  • January 16, 2013

    Project Connect

  • Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting February 13 Adjourn

    Project Connect 2

  • Budget and Timeline Project Update Current and Upcoming Activities Risks and Issues New Mexico Trip Report Key Project Dates

    Welcome to our newest ESC Member

    Tony Powell, CIO, Department of Revenue

    Project Connect 3

  • Project Connect 4

  • Project Connect 5

  • Project Connect 6

    SPI as of December 21: 1.01 CPI as of December 15: .95

  • Project Connect 7

    Rebaselined Budget

    Allocated Contingency

    & Management

    Reserves

    Supplemental Budget Requests

    REA GrantUpdated Project Budget

    Estimate at Completion

    Project Variance

    Project FundingOPS 217,770 0 0 0 217,770 221,368 (3,598)Expenses 7,240,310 1,013,200 0 0 8,253,510 8,467,240 (213,730)OCO (Hardware) 1,441,425 (184,637) 0 0 1,256,788 968,889 287,899 Contracted Services

    Project Management & SupportProject Management Office 2,019,270 0 0 0 2,019,270 2,019,270 0Project & Operational Support 3,694,500 (749,261) 1,082,350 119,474 4,147,063 4,012,685 134,378Outside Legal 230,652 0 0 0 230,652 230,652 0ITN Development 512,700 0 0 0 512,700 512,700 0Business Transition 3,945,916 0 0 134,730 4,080,646 4,064,881 15,765Other Contracted Services 164,790 50,000 0 0 214,790 230,358 (15,568)

    Total Project Management & Support 10,567,828 (699,261) 1,082,350 254,204 11,205,121 11,070,545 134,575 IV&V Services 2,019,940 0 0 75,000 2,094,940 2,094,940 0 Benefits Realization Strategy 239,391 0 0 0 239,391 239,391 0 Organizational Change Management 467,520 0 0 0 467,520 467,520 0 System Integrator (SI) Services 28,285,557 902,238 0 1,054,586 30,242,381 29,187,795 1,054,585 SI Hardware & Maintenance 2,607,493 184,637 0 0 2,792,130 2,599,812 192,318 SI Software & Maintenance 6,488,115 (1,013,200) 0 0 5,474,915 5,603,682 (128,767)Project Reserves 122,695 0 0 0 122,695 0 122,695

    Project Funding Totals 59,698,044 202,977 1,082,350 1,383,790 62,367,160 60,921,184 1,445,976 Cotingency/Management Reserves 3,100,651 2,897,674 622,460

  • Project Connect 8

    0

    10

    20

    30

    40

    50

    60

    70

    FY11Q1

    FY11Q2

    FY11Q3

    FY11Q4

    FY12Q1

    FY12Q2

    FY12Q3

    FY12Q4

    FY13Q1

    FY13Q2

    FY13Q3

    FY13Q4

    FY14Q1

    FY14Q2

    FY14Q3

    FY14Q4

    FY 15 Q1

    FY 15 Q2

    Mill

    ions

    Project Funding - Cumulative by Quarter

    Budget Forecast Committed

    Budgeted: Forecast: Variance:

    $62,367,160$60,921,184$1,445,976

  • Current Contingency $3,100,651 Language Translations Services ($50,000) TOP Offset (Sogeti-Deloitte) ($152,977) Updated Contingency $2,897,674 Current Budget Positive Variance $1,445,976 Available Budget $4,343,650

    Potential Allocations RAAC/SIDES Contingency (TBD) DEO CR support (TBD) Post Release 1.0 Change Requests (TBD) SSRC Off-Site Tape Backup (TBD) Security Assessment & ($75,000)

    Intrusion Vulnerability Testing Project Connect 9

  • Core Development Interim Gate signed-off One month ahead of schedule

    Amendment 8 has been signed-off Treasury Offset Program plus 11 other Change

    Requests Final Production Hardware/Software Order

    Language translation (Spanish/Creole) services contract with Languages Unlimited, LLC is signed-off and work proceeding

    Project Connect 10

  • Legacy Treasury Offset Program (TOP) is prepared for Go Live Wednesday, January 16 with the transfer of the first file to the Treasury

    Voice over IP upgrade has been kicked off with a completion date pushed to July 26 Resource contention with Data Center Consolidation No Go Live impact at this time

    The potential of a July early rollout of the IVR system is dependent on completion of the VoIP rollout by April 1

