57086 Contract and Project Management 7 David Sowden, The University of Hull
May 21, 2015
57086 Contract and Project Management7David Sowden, The University of Hull
757086 Contract and Project Management
Introduction to Processes - Managing a Stage Boundary
David Sowden, The University of Hull
Overview
• Managing Stage Boundaries– Fundamental principles– Contexts– Process description– Planning a Stage– Updating a Project Plan– Updating a Project Business Plan– Updating the Risk Log– Reporting Stage End– Producing an Exception Plan
3
4
Directing a Project
Initiating a Project
Managing a Stage
Boundary
Controlling a Stage
Relationships of Processes
5
Starting a Project
Directing a Project
Initiating a Project
Managing a Stage
Boundary
Controlling a Stage
Managing ‘Product’ Delivery
End
Closing a Project
6
THE BASICSManaging a Stage Boundary
Prepare a report for the ‘Project Board’
Check if the Business Case or risk have changed
Plan the next stage (or Exception Plan) and update the Project Plan
Complete the performance statistics for the current stage
Icons
7
Guidelines - Rules, Policies,instructions that should be followed
Resources - tools, systemsor materials required to complete a task
Managing a Stage Boundary (1)
8
Plan the next stage
Stage boundary approaching
Exception Plan request
Issue Register
Update Configuration Item RecordUpdate Issue RegisterUpdate Quality RegisterCreate ‘Product’ DescriptionUpdate PID
Lessons LogPIDRisk Register
Managing a Stage Boundary (2)
9
Update the Project PlanNext stage planned
Stage Plan (current stage)
Update Issue RegisterUpdate Project PlanUpdate Risk Register
Stage Plan (next stage)
Exception PlanPID
Managing a Stage Boundary (3)
10
Update the Business CaseProject Plan updated
Benefits Review Plan
Update Benefits Review PlanUpdate Business CaseUpdate Risk Register
Issue RegisterProject Plan
PID
Risk Register
Managing a Stage Boundary (4)
11
Report stage endBusiness Case updated
Benefits Review Plan
Create End Stage ReportCreate Lessons ReportCreate follow-on actionrecommendations
Lessons logIssue Register
PID
Quality Register
Update Configuration Item RecordsCreate Exception Plan
Managing a Stage Boundary (5)
12
Request to approve next Stage Plan
Stage Plan (current stage)Update Issue Register
Update Quality RegisterCreate ‘Product’ Description
Risk RegisterIssue Register
PID
Configuration ItemRecords
Directing a Project
Produce an Exception Plan Request to approve Exception Plan
section 4
Exceptions
13
Plan the next stageException Plan request
EXAMPLE
TASK
Review and tailor your stage boundaries
Have all products that were planned to be completed within the stage been approved?
Has a Product Status Account been created to verify the status of the stage’s products?
If there was a product handover during the stage, were lated outstanding issues documented as follow-on action recommendations ready for distribution subject to Project Board approval?
Has the Lessons Log been reviewed and updated?
If required, has the Lessons report been created ready for distribution, subject to Project Board approval?
Has the Stage Plan been updated with actuals?
Has the Risk Management Strategy been review and (if necessary) updated?
Has the Risk Register been reviewed and updated?
Has the Configuration Management Strategy been reviewed and (if necessary) updated?
Have the Configuration Items Records been reviewed and updated?
Has the Issue Register been reviewed and updated?
Has the Quality Management Strategy been reviewed and (if necessary) updated?
Has the Quality Register been reviewed and updated?
Has the Communication Management Strategy been reviewed and (if necessary) updated?
Have the project controls been reviewed and (if necessary) updated?
Has the Project Plan been reviewed and (if necessary) updated?
Has the project management team structure been updated to reflect and new roles being appointed or any changes to responsibilities of existing roles?
CHECK(1)Managing a Stage Boundary
CHECK(2)For new appointments, do role descriptions exist and have those people who have been appointed confirmed their acceptance?
Has the Business Case been reviewed and (if necessary) updated?
Has the Benefits Review Plan been reviewed and (if necessary) updated?
Has the Project Initiation Documentation been reviewed and (if necessary) updated?
Has the End Stage Report been produced showing actual against planned performance, and summarising lessons and follow-on recommendations
Has the End Stage Report been issued to the Project Board in accordance with the project controls?
For the next stage
Has the Stage Plan for the next stage been created?
Have Product Descriptions been created for the next stage’s products?
Has the Project Board been requested to authorise the next stage?
For Exceptions
Has an Exception Plan been created (if requested by the Project Board)?
Have Product Descriptions been created/updated for the Exception Plan?
Hs the Project Board been requested to approve the Exception Plan?
Managing a Stage Boundary