• iGIP: Giving the same reasoning as oGCDP, we have enough people for iGIP Mar-Apr peak (TEACH 1 & GROW 1).

• oGIP: Giving the same reasoning as oGCDP, we have enough for oGIP summer peak (OC oGIP 1).

• Supporting functions: For period May-Jul 2014, each supporting team needs 2-3 new members to replace senior members who will leave around May. Thus, we will count 3 new members for MarCom, 2 for Finance, 2 for BD and 2 for TM.

• OC NatCo: As all senior members are allocated in either X or S teams, there is no one left for OC NatCo except for OCP who is already selected. Thus, we will recruit 9 new members for OC NatCo.

Page 31: AIESEC Vietnam | Talent planning for dummies

• Step #3: Calculate number of new members to recruit.– For autumn & winter peak:

• oGCDP: We need 18 people for 3 OCs serving autumn & winter peak (e.g.. oGCDP 3, oGCDP 4, SU). In Jul 2014, we will have only 16 people. Thus, we need to recruit 2 new members for oGCDP in Spring recruitment so that they have enough time to learn and develop as preparation for autumn & winter peak.

• iGCDP: We need 24 people for 4 OCs serving autumn & winter peak (e.g.. GPC 2, SU X, SU Y & NPO 2). In Jul 2014, we will have only 21 people. Thus, we need to recruit 3 new members.

• iGIP: We need 18 people for 3 OCs serving autumn wave (e.g.. TEACH 2, GROW 2, CONNECT). In Jul 2014, we will have only 11 people. Thus, we need to recruit 7 new members.

• oGIP: We need 6 people for OC oGIP 2 to serve winter peak. In Jul 2014, we will have only 5 people. Thus, we need to recruit 1 new member.

• Supporting functions: We have counted new members for S teams in the above part of “summer peak”, and the number of members remain the same all year round for each supporting function.

• LCEB election & selection: Effect of this activity will be reflected in July planning, not now.

Page 32: AIESEC Vietnam | Talent planning for dummies

• Step #3: Calculate number of new members to recruit.– Adding up talent needs for the next 12 months, we need to recruit 31 new members, including:

• 3 new members for MarCom;• 2 new members for Finance;• 2 new members for BD;• 2 new members for TM;• 9 new members for OC NatCo;• 2 new members for oGCDP;• 3 new members for iGCDP;• 7 new members for iGIP;• 1 new member for oGIP;

– To protect ourselves from unforeseen problems which lead to leak-out, we add 10% to the above number. Thus, we will adjust the goal into 34 new members to recruit.

– Given no information about the number of reintegrated returnees, we consider this number is zero. Therefore, 34 is the final number of new members to recruit at Spring recruitment 2014.

Page 33: AIESEC Vietnam | Talent planning for dummies

• Step #4: Do final check.– Define competency profile of recruiting positions as criterion to assess

candidates;– Decide target segments, including years of study, universities and majors;– Function-based talent allocation criteria is satisfied (checked!).– Contact LCVPs/OCPs to collect relevant documents.– Set expectation in EB about priority order in getting new members and propose

solution for different cases, e.g.. recruiting only 25 instead of 34. Discuss to see which teams may cover 3 “extra” members.

Page 34: AIESEC Vietnam | Talent planning for dummies