January 16, 2013 Project Connect
January 16, 2013
Project Connect
Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting February 13 Adjourn
Project Connect 2
Budget and Timeline Project Update Current and Upcoming Activities Risks and Issues New Mexico Trip Report Key Project Dates
Welcome to our newest ESC Member
Tony Powell, CIO, Department of Revenue
Project Connect 3
Project Connect 4
Project Connect 5
Project Connect 6
SPI as of December 21: 1.01 CPI as of December 15: .95
Project Connect 7
Rebaselined Budget
Allocated Contingency
& Management
Reserves
Supplemental Budget Requests
REA GrantUpdated Project Budget
Estimate at Completion
Project Variance
Project FundingOPS 217,770 0 0 0 217,770 221,368 (3,598)Expenses 7,240,310 1,013,200 0 0 8,253,510 8,467,240 (213,730)OCO (Hardware) 1,441,425 (184,637) 0 0 1,256,788 968,889 287,899 Contracted Services
Project Management & SupportProject Management Office 2,019,270 0 0 0 2,019,270 2,019,270 0Project & Operational Support 3,694,500 (749,261) 1,082,350 119,474 4,147,063 4,012,685 134,378Outside Legal 230,652 0 0 0 230,652 230,652 0ITN Development 512,700 0 0 0 512,700 512,700 0Business Transition 3,945,916 0 0 134,730 4,080,646 4,064,881 15,765Other Contracted Services 164,790 50,000 0 0 214,790 230,358 (15,568)
Total Project Management & Support 10,567,828 (699,261) 1,082,350 254,204 11,205,121 11,070,545 134,575 IV&V Services 2,019,940 0 0 75,000 2,094,940 2,094,940 0 Benefits Realization Strategy 239,391 0 0 0 239,391 239,391 0 Organizational Change Management 467,520 0 0 0 467,520 467,520 0 System Integrator (SI) Services 28,285,557 902,238 0 1,054,586 30,242,381 29,187,795 1,054,585 SI Hardware & Maintenance 2,607,493 184,637 0 0 2,792,130 2,599,812 192,318 SI Software & Maintenance 6,488,115 (1,013,200) 0 0 5,474,915 5,603,682 (128,767)Project Reserves 122,695 0 0 0 122,695 0 122,695
Project Funding Totals 59,698,044 202,977 1,082,350 1,383,790 62,367,160 60,921,184 1,445,976 Cotingency/Management Reserves 3,100,651 2,897,674 622,460
Project Connect 8
0
10
20
30
40
50
60
70
FY11Q1
FY11Q2
FY11Q3
FY11Q4
FY12Q1
FY12Q2
FY12Q3
FY12Q4
FY13Q1
FY13Q2
FY13Q3
FY13Q4
FY14Q1
FY14Q2
FY14Q3
FY14Q4
FY 15 Q1
FY 15 Q2
Mill
ions
Project Funding - Cumulative by Quarter
Budget Forecast Committed
Budgeted: Forecast: Variance:
$62,367,160$60,921,184$1,445,976
Current Contingency $3,100,651 Language Translations Services ($50,000) TOP Offset (Sogeti-Deloitte) ($152,977) Updated Contingency $2,897,674 Current Budget Positive Variance $1,445,976 Available Budget $4,343,650
Potential Allocations RAAC/SIDES Contingency (TBD) DEO CR support (TBD) Post Release 1.0 Change Requests (TBD) SSRC Off-Site Tape Backup (TBD) Security Assessment & ($75,000)
Intrusion Vulnerability Testing Project Connect 9
Core Development Interim Gate signed-off One month ahead of schedule
Amendment 8 has been signed-off Treasury Offset Program plus 11 other Change
Requests Final Production Hardware/Software Order
Language translation (Spanish/Creole) services contract with Languages Unlimited, LLC is signed-off and work proceeding
Project Connect 10
Legacy Treasury Offset Program (TOP) is prepared for Go Live Wednesday, January 16 with the transfer of the first file to the Treasury
Voice over IP upgrade has been kicked off with a completion date pushed to July 26 Resource contention with Data Center Consolidation No Go Live impact at this time
The potential of a July early rollout of the IVR system is dependent on completion of the VoIP rollout by April 1
Project Connect 11
Legacy System completed a data purge in December resulting in an ~10% reduction in overall size Will still be converting over 1,000,000,000 rows of
data
Project Connect 12
Area Start Purged Remainder %Claims 7,566,405 1,828,898 5,737,507 24%Claim Charge 6,419,481 1,217,056 5,202,425 19%Claimant History 553,320,125 51,047,661 502,272,464 9%History Transcript 78,790,878 16,300,484 62,490,394 21%
