Page 1: 136406990 MS Project Step by Step Guide

Rajiv Misra 1

Project Management

Introduction to Microsoft Project 1

Page 2: 136406990 MS Project Step by Step Guide

Rajiv Misra 2

Defining A Project in MS Project

• Steps 1. Create a new project file.2. Setup the Project – Views, Table and Calendar3. Define WBS code structure.4. Entering activity information.

Page 3: 136406990 MS Project Step by Step Guide

Rajiv Misra 3

Create a new project file.

Page 4: 136406990 MS Project Step by Step Guide

Rajiv Misra 4

Create an MS Project File

1.Click on White Document Icon

2. Fill in the Project Information and click OK.You can access Project Information later from the Project menu.

Page 5: 136406990 MS Project Step by Step Guide

Rajiv Misra 5

Create an MS Project File

Backward vs Forward Scheduling

Page 6: 136406990 MS Project Step by Step Guide

Rajiv Misra 6

Getting Specific Help

1.Click on question mark icon

2. Move the cursor onto the Option and click.

Page 7: 136406990 MS Project Step by Step Guide

Rajiv Misra 7

Setup the Project – Views, Table and Calendar

Page 8: 136406990 MS Project Step by Step Guide

Rajiv Misra 8

Understanding View / Table

VIEWTABLE

Page 9: 136406990 MS Project Step by Step Guide

Rajiv Misra 9

Understanding View / Table

VIEWTABLEVIEW

TABLE

Note different style of Table/ View

Page 10: 136406990 MS Project Step by Step Guide

Rajiv Misra 10

Setting the View

Select this

Page 11: 136406990 MS Project Step by Step Guide

Rajiv Misra 11

Setting the View

Select thisDetail Gantt

Page 12: 136406990 MS Project Step by Step Guide

Rajiv Misra 12

Setting the Table

Select thisSchedule

Page 13: 136406990 MS Project Step by Step Guide

Rajiv Misra 13

Navigating the Table

Use the SliderTo see Columns

Page 14: 136406990 MS Project Step by Step Guide

Rajiv Misra 14

Navigating the Table

Use the SliderTo see ColumnsThis table showsSlack values too

Page 15: 136406990 MS Project Step by Step Guide

Rajiv Misra 15

Understanding the Calendar

CalendarsProject

AndResource

Gray Portion

IndicatesHoliday

Page 16: 136406990 MS Project Step by Step Guide

Rajiv Misra 16

Understanding the Calendar

Project Calendar

Resource Calendar

Page 17: 136406990 MS Project Step by Step Guide

Rajiv Misra 17

Changing the Calendar

Project Calendar

Resource Calendar

Page 18: 136406990 MS Project Step by Step Guide

Rajiv Misra 18

Changing the Calendar

Project Calendar

Resource Calendar

Select datesAnd this

Radio buttonFor Working

day

Page 19: 136406990 MS Project Step by Step Guide

Rajiv Misra 19

Entering activity information

Page 20: 136406990 MS Project Step by Step Guide

Rajiv Misra 20

A Simple Project

project

1 2 3 4 5 6

2.32.22.1

Page 21: 136406990 MS Project Step by Step Guide

Rajiv Misra 21

Entering Activity Information

To add activity double click on the any field (e.g. Task Name).

… or you can right-click on any field and select Task Information.

… or if you right-click on the row header you get access to a wider set of actions..

Page 22: 136406990 MS Project Step by Step Guide

Rajiv Misra 22

1.Task Name 2.Duration

3.WBS Code

Entering Activity Information

Page 23: 136406990 MS Project Step by Step Guide

Rajiv Misra 23

2. Enter Predecessors 1.Click Predecessors

Entering Activity Information

Now enter work packages (not the summary tasks) which aregiven to you in the Assignment

Page 24: 136406990 MS Project Step by Step Guide

Rajiv Misra 24

1. Enter Predecessors2. Enter Relation type: FS, SS, SF, OR FF

Entering Activity Information

Now enter work packages (not the summary tasks) which aregiven to you in the Assignment