    Project Connect 11

  • Legacy System completed a data purge in December resulting in an ~10% reduction in overall size Will still be converting over 1,000,000,000 rows of

    data

    Project Connect 12

    Area Start Purged Remainder %Claims 7,566,405 1,828,898 5,737,507 24%Claim Charge 6,419,481 1,217,056 5,202,425 19%Claimant History 553,320,125 51,047,661 502,272,464 9%History Transcript 78,790,878 16,300,484 62,490,394 21%

  • Amendment 8 Design complete Several artifacts have preliminary approval Final approval scheduled for this week (late, no project

    impact) Reemployment Assistance Appeals Commission

    (RAAC) CR190 Release 1.1/Go Live ASAP Under discussion to move to Release 1.0

    State Information Exchange System (SIDES) CR189

    Assessment complete Release 1.2/by December 2013

    Project Connect 13

  • The Reporting Database (production clone) will be housed in the Production Environment Ensures security Can mitigate contention via Oracle Resource Manager Nightly refresh

    Project Connect 14

  • Non-Core Development and Component Testing continue on schedule

    System Test starts this week With 2,500 scripts completed so far Completed end-to-end test Claims to Payment Prioritizing defects going forward

    Project Connect 15

  • Conversion Preparing for next Mock Conversion test beginning

    Friday, January 18 Expect to load Mock Conversion results to converted

    data application test environment week of January 21 Risk: Timing for discontinuation of paper checks

    Performance Testing Performance Testing on track to meet the Test execution

    schedule In the process of identifying top ten slow transactions Finalizing the approach for remediation of slow

    transactions

    Project Connect 16

  • Training Preparation of training materials is on track 31 trainers being onboarded A kick off meeting will be held next week to

    introduce the training developers to DEO SMEs and trainers and review the 6-month schedule

    Will develop a Claims overview (via Webex) and handouts for Claimants to the Workforce One-Stop Offices

    Infrastructure Building out our operational procedures for error

    detection, assessment/triage, and escalation

    Project Connect 17

  • Project Connect 18

  • Project Connect 19

  • Project Connect 20

    0

    500

    1000

    1500

    2000

    2500

    3000

    15-Aug

    15-Jan

    31-Jan

    28-Feb

    Test Execution Original vs. Revised

    Original Plan Actual Execution

    Revised Plan

  • Project Connect 21

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    4500

    5000

    11-Ju

    n

    18-Ju

    n

    25-Ju

    n

    2-Ju

    l

    9-Ju

    l

    16-Ju

    l

    23-Ju

    l

    30-Ju

    l

    6-Au

    g

    13-A

    ug

    20-A

    ug

    27-A

    ug

    3-Se

    p

    10-S

    ep

    17-S

    ep

    24-S

    ep

    1-O

    ct

    8-O

    ct

    15-O

    ct

    22-O

    ct

    29-O

    ct

    5-N

    ov

    12-N

    ov

    19-N

    ov

    26-N

    ov

    3-De

    c

    10-D

    ec

    17-D

    ec

    24-D

    ec

    31-D

    ec

    7-Ja

    n

    # of

    Def

    ects

    Week Starting

    Identified/Resolved Defect Trends

    Issues Identified Issues Resolved Issues Open

    Projected Identified Projected Resolved Projected Open

  • Project Connect 22

  • Project Connect 23

  • Project Connect 24

  • Project Connect 25

    -20

    0

    20

    40

    60

    80

    100

    120

    140

    160

    180 Conversion Target ETL/Table DevelopmentAs of 1/7 Revised (165 ) vs. Actual (153)Planned

    Actual

    Revised Forecat

    Planned - Cumulative

    Actual - Cumulative

    Revised Forecast - Cumulative

  • Project Connect 26

    2 611 7 11

    14 14 13

    08

    13 13 10 13

    2 611 7 11

    14 148

    0

    13

    0

    20

    40

    60

    80

    100

    120

    140

    160

    Script CompletionPlanned vs. Actual

    Planned

    Actual

    Planned - Cumulative

    Actual - Cumulative

    02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan 1-Feb

    1

    0

    1

    0

    1

    2 2

    1

    2

    1

    0

    2

    1

    0

    1 1

    2

    1

    0

    2

    4

    6

    8

    10

    12

    Cycle 1 - Test Execution StatusPlanned vs. Actual

    Planned

    Actual

    Planned - Cumulative

    Actual - Cumulative

    9-Nov 16-Nov 23-Nov 30-Nov 7-Dec 14-Dec 21-Dec 4-Jan 18-Jan 1-Feb

  • Project Connect 27

  • Total Functional CRs Received 208 Withdrawn/Closed (88) Total CRs 120 Amendment 7 (In Development) 27 Amendment 8 (In Design) 12 Amendment 9 (In Impact Assessment) 2 DEO Development (In Development) 13 On Hold Non-Critical 66 Total CRs 120