Amendment 8 Design complete Several artifacts have preliminary approval Final approval scheduled for this week (late, no project
impact) Reemployment Assistance Appeals Commission
(RAAC) CR190 Release 1.1/Go Live ASAP Under discussion to move to Release 1.0
State Information Exchange System (SIDES) CR189
Assessment complete Release 1.2/by December 2013
Project Connect 13
The Reporting Database (production clone) will be housed in the Production Environment Ensures security Can mitigate contention via Oracle Resource Manager Nightly refresh
Project Connect 14
Non-Core Development and Component Testing continue on schedule
System Test starts this week With 2,500 scripts completed so far Completed end-to-end test Claims to Payment Prioritizing defects going forward
Project Connect 15
Conversion Preparing for next Mock Conversion test beginning
Friday, January 18 Expect to load Mock Conversion results to converted
data application test environment week of January 21 Risk: Timing for discontinuation of paper checks
Performance Testing Performance Testing on track to meet the Test execution
schedule In the process of identifying top ten slow transactions Finalizing the approach for remediation of slow
transactions
Project Connect 16
Training Preparation of training materials is on track 31 trainers being onboarded A kick off meeting will be held next week to
introduce the training developers to DEO SMEs and trainers and review the 6-month schedule
Will develop a Claims overview (via Webex) and handouts for Claimants to the Workforce One-Stop Offices
Infrastructure Building out our operational procedures for error
detection, assessment/triage, and escalation
Project Connect 17
Project Connect 18
Project Connect 19
Project Connect 20
0
500
1000
1500
2000
2500
3000
15-Aug
15-Jan
31-Jan
28-Feb
Test Execution Original vs. Revised
Original Plan Actual Execution
Revised Plan
Project Connect 21
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
11-Ju
n
18-Ju
n
25-Ju
n
2-Ju
l
9-Ju
l
16-Ju
l
23-Ju
l
30-Ju
l
6-Au
g
13-A
ug
20-A
ug
27-A
ug
3-Se
p
10-S
ep
17-S
ep
24-S
ep
1-O
ct
8-O
ct
15-O
ct
22-O
ct
29-O
ct
5-N
ov
12-N
ov
19-N
ov
26-N
ov
3-De
c
10-D
ec
17-D
ec
24-D
ec
31-D
ec
7-Ja
n
# of
Def
ects
Week Starting
Identified/Resolved Defect Trends
Issues Identified Issues Resolved Issues Open
Projected Identified Projected Resolved Projected Open
Project Connect 22
Project Connect 23
Project Connect 24
Project Connect 25
-20
0
20
40
60
80
100
120
140
160
180 Conversion Target ETL/Table DevelopmentAs of 1/7 Revised (165 ) vs. Actual (153)Planned
Actual
Revised Forecat
Planned - Cumulative
Actual - Cumulative
Revised Forecast - Cumulative
Project Connect 26
2 611 7 11
14 14 13
08
13 13 10 13
2 611 7 11
14 148
0
13
0
20
40
60
80
100
120
140
160
Script CompletionPlanned vs. Actual
Planned
Actual
Planned - Cumulative
Actual - Cumulative
02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan 1-Feb
1
0
1
0
1
2 2
1
2
1
0
2
1
0
1 1
2
1
0
2
4
6
8
10
12
Cycle 1 - Test Execution StatusPlanned vs. Actual
Planned
Actual
Planned - Cumulative
Actual - Cumulative
9-Nov 16-Nov 23-Nov 30-Nov 7-Dec 14-Dec 21-Dec 4-Jan 18-Jan 1-Feb
Project Connect 27
Total Functional CRs Received 208 Withdrawn/Closed (88) Total CRs 120 Amendment 7 (In Development) 27 Amendment 8 (In Design) 12 Amendment 9 (In Impact Assessment) 2 DEO Development (In Development) 13 On Hold Non-Critical 66 Total CRs 120
Project Connect 28
Open risks being actively monitored: Risk #24 Pending Legislation 2013 Session Risk #29 Availability of External System Resources Risk #31 Creole/Spanish Translation Risk #32 System Test Readiness Risk #34 Identifying DEO Trainers Risk #35 Updating SOP Documentation Risk #37 Co-Development Efforts (Deloitte/DEO) Risk #38 Review priority of Amendment 7 Reports Risk #39 Federal Extension of EUC/RES