Page 25: 136406990 MS Project Step by Step Guide

Rajiv Misra 25

1. Enter Predecessors2. Enter Relation type: FS, SS, SF, OR FF

Entering Activity Information

Now enter work packages (not the summary tasks) which aregiven to you in the Assignment

3. Lead or Lag

Page 26: 136406990 MS Project Step by Step Guide

Rajiv Misra 26

Sub Projects and Recurring Tasks

Page 27: 136406990 MS Project Step by Step Guide

Rajiv Misra 27

Sub Project

Link the project to other tasks like any other activity

Page 28: 136406990 MS Project Step by Step Guide

Rajiv Misra 28

Sub Project

Link the project to other tasks like any other activity

Changes here affect Main Project

Page 29: 136406990 MS Project Step by Step Guide

Rajiv Misra 29

Sub Project

Link the project to other tasks like any other activity

Page 30: 136406990 MS Project Step by Step Guide

Rajiv Misra 30

Recurring Tasks (Insert – Recurring Tasks)

Page 31: 136406990 MS Project Step by Step Guide

Rajiv Misra 31

Summary Tasks (Heading)

Page 32: 136406990 MS Project Step by Step Guide

Rajiv Misra 32

Defining Summary Tasks

First insert a task right above the tasks that will make up the summary task, by right-clicking on the row header.

Page 33: 136406990 MS Project Step by Step Guide

Rajiv Misra 33

Defining Summary Tasks

Select the tasks that will make up the summary task, right-click and select Indent.

Note how initially a WBS code of 9 is automatically assigned. This will change when Indent operation is complete.

Page 34: 136406990 MS Project Step by Step Guide

Rajiv Misra 34

Defining Summary Tasks

After the Indent operation is complete, and WBC codes are renumbered as described in slide 13, we obtain the structure displayed below.

You can hide a summary task by clicking on the minus sign.

Summary task duration is calculated automatically.

Page 35: 136406990 MS Project Step by Step Guide

Rajiv Misra 35

Do NOT forget

to save your file as

<username>-PART1.

Page 36: 136406990 MS Project Step by Step Guide

Rajiv Misra 36

Define WBS code structure.

Page 37: 136406990 MS Project Step by Step Guide

Rajiv Misra 37

1.Click on Project

2.Select WBS, then Define Code...

Defining WBS Code Structure

Page 38: 136406990 MS Project Step by Step Guide

Rajiv Misra 38

Level of WBSdepends on

complexity of the project. In this project there are 2 levels.

Code Structure, changes made below settingscan be followedby this preview.

• Generally, for complex projects with many levels, letters are used for upper levels of the WBS hierarchy. • It is very important that you set the WBS structure correctly in the beginning :

• Once you set the it, it it would be difficult to change it. • Clearly defined WBS means that the project is already solved in the mind.

Defining WBS Code Structure

Page 39: 136406990 MS Project Step by Step Guide

Rajiv Misra 39

Length of the codes can be set here.Click on Length, the box below will be opened.Select 1, since there are not too manyactivities in this WBS.

Click on Separator. Select “.”

Defining WBS Code Structure

Page 40: 136406990 MS Project Step by Step Guide

Rajiv Misra 40

Displaying WBS

Page 41: 136406990 MS Project Step by Step Guide

Rajiv Misra 41

Displaying WBS Code

Select the column header where you want the new WBS column.Right-click and select Insert Column.

Choose WBS as the Field name of the new column.

Page 42: 136406990 MS Project Step by Step Guide

Rajiv Misra 42

Displaying WBS CodesThese codes can be automatically (re)generated using the WBS code structure you have defined earlier.

Page 43: 136406990 MS Project Step by Step Guide

Rajiv Misra 43

Developing a Network Plan

• Steps1. Network Diagram view (AoN network).2. Customizing Network Diagram view.3. Identifying critical path(s).4. Overview Report.5. Current Activities Report.6. Printing a Gantt chart.7. Creating a Milestone.