    Project Connect 28

  • Open risks being actively monitored: Risk #24 Pending Legislation 2013 Session Risk #29 Availability of External System Resources Risk #31 Creole/Spanish Translation Risk #32 System Test Readiness Risk #34 Identifying DEO Trainers Risk #35 Updating SOP Documentation Risk #37 Co-Development Efforts (Deloitte/DEO) Risk #38 Review priority of Amendment 7 Reports Risk #39 Federal Extension of EUC/RES

    No Open Issues

    Project Connect 29

  • Implementation went very well Systems is working! A success! Assisted 22,000 people to open online accounts Certified more than 17,000 for benefits Paid out $4 million in claims Enabled nearly 1,000 employers to electronically file

    wage reports Major issue was confusion around the EUC

    extension and external interfaces Bank did not process the debit card file for two days Biggest visible issue

    Federal (ICON/SSA) testing challenges Some conversion and code issues

    Project Connect 30

  • Consistent Information across all channels Single Point Of Contact (POC) for each channel

    Press/Claimants (New/Continuing/EUC) Directing folks to the Internet and Call Center v. the

    One-Stops Need to explain that wait times will be excessive

    Governor & Executive Director Offices, Legislature Executive Dashboard (# Claims, calls, etc.)

    Getting the Workforce Centers some help Training/Handouts/POC

    Project Connect 31

  • Staff Big change for staff Change of organization, process/procedures,

    roles/responsibilities, and systems Focus on training, awareness and operational

    readiness Training play area Get the security roles assigned correctly up front Get the IVR routing and virtual hold set up correctly

    Project Connect 32

  • Go Live Incident/Communications Management Very controlled and disciplined incident escalation

    process (War Room) Lots of issues day one that are training,

    knowledge, transition related - not defects Triage of incidents - focusing of critical ones first Communicate out known issues, responses,

    workarounds via Intranet Need strong leadership, communications and

    trust!

    Project Connect 33

  • January 25 Core Development December 21 Interim Gate

    February 13 ESC Meeting March 13 ESC Meeting March 15 Core Functionality Tested April 10 ESC Meeting May 8 ESC Meeting May 10 All Functions w/ Prod. Data June 12 ESC Meeting June 14 Testing Complete

    Project Connect 34

  • Project Connect 35

  • Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting February 13 Adjourn

    Project Connect 36

  • Project CONNECT Independent Verification and Validation Monthly Assessment Report Summary 08 January 2013

  • Page 38

    Topics for discussion

    General IV&V overview Overall risk state and trending Key indicators Overall project performance Projected milestone slippage Upcoming IV&V activities Supporting information

    Summary of changes IV&V ratings summary Open deficiencies Project milestones Open technology facets

  • Page 39

    General IV&V overview

    The Project CONNECT Team has satisfactorily addressed all deficiencies identified by the IV&V Team.

    The Core Development Interim 1 Gate was passed on 21 December 2012, 35 calendar days early.

    Based on the current schedule performance index (SPI), the Development/Test Phase Gate is projected to be completed 3 days early. All subsequent phase gates are projected to be completed early. The project is within the prescribed control limits.

    No new deficiencies identified since the last report.

    Overall IV&V risk state: Green

  • Page 40

    Overall risk state and trending

    Risk state of Project CONNECT Risk state with trending

    Indicates that the area being assessed has critical issues that will result in significant risk to the project most likely resulting in either the inability to achieve the outcomes, inability to meet the projected schedule, or a significant cost over-run. Requires immediate action.

    Indicates that the area being assessed has issues that need to be resolved; inefficiencies exist. Current process/method can be used with refinement. Indicates that the area being assessed did not have significant issues to report. Continued monitoring should be performed. Indicates that the area being assessed has incomplete information available for a conclusive finding or is not applicable.