No Open Issues
Project Connect 29
Implementation went very well Systems is working! A success! Assisted 22,000 people to open online accounts Certified more than 17,000 for benefits Paid out $4 million in claims Enabled nearly 1,000 employers to electronically file
wage reports Major issue was confusion around the EUC
extension and external interfaces Bank did not process the debit card file for two days Biggest visible issue
Federal (ICON/SSA) testing challenges Some conversion and code issues
Project Connect 30
Consistent Information across all channels Single Point Of Contact (POC) for each channel
Press/Claimants (New/Continuing/EUC) Directing folks to the Internet and Call Center v. the
One-Stops Need to explain that wait times will be excessive
Governor & Executive Director Offices, Legislature Executive Dashboard (# Claims, calls, etc.)
Getting the Workforce Centers some help Training/Handouts/POC
Project Connect 31
Staff Big change for staff Change of organization, process/procedures,
roles/responsibilities, and systems Focus on training, awareness and operational
readiness Training play area Get the security roles assigned correctly up front Get the IVR routing and virtual hold set up correctly
Project Connect 32
Go Live Incident/Communications Management Very controlled and disciplined incident escalation
process (War Room) Lots of issues day one that are training,
knowledge, transition related - not defects Triage of incidents - focusing of critical ones first Communicate out known issues, responses,
workarounds via Intranet Need strong leadership, communications and
trust!
Project Connect 33
January 25 Core Development December 21 Interim Gate
February 13 ESC Meeting March 13 ESC Meeting March 15 Core Functionality Tested April 10 ESC Meeting May 8 ESC Meeting May 10 All Functions w/ Prod. Data June 12 ESC Meeting June 14 Testing Complete
Project Connect 34
Project Connect 35
Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting February 13 Adjourn
Project Connect 36
Project CONNECT Independent Verification and Validation Monthly Assessment Report Summary 08 January 2013
Page 38
Topics for discussion
General IV&V overview Overall risk state and trending Key indicators Overall project performance Projected milestone slippage Upcoming IV&V activities Supporting information
Summary of changes IV&V ratings summary Open deficiencies Project milestones Open technology facets
Page 39
General IV&V overview
The Project CONNECT Team has satisfactorily addressed all deficiencies identified by the IV&V Team.
The Core Development Interim 1 Gate was passed on 21 December 2012, 35 calendar days early.
Based on the current schedule performance index (SPI), the Development/Test Phase Gate is projected to be completed 3 days early. All subsequent phase gates are projected to be completed early. The project is within the prescribed control limits.
No new deficiencies identified since the last report.
Overall IV&V risk state: Green
Page 40
Overall risk state and trending
Risk state of Project CONNECT Risk state with trending
Indicates that the area being assessed has critical issues that will result in significant risk to the project most likely resulting in either the inability to achieve the outcomes, inability to meet the projected schedule, or a significant cost over-run. Requires immediate action.
Indicates that the area being assessed has issues that need to be resolved; inefficiencies exist. Current process/method can be used with refinement. Indicates that the area being assessed did not have significant issues to report. Continued monitoring should be performed. Indicates that the area being assessed has incomplete information available for a conclusive finding or is not applicable.