Page 44: 136406990 MS Project Step by Step Guide

Rajiv Misra 44

Select “Detail GanttView”

Checking the Gantt ChartProject Network

Red Bars indicate CRITICAL

SLACK is shown as GREEN lines

Page 45: 136406990 MS Project Step by Step Guide

Rajiv Misra 45

Viewing Only the Critical Path

Select Critical

Page 46: 136406990 MS Project Step by Step Guide

Rajiv Misra 46

Viewing Only the Critical Path

Select Critical

Page 47: 136406990 MS Project Step by Step Guide

Rajiv Misra 47

Select “NetworkDiagram”

Developing an Activity-On-Node (AoN) Project Network

These make upthe summary task. You can hide them by clicking on the minus sign.

Page 48: 136406990 MS Project Step by Step Guide

Rajiv Misra 48

Customizing Network Diagram

Right-click on the background,then select “Box Styles”

You may want to see different information on the nodes.

Page 49: 136406990 MS Project Step by Step Guide

Rajiv Misra 49

Click“More Templates...”

Customizing Network Diagram

Page 50: 136406990 MS Project Step by Step Guide

Rajiv Misra 50

Select “New...””

Customizing Network Diagram

Page 51: 136406990 MS Project Step by Step Guide

Rajiv Misra 51

Customizing Network Diagram

1.Give a name to your template

Info: You may folllow the changes in your template

2.You maychange the cell layout (# rows &# columns) by clickingthis icon.

Page 52: 136406990 MS Project Step by Step Guide

Rajiv Misra 52

Customizing Network Diagram

2.CheckShowlabel in cell.

1.Select the activity

Propertysuch as

“Late finish”

Page 53: 136406990 MS Project Step by Step Guide

Rajiv Misra 53

Identifying the Critical Path

Critical path indicated by RED boxes To see the details, move

the pointer on to boxes

Page 54: 136406990 MS Project Step by Step Guide

Rajiv Misra 54

Viewing Only the Critical Path

Select Critical

Page 55: 136406990 MS Project Step by Step Guide

Rajiv Misra 55

Reports

Page 56: 136406990 MS Project Step by Step Guide

Rajiv Misra 56

Getting an Overview Report

2.Select “Reports”1.Select “View”

Page 57: 136406990 MS Project Step by Step Guide

Rajiv Misra 57

Getting an Overview Report

2.Enter “Select”1.Select

“Overview”

Page 58: 136406990 MS Project Step by Step Guide

Rajiv Misra 58

Getting an Overview Report

2.Enter “Select”

1.Select “Project

Summary”

Page 59: 136406990 MS Project Step by Step Guide

Rajiv Misra 59

Getting an Overview Report

Project Summary Report

Page 60: 136406990 MS Project Step by Step Guide

Rajiv Misra 60

1.From “View” menuSelect “Reports”

2.SelectCurrent Activities 3. Select

Print out ES-LS-EF-LF-Slack Times

Page 61: 136406990 MS Project Step by Step Guide

Rajiv Misra 61

1.Select “Unstarted Tasks” 2.Edit...

Print out ES-LS-EF-LF-Slack Times

Page 62: 136406990 MS Project Step by Step Guide

Rajiv Misra 62

1.From Table option, select “Schedule” 2. “OK”

Print out ES-LS-EF-LF-Slack Times

Page 63: 136406990 MS Project Step by Step Guide

Rajiv Misra 63

1. Choose “Unstarted Tasks”

2. “Select”

Print out ES-LS-EF-LF-Slack Times

Page 64: 136406990 MS Project Step by Step Guide

Rajiv Misra 64

Report with ES,LS,EF,LF and Slack

Print out ES-LS-EF-LF-Slack Times

Page 65: 136406990 MS Project Step by Step Guide

Rajiv Misra 65

Print out a Gantt ChartOr alternatively,

1.Go to View , then 2. Select Gantt Chart

1.Click on “Gantt Chart”

Page 66: 136406990 MS Project Step by Step Guide

Rajiv Misra 66

Print Out a Gantt Chart:Obtaining A Printable Timescale

1.Right click mouse,when your pointer is on the timescale

2.Select “Timescale”