    Program

    B2B3

    B5B6B1

    B4

    B7B8

    B9

    BusinessTechnology

    T1

    T2

    T4

    T6

    T9

    P4P1

    Risk state with trending

    T3

    T5

    T7T8

    P2P3

    P6 P8P7

    P9

    P5

    Technology

    Program

    Business

    Functionality

    Operationssupport

    Non-functionalrequirementsTechnical

    architecture

    High-levelsystem

    architecture

    Legacyintegration

    Requirementsmapping

    Stabilization

    Resourcemanagement

    Costmanagement

    Governance

    Risk adjustedfinancials

    Performancemanagement

    Timemanagement

    Riskmanagement

    Qualitymanagement

    Changemanagement

    Businessobjectivesand valuealignment

    Businessprocess

    Organizationdesign

    Cost,benefit and

    risk

    Benefitstracking

    Communication

    Complianceand

    regulatory

    Investmentgovernance

    and approval

    Reportingand value

    monitoring

    Functionalrequirements

    As of 08 January 2013

    P1

    P2

    P3

    P4

    P5

    P6

    P7

    P8

    P9T1

    T2

    T3T4

    T5

    T6T7

    T8

    T9

    B1

    B2

    B3

    B4

    B5

    B6

    B7

    B8

    B9

  • Page 41

    Key indicators

    Indicator Value Comment

    Is the project approach sound? Yes

    Is the project on time? Yes The project is within the prescribed control limits.

    Is the project on budget? Yes

    Is scope being managed so there is no scope creep?

    Yes The work being completed as part of the project is within the scope of the project as defined for Project CONNECT.

    What are the projects future risks? N/A The Project CONNECT Team has satisfactorily addressed all deficiencies identified by the IV&V Team.

    Are the projects risks increasing or decreasing?

    Decreasing The Project CONNECT Team has satisfactorily addressed all deficiencies identified by the IV&V Team.

    Are there new or emerging technological solutions that will affect the projects technology assumptions?

    No New and emerging technologies were considered in the Feasibility Study.

    None have an adverse effect on the projects technological assumptions.

  • Page 42

    Overall project performance

    0.70

    0.80

    0.90

    1.00

    1.10

    1.20

    1.30

    0.70 0.80 0.90 1.00 1.10 1.20 1.30

    SPI

    CPIPC project performance

    Ahead of schedule and underspentBehind schedule and underspent

    Ahead of schedule and overspentBehind schedule and overspent

    SPI = 1.01CPI = 0.95

  • Page 43

    Projected milestone slippage

    0

    0

    0

    4

    0

    245

    210

    210

    0

    -2

    -35

    -2

    -3

    -3

    -3

    -50 0 50 100 150 200 250 300

    Planning Interim Gate

    Planning Phase Gate

    Define Interim Gate 1

    Define Interim Gate 2

    Define Phase Gate

    Design Interim Gate 1

    Design Interim Gate 2

    Design Interim Gate 3

    Design Phase Gate

    Interim Development Interim Gate

    Core Development Interim 1 Gate

    Remaining Development Interim 2 Gate

    Development/Test Phase Gate

    UAT Phase Gate

    Implementation Phase Gate

    Number of calendar days

    PC projected milestone slippage

    Dec 2012

    Nov 2012

    Oct 2012

    Sep 2012

    Aug 2012

    Schedule re-baselined

  • Page 44

    Upcoming IV&V activities

    Participate in PC meetings IV&V review meetings with the PC Project Team Executive Steering Committee meetings

    Review integrated master schedule and associated project performance reports

    Deliverable review schedule is as follows:

    Deliverable Planned finish Actual finish Comment

    UC3-06A, Project Management Documents 24 August 2011 30 September 2011 Complete

    UC3-06B, Requirements Validation 19 August 2011 19 August 2011 Complete

    UC3-06C, Design Documents Canceled

    UC3-06D, Development Canceled

    PC-06E, Testing 21 August 2012 23 August 2012 Complete

    PC-06F, Data Conversion Canceled

    PC-06G, Training Canceled

    PC-06H, Implementation 01 November 2013

  • Page 45

    Summary of changes

    Item Description

    Deficiencies addressed

    There are no open deficiencies.

    New deficiencies No new deficiencies identified since the last report

    Risk ratings No risk rating changes since the last report.

    Maturity ratings No maturity rating changes since the last report.

    Interviews conducted No interviews conducted since the last report.

    Artifacts received Artifacts received include deliverables, Executive Steering Committee (ESC) meeting materials, phase gate review board materials, schedule, and status reports.

    Supporting information

  • Page 46

    IV&V ratings summary Supporting information

    0

    5

    10

    15

    20

    25

    30

    Number

    IV&V cube facet ratings and open deficiencies per month

    Critical Issues Inefficiencies No Issues Not Evaluated Open Deficiencies

  • Page 47

    Open deficiencies

    No. Areas Deficiency Implications Recommendations

    None None None None

    Supporting information

    There are no open IV&V deficiencies with Project CONNECT.