Program
B2B3
B5B6B1
B4
B7B8
B9
BusinessTechnology
T1
T2
T4
T6
T9
P4P1
Risk state with trending
T3
T5
T7T8
P2P3
P6 P8P7
P9
P5
Technology
Program
Business
Functionality
Operationssupport
Non-functionalrequirementsTechnical
architecture
High-levelsystem
architecture
Legacyintegration
Requirementsmapping
Stabilization
Resourcemanagement
Costmanagement
Governance
Risk adjustedfinancials
Performancemanagement
Timemanagement
Riskmanagement
Qualitymanagement
Changemanagement
Businessobjectivesand valuealignment
Businessprocess
Organizationdesign
Cost,benefit and
risk
Benefitstracking
Communication
Complianceand
regulatory
Investmentgovernance
and approval
Reportingand value
monitoring
Functionalrequirements
As of 08 January 2013
P1
P2
P3
P4
P5
P6
P7
P8
P9T1
T2
T3T4
T5
T6T7
T8
T9
B1
B2
B3
B4
B5
B6
B7
B8
B9
Page 41
Key indicators
Indicator Value Comment
Is the project approach sound? Yes
Is the project on time? Yes The project is within the prescribed control limits.
Is the project on budget? Yes
Is scope being managed so there is no scope creep?
Yes The work being completed as part of the project is within the scope of the project as defined for Project CONNECT.
What are the projects future risks? N/A The Project CONNECT Team has satisfactorily addressed all deficiencies identified by the IV&V Team.
Are the projects risks increasing or decreasing?
Decreasing The Project CONNECT Team has satisfactorily addressed all deficiencies identified by the IV&V Team.
Are there new or emerging technological solutions that will affect the projects technology assumptions?
No New and emerging technologies were considered in the Feasibility Study.
None have an adverse effect on the projects technological assumptions.
Page 42
Overall project performance
0.70
0.80
0.90
1.00
1.10
1.20
1.30
0.70 0.80 0.90 1.00 1.10 1.20 1.30
SPI
CPIPC project performance
Ahead of schedule and underspentBehind schedule and underspent
Ahead of schedule and overspentBehind schedule and overspent
SPI = 1.01CPI = 0.95
Page 43
Projected milestone slippage
0
0
0
4
0
245
210
210
0
-2
-35
-2
-3
-3
-3
-50 0 50 100 150 200 250 300
Planning Interim Gate
Planning Phase Gate
Define Interim Gate 1
Define Interim Gate 2
Define Phase Gate
Design Interim Gate 1
Design Interim Gate 2
Design Interim Gate 3
Design Phase Gate
Interim Development Interim Gate
Core Development Interim 1 Gate
Remaining Development Interim 2 Gate
Development/Test Phase Gate
UAT Phase Gate
Implementation Phase Gate
Number of calendar days
PC projected milestone slippage
Dec 2012
Nov 2012
Oct 2012
Sep 2012
Aug 2012
Schedule re-baselined
Page 44
Upcoming IV&V activities
Participate in PC meetings IV&V review meetings with the PC Project Team Executive Steering Committee meetings
Review integrated master schedule and associated project performance reports
Deliverable review schedule is as follows:
Deliverable Planned finish Actual finish Comment
UC3-06A, Project Management Documents 24 August 2011 30 September 2011 Complete
UC3-06B, Requirements Validation 19 August 2011 19 August 2011 Complete
UC3-06C, Design Documents Canceled
UC3-06D, Development Canceled
PC-06E, Testing 21 August 2012 23 August 2012 Complete
PC-06F, Data Conversion Canceled
PC-06G, Training Canceled
PC-06H, Implementation 01 November 2013
Page 45
Summary of changes
Item Description
Deficiencies addressed
There are no open deficiencies.
New deficiencies No new deficiencies identified since the last report
Risk ratings No risk rating changes since the last report.
Maturity ratings No maturity rating changes since the last report.
Interviews conducted No interviews conducted since the last report.
Artifacts received Artifacts received include deliverables, Executive Steering Committee (ESC) meeting materials, phase gate review board materials, schedule, and status reports.
Supporting information
Page 46
IV&V ratings summary Supporting information
0
5
10
15
20
25
30
Number
IV&V cube facet ratings and open deficiencies per month
Critical Issues Inefficiencies No Issues Not Evaluated Open Deficiencies
Page 47
Open deficiencies
No. Areas Deficiency Implications Recommendations
None None None None
Supporting information
There are no open IV&V deficiencies with Project CONNECT.