Page 67: 136406990 MS Project Step by Step Guide

Rajiv Misra 67

Print Out a Gantt Chart:Obtaining A Printable Timescale

2.Select “Months”

1.Click on“Major Scale”

Page 68: 136406990 MS Project Step by Step Guide

Rajiv Misra 68

Print Out a Gantt Chart:Obtaining A Printable Timescale

1.Click on “Minor Scale”

2.Select “Days”

Page 69: 136406990 MS Project Step by Step Guide

Rajiv Misra 69

Print Out a Gantt Chart:Obtaining A Printable Timescale

1.Arrange the Size of timescale by increasing or decreasing this number.

You can follow the changes in the timescaleby observing this area. 2.Click OK.

Page 70: 136406990 MS Project Step by Step Guide

Rajiv Misra 70

Print Out a Gantt Chart

1.Select “Print Preview”

Page 71: 136406990 MS Project Step by Step Guide

Rajiv Misra 71

Print out a Gantt Chart Click on “Page Setup...” to set the printoutput styles

Page 72: 136406990 MS Project Step by Step Guide

Rajiv Misra 72

Milestones

Page 73: 136406990 MS Project Step by Step Guide

Rajiv Misra 73

Creating a Milestone

1.Right-click on the activity where you want to put a milestone.

2.Click on the “New Task”

Page 74: 136406990 MS Project Step by Step Guide

Rajiv Misra 74

Creating a Milestone

1.Double-click on this new activity

2.Select Advanced.

Page 75: 136406990 MS Project Step by Step Guide

Rajiv Misra 75

Creating a Milestone

3. Check Mark task as milestone.

2. Give zeroduration.

1.Give a name to your milestone

Page 76: 136406990 MS Project Step by Step Guide

Rajiv Misra 76

Creating a Milestone

1.Click on Predecessors.

2.Choose necessaryactivities to link your milestone to the network

Page 77: 136406990 MS Project Step by Step Guide

Rajiv Misra 77

Creating a Milestone

NOTE: Pay attention to Predecessors column. When you add any new task these numbers are changed automatically; therefore you do not need to change predecessors of each activity.

Page 78: 136406990 MS Project Step by Step Guide

Rajiv Misra 78

Creating a Milestone

1.Select “Network View”.Milestone 1 is in the network.Note that its shape is different from regular activities.

Page 79: 136406990 MS Project Step by Step Guide

Rajiv Misra 79

Do NOT forget

to save your file as

<username>-PART2.

Page 80: 136406990 MS Project Step by Step Guide

Rajiv Misra 80

ResourcesResources

Page 81: 136406990 MS Project Step by Step Guide

Rajiv Misra 81

Entering Resources-1

1.Click on “View”

2.Select “Resource Sheet”

Page 82: 136406990 MS Project Step by Step Guide

Rajiv Misra 82

Entering Resources-2

1.Click on the Resource Name cell to enter the

resource name.

2.There are two types of resources. One is labor, the other one is material. In this example project we just have

workers as a resource.

Page 83: 136406990 MS Project Step by Step Guide

Rajiv Misra 83

Entering Resources-3

1.Write the label of material here.In this project there is no material.

2.Write the initials of workers.

3. Enter the number of units in this cell. 100% means that resource or department is used fully.50% means that half capacity of that resource is used.

Page 84: 136406990 MS Project Step by Step Guide

Rajiv Misra 84

Entering Resources-4

1.Standard Rate:Write the standard hourly wage rate of resources.

2.Overtime Rate:Write the hourly overtime rate. If a resource is used overtime, this rate is used to calculate the cost of overtime work.

3.Cost per use:A set fee for the use of a resource.(e.g. Travel cost, insurance) It is not related with the working hours.

Page 85: 136406990 MS Project Step by Step Guide

Rajiv Misra 85

Entering Resources-5

This cell is used for accounting purposes. There are 3 types of entering the cost of resources.In this example we will use “Prorated”

Start: Cost at the beginning of the work.