  • Page 48

    Project milestones

    WBS Title Completion date

    Original Scheduled Planned Projected Actual

    2.2.1.1 Design Phase Gate 12/16/2011 06/29/2012 06/29/2012 06/29/2012 06/29/2012

    3.2.4.12 Amendment 7 CRs Design 11/02/2012 11/02/2012 11/28/2012

    3.8.1 Interim Development Interim Gate 09/28/2012 09/28/2012 09/26/2012 09/26/2012

    3.8.2 Core Development Interim 1 Gate 01/25/2013 01/25/2013 01/23/2013 12/21/2012

    3.8.3 Remaining Development Interim 2 Gate 04/11/2013 04/11/2013 04/09/2013

    3.8.4 Development/Test Phase Gate (includes Amendment 7)

    07/18/2013 07/18/2013 07/15/2013

    4.8.1 UAT Phase Gate 11/16/2012 10/18/2013 10/18/2013 10/15/2013

    5.9.1 Implementation Phase Gate (includes Amendment 7) 12/14/2012 11/15/2013 12/03/2013 11/30/2013

    Supporting information

    Late

  • Page 49

    Open technology facets

    Facet Expectations Project deliverable Planned completion Status

    T2 : Operations support

    An organizational structure and support strategy to manage the new implementation is in place.

    Tools exist for tracking performance of application at object levels.

    A maintenance strategy is developed to manage modification, migration, and retirement of products according to the release strategy.

    Ongoing knowledge transfer, as systems are developed.

    A detailed training strategy exists for training the different categories of business and technical users of the system for them to be able to adopt to the system and use it more effectively.

    Training documents are in place. Training strategy is agreed upon, communicated

    and being executed. Trainers are qualified via agreed upon selection

    process. Training materials are standard across all

    modules and functions and are capturing an adequate level of detail.

    3.12 PMP Human Resource Management and Staffing Plan

    06/17/11 Complete

    3.14 PMP Knowledge Management Plan

    06/17/11 Complete

    5 Validated Requirements Document

    06/24/11 07/15/11 08/05/11

    Complete

    24 Operations Documentation

    07/25/13

    26 Training Plan 12/07/12 Complete

    27 Training (execution) 10/10/13

    28 Production System Implementation Plan

    09/12/13

    30 System Operations and Maintenance Plan

    11/15/13

    Supporting information

  • Page 50

    Open technology facets (continued)

    Facet Expectations Project deliverable Planned completion Status

    T9 : Stabilization An extended team has been defined across the organization and is working as an extension of the project team. Tasks have been assigned and key metrics are in place to monitor progress.

    Long-term sustainability plans are in place to keep support and maintenance of the implementation viable.

    Long-term vendor contracts are implemented to maintain the system in the absence of an in-house capability to maintain the system.

    A vendor management body is established to maintain the relationship with vendors to facilitate smooth delivery of outsourced services.

    30 System Maintenance and Operations Plan

    11/15/13

    KPIs

    12-month Warranty Period

    12-months Operations Support and Maintenance Agreement

    Executed contracts and license agreements

    Supporting information

  • Seek approval to pass through the Core Development Interim Gate

    Project Connect 51

  • Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting February 13 Adjourn

    Project Connect 52

  • FY12/13 Spend Plan Graph FY12/13 Spend Plan Details

    Project Connect 53

  • Project Connect 54

    0

    5

    10

    15

    20

    25

    Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Mill

    ions

    FY 2012-2013 Project Funding - Cumulative by Month

    FY Budget Forecast Committed

    Budgeted: $ 22,431,336Forecast: 22,224,153

    Variance: $ 207,183

  • Project Connect 55

    Budget Committed Budget Committed Budget Committed Budget Forecast Budget Forecast Budget ForecastOPS

    Funding 17,605 16,078 16,940 15,524 3,735 6,591 3,735 4,424 3,735 3,009 3,735 6,146

    ExpensesFunding 44,346 43,375 463,994 218,916 83,825 37,143 83,826 82,437 83,827 210,993 472,277 320,758