Page 48
Project milestones
WBS Title Completion date
Original Scheduled Planned Projected Actual
2.2.1.1 Design Phase Gate 12/16/2011 06/29/2012 06/29/2012 06/29/2012 06/29/2012
3.2.4.12 Amendment 7 CRs Design 11/02/2012 11/02/2012 11/28/2012
3.8.1 Interim Development Interim Gate 09/28/2012 09/28/2012 09/26/2012 09/26/2012
3.8.2 Core Development Interim 1 Gate 01/25/2013 01/25/2013 01/23/2013 12/21/2012
3.8.3 Remaining Development Interim 2 Gate 04/11/2013 04/11/2013 04/09/2013
3.8.4 Development/Test Phase Gate (includes Amendment 7)
07/18/2013 07/18/2013 07/15/2013
4.8.1 UAT Phase Gate 11/16/2012 10/18/2013 10/18/2013 10/15/2013
5.9.1 Implementation Phase Gate (includes Amendment 7) 12/14/2012 11/15/2013 12/03/2013 11/30/2013
Supporting information
Late
Page 49
Open technology facets
Facet Expectations Project deliverable Planned completion Status
T2 : Operations support
An organizational structure and support strategy to manage the new implementation is in place.
Tools exist for tracking performance of application at object levels.
A maintenance strategy is developed to manage modification, migration, and retirement of products according to the release strategy.
Ongoing knowledge transfer, as systems are developed.
A detailed training strategy exists for training the different categories of business and technical users of the system for them to be able to adopt to the system and use it more effectively.
Training documents are in place. Training strategy is agreed upon, communicated
and being executed. Trainers are qualified via agreed upon selection
process. Training materials are standard across all
modules and functions and are capturing an adequate level of detail.
3.12 PMP Human Resource Management and Staffing Plan
06/17/11 Complete
3.14 PMP Knowledge Management Plan
06/17/11 Complete
5 Validated Requirements Document
06/24/11 07/15/11 08/05/11
Complete
24 Operations Documentation
07/25/13
26 Training Plan 12/07/12 Complete
27 Training (execution) 10/10/13
28 Production System Implementation Plan
09/12/13
30 System Operations and Maintenance Plan
11/15/13
Supporting information
Page 50
Open technology facets (continued)
Facet Expectations Project deliverable Planned completion Status
T9 : Stabilization An extended team has been defined across the organization and is working as an extension of the project team. Tasks have been assigned and key metrics are in place to monitor progress.
Long-term sustainability plans are in place to keep support and maintenance of the implementation viable.
Long-term vendor contracts are implemented to maintain the system in the absence of an in-house capability to maintain the system.
A vendor management body is established to maintain the relationship with vendors to facilitate smooth delivery of outsourced services.
30 System Maintenance and Operations Plan
11/15/13
KPIs
12-month Warranty Period
12-months Operations Support and Maintenance Agreement
Executed contracts and license agreements
Supporting information
Seek approval to pass through the Core Development Interim Gate
Project Connect 51
Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting February 13 Adjourn
Project Connect 52
FY12/13 Spend Plan Graph FY12/13 Spend Plan Details
Project Connect 53
Project Connect 54
0
5
10
15
20
25
Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13
Mill
ions
FY 2012-2013 Project Funding - Cumulative by Month
FY Budget Forecast Committed
Budgeted: $ 22,431,336Forecast: 22,224,153
Variance: $ 207,183
Project Connect 55
Budget Committed Budget Committed Budget Committed Budget Forecast Budget Forecast Budget ForecastOPS
Funding 17,605 16,078 16,940 15,524 3,735 6,591 3,735 4,424 3,735 3,009 3,735 6,146
ExpensesFunding 44,346 43,375 463,994 218,916 83,825 37,143 83,826 82,437 83,827 210,993 472,277 320,758