Prorated: Cost accrues while activity progress. If 30% of the work is finished, 30% of the cost related with that work accrued.

End:Cost is accrued at the end of the work.

Page 86: 136406990 MS Project Step by Step Guide

Rajiv Misra 86

Entering Resources-6

Through “Base Calender”cell, you can assign different calendars to different resources. In this example, Standard calendar is used:5 working-days in a week, 8 hours a day.

There are 2 more default base calendars which are 24 Hours and Night Shift. Other than these, you can create resources’ own calendars from “Tools”, “Change Working Time...”. In the appeared dialog box choose “New...” icon.

Page 87: 136406990 MS Project Step by Step Guide

Rajiv Misra 87

Resource Information Dialog Box

1.Double-click on the resource name cell.

Resource Information box will appear

You can also enter resourse details using this dialog box instead of “Resource Sheet”. There are lots of details in this dialog box, Do Not Be Lost in these details.

Page 88: 136406990 MS Project Step by Step Guide

Rajiv Misra 88

Resource Information Dialog Box

1.Double-click on the resource name cell.

Manage Costs Information

Page 89: 136406990 MS Project Step by Step Guide

Rajiv Misra 89

Resource Information Dialog Box

Rates for different periods can be given here

Different Cost tables A-F

Page 90: 136406990 MS Project Step by Step Guide

Rajiv Misra 90

Work Contours (View – Task Usage. Click on Task Assignment – Resource)

Work Load varies over time

Front vs back …

Page 91: 136406990 MS Project Step by Step Guide

Rajiv Misra 91

Assigning Resources to Tasks

1.Double click on an activity

2.From “Task Information”dialog box, click on “Resources”

100% means that this resource, “A” in this case, is used at full capacity.

3.Enter the resources which are needed for this activity.

Page 92: 136406990 MS Project Step by Step Guide

Rajiv Misra 92

A Simple Project

project

1 2 3 4 5 6

2.32.22.1

Page 93: 136406990 MS Project Step by Step Guide

Rajiv Misra 93

Resource Leveling

Page 94: 136406990 MS Project Step by Step Guide

Rajiv Misra 94

Identify which resources are overloaded-1

2.Click on “Resources Usage”

1.Go to “View”menü

Page 95: 136406990 MS Project Step by Step Guide

Rajiv Misra 95

Identify which resources are overloaded-2

The resources in red are overloaded on at least one day.

Page 96: 136406990 MS Project Step by Step Guide

Rajiv Misra 96

Identify which resources are overloaded-3

By scrolling to the right, you can see when each resource is used, how much it is used and whether it is overloaded

(indicated with red colour)

Page 97: 136406990 MS Project Step by Step Guide

Rajiv Misra 97

Graphical Display of the Load Distribution of Each Resource Over Time-1

2.Select “Resource Graph”

1.Go to “View” menu.

Page 98: 136406990 MS Project Step by Step Guide

Rajiv Misra 98

Graphical Display of the Load Distribution of Each Resource Over Time-2

By scrolling this cursor to the right, you can see

other resources.

By scrolling this cursor to the right, you can see resource load over time.

Page 99: 136406990 MS Project Step by Step Guide

Rajiv Misra 99

Graphical Display of the Load Distribution of Each Resource Over Time-3

Red area indicates that this resource is overallocated at these times

Page 100: 136406990 MS Project Step by Step Guide

Rajiv Misra 100

Resolve over-allocation problems-1

1.Go to “Tools” 2.Select “Resource Leveling”

Page 101: 136406990 MS Project Step by Step Guide

Rajiv Misra 101

Ways of Leveling Resources

AutomaticAutomatic: : Automatic leveling levels resources instantaneously when you change a task or resource. If your project is large, automatic leveling might slow down your work in the schedule.

ManualManual::Manual leveling allows you to control when Microsoft Project levels resources.

