I.S.DIVISION ICLEAN Presented By : Madhusudan.G.S PROJECT PLANNING
Aug 27, 2014
I.S.DIVISIONICLEAN
Presented By : Madhusudan.G.S
PROJECT PLANNING
INDEX
Introduction and Definitions Typical Phases of a Project Project Planning Phase Tools and Techniques Project Cost monitoring Summary
DEFINITION OF A PROJECT
A project is a temporary endeavor designed to produce a unique product, service or result, with a defined beginning and end (usually time-constrained, and often constrained by funding or deliverables),undertaken to meet unique goals and objectives, typically to bring about beneficial change or added value.Source : PMBOK (5th Edition)
WHAT IS A PROJECT?
A unique undertaking composed of interrelated activities which has a well defined beginning and end, often involving staff from cross-functional groups, that operates under specific constraints of resources, schedules, and requirements.
Process of application of set of skills and methods of planning, organizing, and managing a project from inception to its successful completion
WHAT IS PROJECT MANAGEMENT?
WHO IS PROJECT MANAGER?
The role responsible for leading and coordinating the project effort from
inception to its successful completion;
WHO IS PROJECT MANAGER?
The role responsible for leading and coordinating the project effort from
inception to its successful completion; the person responsible for making
things happen
WHAT IS PROJECT PLANNING?
A project plan is a model of the process that the project team intends to follow to realise the project objectives. It brings together a number of important aspects of this process including its scope, timing, cost, and associated risks.
The project plan can be viewed as a type of “contract” between the project team members and other stakeholders. It defines” the process by which the objectives will be achieved, and the responsibilities in carrying out this process.
Project plans also underpin a number of other key project management functions including estimating and forecasting, options analysis and decision-making, and performance monitoring and control.
WHO IS RESPONSIBLE FOR PLANNING?
Everyone in the project team should be involved in developing the plan. It should be a collaborative effort.
The project manager should provide leadership in this area but may delegate some of the administrative aspects and detailed analysis to a project support role.
On larger projects there may be one or more dedicated planners.
TYPICAL PROJECT PHASES
Initiate Plan Execute
Commissioning
Close-out
INITIATE PHASE
Initiate Plan Execute Commissioning
Close-out
Project Contract Receipt and Acknowledgement. Techno-commercial verification and clarification with customer Handover from Sales to Projects Internal team Kick-off meeting to understand the scope , time, cost and other constraints. Kick-off meeting with Customer to provide project details and commitments and also to clarify relevant points such as material receipt procedure, working hour restrictions, Approval procedures, etc.,
PLAN PHASE
Initiate Plan Execute Commissioning
Close-out
Develop, Agree and Baseline: Project Budget and contingencies Project Schedule Approvals Plan Cash flow plan Sale Invoicing plan
Release Purchase specifications and Purchase Indents. Release of Purchase Orders Site Preparation works.
EXECUTE PHASE
Initiate Plan Execute Commissioning
Close-out
Review progress periodically by Review meetings (Both internal and with customer) One-to-one meetings Emails, Calls, Etc.,
Update progress on the Baselined Schedule and cost files and take measures control from Cost overruns, Schedule delays, etc., Interactions with Vendors, Customers and Site team for project proceeding.
COMMISSION PHASE
Initiate Plan Execute Commissioning
Close-out
Commissioning of Individual systems for their performance. Integration with related systems Pre-commissioning Checks and Sign-off Commissioning start. Testing for target parameters. Fine tuning to balanced parameters.
CLOSE PHASE
Initiate Plan Execute Commissioning
Close-out
Submit and get the Acceptance / Validation plan approved. Execute the Validation procedures in witness of Customer. Provide required documentation such as Test certificates, Data sheets, Warranty Cards, Etc., to Customer as applicable. Prepare training plan and train customer. Prepare plant operations Manual. And SubmitSubmit As-built Drawings and details
PROJECT PLANNING PHASE
MAJOR DELIVERABLES OF A PROJECT PLAN
PROJECT SCHEDULE PROJECT COST AND BUDGET DOCUMENTS SCOPE OF WORKS STATEMENT QUALITY PLAN SAFETY PLAN RISK MATRIX
PURPOSE OF A SCHEDULE
Provides a commitment about when things will be done
Encourage everyone on the project to see their efforts as part of a whole
Provides a tool for breaking work into manageable chunks
Provides a tool for measuring progress
SCHEDULES VARY BETWEEN PROJECTS
VARIOUS TOOLS AND TECHNIQUES FOR PROJECT PLANNING
Tools MS OFFICE (WORD, EXCEL & POWERPOINT) MS PROJECT (Complete Project control) Primavera, etc.,
Monitor & control Techniques Schedule and cost monitoring sheets. Earned Value Management (EVM) Project Dashboards.
PROJECT PLANNING SUMMARY VIDEO
QUESTIONS ??