OCOFunding 0 2,257 155,000 178,516 0 0 0 0 0 0 1,170,785 40,898
Contracted ServicesProject Management & Support 487,190 256,716 504,707 290,226 481,910 284,677 481,910 328,728 511,485 310,168 461,510 271,929IV&V Services 46,456 46,456 77,762 77,762 53,956 53,956 53,956 53,956 53,956 53,956 53,956 53,956Benefits Realization Strategy 0 0 0 0 0 0 0 0 0 0 6,388 0Organizational Change Management 0 0 0 0 0 0 0 0 0 0 0 0System Integrator (SI) Services 5,670,467 5,670,467 122,805 122,805 1,922,805 1,922,805 122,805 122,805 1,732,805 1,557,805 122,805 672,805SI Hardware & Maintenance 0 0 0 0 0 (10,040) 0 0 1,282,389 0 0 1,369,638SI Software & Maintenance 0 0 0 0 0 0 0 10,040 40,986 0 0 159,714Project Reserves 0 0 0 0 0 0 0 0 0 0 0 0
Total Contracted Services 6,204,113 5,973,638 705,274 490,793 2,458,671 2,251,398 658,671 515,528 3,621,621 1,921,928 644,659 2,528,041
Total Budget Allocation & Spend 6,266,064 6,035,348 1,341,208 903,749 2,546,231 2,295,131 746,232 602,390 3,709,183 2,135,930 2,291,456 2,895,843
FY 2012-2013 Budget Allocation and Spend by Month - Q1 & Q2Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12
Project Connect 56
Budget Forecast Budget Forecast Budget Forecast Budget Forecast Budget Forecast Budget ForecastOPS
Funding 3,735 3,954 3,735 3,954 3,735 3,954 3,735 3,954 3,735 3,954 3,735 3,954
ExpensesFunding 44,784 314,971 44,784 68,820 66,284 115,320 66,284 115,320 66,284 93,792 66,284 1,191,882
OCOFunding 0 68,576 0 0 0 0 0 500,000 0 63,001 0 0
Contracted ServicesProject Management & Support 455,510 533,634 455,510 526,242 455,510 526,242 455,510 526,242 455,510 517,532 455,514 608,099IV&V Services 53,956 53,956 7,500 7,500 53,956 53,956 7,500 7,500 53,956 53,956 7,500 7,500Benefits Realization Strategy 6,388 7,453 6,388 7,453 6,388 7,453 6,388 7,453 6,388 7,453 6,388 7,453Organizational Change Management 0 0 0 0 0 0 0 0 0 0 0 0System Integrator (SI) Services 550,000 158,283 0 0 0 0 550,000 725,000 0 0 0 450,000SI Hardware & Maintenance 0 0 0 0 0 0 0 0 0 0 84,890 0SI Software & Maintenance 0 0 0 0 0 0 0 0 0 0 1,013,200 0Project Reserves 0 0 0 0 0 0 0 0 0 0 0 0
Total Contracted Services 1,065,854 753,326 469,398 541,195 515,854 587,650 1,019,398 1,266,195 515,854 578,940 1,567,492 1,073,052
Total Budget Allocation & Spend 1,114,373 1,140,827 517,917 613,968 585,873 706,924 1,089,417 1,885,468 585,873 739,687 1,637,511 2,268,887
FY 2012-2013 Budget Allocation and Spend by Month - Q3 & Q4Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13
Executive Steering CommitteeUpdateAgendaProject Status ReportProject TimelineProject TimelineSchedule Performance IndexBudget & EAC SummaryBudget TrackingManagement Reserve AllocationOverall Project StatusOverall Project StatusOverall Project StatusDesign ActivitiesDesign ActivitiesDevelopment StatusImplementation StatusImplementation StatusDevelopmentComponent TestSubsystem TestSubsystem Test Defect TrackingSystem Test Script DevelopmentSystem Test Script ExecutionInterface TestingConversionPerformance TestingLegacy Data Quality TrackingChange Requests SummaryCurrent Risks / IssuesNew Mexico Go Live Trip ReportNew Mexico Key - Lessons LearnedNew Mexico Key - Lessons LearnedNew Mexico Key - Lessons LearnedKey Project DatesQuestions?AgendaProject CONNECTIndependent Verification and ValidationMonthly Assessment Report Summary08 January 2013Topics for discussionGeneral IV&V overviewOverall risk state and trendingKey indicatorsOverall project performanceProjected milestone slippageUpcoming IV&V activitiesSummary of changesIV&V ratings summaryOpen deficienciesProject milestonesOpen technology facetsOpen technology facets(continued)Next StepsAgendaAttachmentsFY12/13 Spend Plan TrackingFY12/13 Spend Plan 1st HalfFY12/13 Spend Plan 2nd Half