Top Banner
PROJECT MANAGEMENT Session 1 Introduction
25
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 4a4a3PM Session 1 Introduction.ppt

PROJECT MANAGEMENTSession 1

Introduction

Page 2: 4a4a3PM Session 1 Introduction.ppt

Coverage – Session 1

• What is a project?• Project Management:- 1. Project Planning. 2. Project Scheduling. 3. Project Controlling.• Basic Tools:- 1. Bar chart. 2. Milestones chart.• Management Applications of Network Analysis

Page 3: 4a4a3PM Session 1 Introduction.ppt

Definition of Project

• A project (such as construction of a flyover, power plant, research & development work, repair & maintenance of an airplane, marketing of a new product etc.) may be defined as a “collection of inter-related tasks or activities which must be completed in a specified time according to a specific order (or sequence) and require resources such as money, materials, manpower, facilities, space, etc”.

Page 4: 4a4a3PM Session 1 Introduction.ppt

What is Project Management?

• Project management is “the application of knowledge, skills, tools and techniques to project activities to meet project requirements.”*

Page 5: 4a4a3PM Session 1 Introduction.ppt

Questions to be Answered by a Project Manager

• When do we expect project to be completed?

• If any activity is delayed, what effect will this have on the overall completion of the project?

• If there are additional funds available to reduce the time to perform certain activities, how should they be spent?

• What is the probability of completing the project by due date?

Page 6: 4a4a3PM Session 1 Introduction.ppt

Objectives of the Project Management

• Project should finish on time.

• Project cost should be within the allocated budget.

• Project should be within the laid down technical specifications which satisfies the end users.

Page 7: 4a4a3PM Session 1 Introduction.ppt

Main Tasks of Project Manager

1. Project Planning.

2. Project Schedule.

3. Project Control.

Page 8: 4a4a3PM Session 1 Introduction.ppt

1. Project Planning

• Objectives.

• Team Organization.

• Performance Criteria: Time, Cost.

• Requirement of Resources.

• Developing of Network.

Page 9: 4a4a3PM Session 1 Introduction.ppt

2. Project Schedule

• Availability of Resources (Human, Material, Financial).

• Duration estimates of activities.

• Selection of Managerial Technique.

• Networks (PERT, CPM).

Page 10: 4a4a3PM Session 1 Introduction.ppt

3. Project Control

• Monitoring.

• Revision & Updating.

• Rescheduling Measures.

• Reallocation of Resources.

Page 11: 4a4a3PM Session 1 Introduction.ppt

Gantt Chart – An Example

S.No. Activity Duration

1. Preparing a pattern for casting 4 weeks

2 Preparing a mould 2 weeks

3 Casting and cleaning operation of A 1 weeks

4 Heat Treatment of A 2 weeks

5 Installing machine M 7 weeks

6 Machining part B 5 weeks

7 Assembling parts A & B 3 weeks

8 Preparing the test jig 4 weeks

9 Testing the assembly 2 weeks

10 Packing the dispatch 1 weeks

Page 12: 4a4a3PM Session 1 Introduction.ppt

GANTT CHART

Activity 1 2 3 4 5 6 7 8 910

11

12

13

14

15

16

17

18

Prepare Pattern                                    

Prepare Mould                                    

Cast & Clean A                                    

Heat Treatment A                                    

Install Machine M                                    

Machine Part B                                    

Assemble Parts A & B                                    

Prepare Test Rig                                    

Test Assembly                                    

Pack & Dispatch                                    

Page 13: 4a4a3PM Session 1 Introduction.ppt

GANTT CHART

Activity 1 2 3 4 5 6 7 8 910

11

12

13

14

15

16

17

18

Prepare Pattern                                    

Prepare Mould                                    

Cast & Clean A                                    

Heat Treatment A                                    

Install Machine M                                    

Machine Part B                                    

Assemble Parts A & B                                    

Prepare Test Rig                                    

Test Assembly                                    

Pack & Dispatch                                    

Page 14: 4a4a3PM Session 1 Introduction.ppt

Limitations of Bar Chart

• Bar chart can not show clearly the interdependencies among various activities.