    OCOFunding 0 2,257 155,000 178,516 0 0 0 0 0 0 1,170,785 40,898

    Contracted ServicesProject Management & Support 487,190 256,716 504,707 290,226 481,910 284,677 481,910 328,728 511,485 310,168 461,510 271,929IV&V Services 46,456 46,456 77,762 77,762 53,956 53,956 53,956 53,956 53,956 53,956 53,956 53,956Benefits Realization Strategy 0 0 0 0 0 0 0 0 0 0 6,388 0Organizational Change Management 0 0 0 0 0 0 0 0 0 0 0 0System Integrator (SI) Services 5,670,467 5,670,467 122,805 122,805 1,922,805 1,922,805 122,805 122,805 1,732,805 1,557,805 122,805 672,805SI Hardware & Maintenance 0 0 0 0 0 (10,040) 0 0 1,282,389 0 0 1,369,638SI Software & Maintenance 0 0 0 0 0 0 0 10,040 40,986 0 0 159,714Project Reserves 0 0 0 0 0 0 0 0 0 0 0 0

    Total Contracted Services 6,204,113 5,973,638 705,274 490,793 2,458,671 2,251,398 658,671 515,528 3,621,621 1,921,928 644,659 2,528,041

    Total Budget Allocation & Spend 6,266,064 6,035,348 1,341,208 903,749 2,546,231 2,295,131 746,232 602,390 3,709,183 2,135,930 2,291,456 2,895,843

    FY 2012-2013 Budget Allocation and Spend by Month - Q1 & Q2Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12

  • Project Connect 56

    Budget Forecast Budget Forecast Budget Forecast Budget Forecast Budget Forecast Budget ForecastOPS

    Funding 3,735 3,954 3,735 3,954 3,735 3,954 3,735 3,954 3,735 3,954 3,735 3,954

    ExpensesFunding 44,784 314,971 44,784 68,820 66,284 115,320 66,284 115,320 66,284 93,792 66,284 1,191,882

    OCOFunding 0 68,576 0 0 0 0 0 500,000 0 63,001 0 0

    Contracted ServicesProject Management & Support 455,510 533,634 455,510 526,242 455,510 526,242 455,510 526,242 455,510 517,532 455,514 608,099IV&V Services 53,956 53,956 7,500 7,500 53,956 53,956 7,500 7,500 53,956 53,956 7,500 7,500Benefits Realization Strategy 6,388 7,453 6,388 7,453 6,388 7,453 6,388 7,453 6,388 7,453 6,388 7,453Organizational Change Management 0 0 0 0 0 0 0 0 0 0 0 0System Integrator (SI) Services 550,000 158,283 0 0 0 0 550,000 725,000 0 0 0 450,000SI Hardware & Maintenance 0 0 0 0 0 0 0 0 0 0 84,890 0SI Software & Maintenance 0 0 0 0 0 0 0 0 0 0 1,013,200 0Project Reserves 0 0 0 0 0 0 0 0 0 0 0 0

    Total Contracted Services 1,065,854 753,326 469,398 541,195 515,854 587,650 1,019,398 1,266,195 515,854 578,940 1,567,492 1,073,052

    Total Budget Allocation & Spend 1,114,373 1,140,827 517,917 613,968 585,873 706,924 1,089,417 1,885,468 585,873 739,687 1,637,511 2,268,887

    FY 2012-2013 Budget Allocation and Spend by Month - Q3 & Q4Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13

    Executive Steering CommitteeUpdateAgendaProject Status ReportProject TimelineProject TimelineSchedule Performance IndexBudget & EAC SummaryBudget TrackingManagement Reserve AllocationOverall Project StatusOverall Project StatusOverall Project StatusDesign ActivitiesDesign ActivitiesDevelopment StatusImplementation StatusImplementation StatusDevelopmentComponent TestSubsystem TestSubsystem Test Defect TrackingSystem Test Script DevelopmentSystem Test Script ExecutionInterface TestingConversionPerformance TestingLegacy Data Quality TrackingChange Requests SummaryCurrent Risks / IssuesNew Mexico Go Live Trip ReportNew Mexico Key - Lessons LearnedNew Mexico Key - Lessons LearnedNew Mexico Key - Lessons LearnedKey Project DatesQuestions?AgendaProject CONNECTIndependent Verification and ValidationMonthly Assessment Report Summary08 January 2013Topics for discussionGeneral IV&V overviewOverall risk state and trendingKey indicatorsOverall project performanceProjected milestone slippageUpcoming IV&V activitiesSummary of changesIV&V ratings summaryOpen deficienciesProject milestonesOpen technology facetsOpen technology facets(continued)Next StepsAgendaAttachmentsFY12/13 Spend Plan TrackingFY12/13 Spend Plan 1st HalfFY12/13 Spend Plan 2nd Half