• Bar chart does not show the progress of work, therefore can’t be used as control device.

• Bar chart can’t reflect the uncertainties or tolerances in the duration times estimated for various activities.

Page 15: 4a4a3PM Session 1 Introduction.ppt

Milestone Charts

• For dynamic programming, knowledge of amount of work in progress or jobs completed is necessary.

• Suppose 10th weeks have elapsed, what progress is made?

Page 16: 4a4a3PM Session 1 Introduction.ppt

MILESTONE

GANTT CHART

Activity 1 2 3 4 5 6 7 8 910

11

12

13

14

15

16

17

18

Prepare Pattern                                    

Prepare Mould                                    

Cast & Clean A                                    

Heat Treatment A                                    

Install Machine M                                    

Machine Part B                                    

Assemble Parts A & B                                    

Prepare Test Rig                                    

Test Assembly                                    

Pack & Dispatch                                    

At the end of 10th week

Lagging

Page 17: 4a4a3PM Session 1 Introduction.ppt

Exercise 1- Represent on Gantt Chart

Activity Duration in days

Design Questionnaire 7

Print Question paper 2

Distribute to Various Centres 4

Answer Questionnaire 1

Collect Answer Books at Main Office

4

Page 18: 4a4a3PM Session 1 Introduction.ppt

Exercise 1

Activity 1 2 3 4 5 6 7 8 910

11

12

13

14

15

16

17

18

Design Questionnaire                                    

Print question paper                                    

Distribute to various centers                                    

Answer questionnaire                                    

Collect answer books at main office                                    

Page 19: 4a4a3PM Session 1 Introduction.ppt

Exercise 2 - Represent on Gantt Chart

• A project is to be represented by a bar chart. The duration for each activity is in days work . These are the actual work days. The project commenced on Monday – 7th June 2010, with five working days a week. Draw the Gantt chart with horizontal scale denoting calendar dates. The activities duratio are shown in next slide.

• Activities 1 & 2 can occur concurrently. Activity 3 can take place after activity 2 is completed. Activities 4,6, and 3 can occur concurrently. Activity 8 can start 4 days after the commencement of activity 6. Activity 7 should follow activity 5. Activity 5 can begin concurrently with activity 8.

( ---- Data continued in next slide.)

Page 20: 4a4a3PM Session 1 Introduction.ppt

Exercise 2 - Data

Activity Duration in DaysActivity 1 8

Activity 2 4

Activity 3 7

Activity 4 9

Activity 5 3

Activity 6 3

Activity 7 6

Activity 8 7

Page 21: 4a4a3PM Session 1 Introduction.ppt

Exercise 2  June, 2010

Activity 7 8 910

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

Activity 1                                                

Activity 2                                                

Activity 3                                                

Activity 4                                                

Activity 5                                                

Activity 6                                                

Activity 7                                                

Activity 8                                                

Page 22: 4a4a3PM Session 1 Introduction.ppt

Exercise 2  June, 2010

Activity 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

1                                                

2                                                

3                                                

4                                                

5                                                

6                                                

7                                                

8                                                

Page 23: 4a4a3PM Session 1 Introduction.ppt

Exercise 2 - Monitoring

• Answer the following:-

1. On what calendar date the project was completed?

2. On 23rd June, what was the progress of the project?

Page 24: 4a4a3PM Session 1 Introduction.ppt

Exercise 2 - Monitoring

• Answer 1:- The project completed on 30th June.

• Answer 2:-

(i) Activities 1,2,3,4,5,6 had completed.

(ii) Activity 7 was under progress for 2 days, 4 more days required for its completion.

(iii) Activity 8 was under progress for 4 days, 2 more days required for its completion.

Page 25: 4a4a3PM Session 1 Introduction.ppt

Thanks