Page 102: 136406990 MS Project Step by Step Guide

Rajiv Misra 102

Resolve over-allocation problems-2

1.Check “Manual”

2.Select “Week by Week”

Page 103: 136406990 MS Project Step by Step Guide

Rajiv Misra 103

Time-Unit Used in Leveling

• Example:– Resource A has a weekly capacity of 40 hours, and

daily capacity of 8 hours.– His workload on Monday of his 1st week is 10 hours.– His workload for the entire 1st week is 38 hours.– Then, “week-by-week” leveling will not perform any

leveling for resource A in week 1.• “Day-by-day” leveling would change the schedule.

Page 104: 136406990 MS Project Step by Step Guide

Rajiv Misra 104

Resolving Methods Available in MS Project

Level only within available slack: Select this check box if you want to prevent the finish date of your project from being delayed. In many projects, however, unless there is a lot of built-in slack, with this setting you might not see a significant change after leveling.

Leveling can adjust individual assignments on a task:Select this check box to allow leveling to adjust when a resource works on a task independent of the other resources working on the same task.

Leveling can create splits in remaining work: Select this check box if you want leveling to interrupt tasks by creating splits in the remaining work on tasks or assignments.

Page 105: 136406990 MS Project Step by Step Guide

Rajiv Misra 105

Resolve over-allocation problems-3

1.Select “Standart” option

2.Check “Level only within

available lack”

Page 106: 136406990 MS Project Step by Step Guide

Rajiv Misra 106

Resolve over-allocation problems-4

2.Click on “Level now”

2.Do not check others.

Page 107: 136406990 MS Project Step by Step Guide

Rajiv Misra 107

Save Your Results

SAVE AS YOUR RESULTSSAVE AS YOUR RESULTSASAS

<username><username>--partpart33--2 2

Page 108: 136406990 MS Project Step by Step Guide

Rajiv Misra 108

Seeing the Effects of Leveling in the Leveling Gantt Chart

1.Go to “View”

2.Select “More Views”

Page 109: 136406990 MS Project Step by Step Guide

Rajiv Misra 109

Seeing the Effects of Leveling in the Leveling Gantt Chart

1.Select “Leveling Gantt”

2.Click on “Apply”

Page 110: 136406990 MS Project Step by Step Guide

Rajiv Misra 110

Seeing the Effects of Leveling in the Leveling Gantt Chart

1. Effects of leveling seen as green lines

Page 111: 136406990 MS Project Step by Step Guide

Rajiv Misra 111

Seeing the Effects of Leveling in Summary Report -1

1.Go to “Toolbar” 2.Select “Resource Leveling”

Page 112: 136406990 MS Project Step by Step Guide

Rajiv Misra 112

Seeing the Effects of Leveling in Summary Report -2

2.Select “Reports”1.Select “View”

Page 113: 136406990 MS Project Step by Step Guide

Rajiv Misra 113

Seeing the Effects of Leveling in Summary Report -3

2.Enter “Select”

1.Select “Overview”

Page 114: 136406990 MS Project Step by Step Guide

Rajiv Misra 114

Seeing the Effects of Leveling in Summary Report -4

2.Enter “Select”

1.Select “Project

Summary”

Page 115: 136406990 MS Project Step by Step Guide

Rajiv Misra 115

Seeing the Effects of Leveling in Summary Report –5

Duration of the project project did not change.This is because we selected

“Level only within available slack” in the leveling dialog box.

There is still an overallocated resource

Page 116: 136406990 MS Project Step by Step Guide

Rajiv Misra 116

Seeing the Effects of Leveling on The Critical Path-1

1.Click on “More Views...”

2.Select “Leveling Gantt”

3.Click on “Apply”

Page 117: 136406990 MS Project Step by Step Guide

Rajiv Misra 117

Seeing the Effects of Leveling on The Critical Path-2

1.Firstly, Choose “Critical”

from the menuThere is delay at one of the critical activities.

This has not caused any delay in the project’s completion, becausethis critical activity was not a critical activity before leveling,

it became critical due to delaying.

Page 118: 136406990 MS Project Step by Step Guide

Rajiv Misra 118

Compare After-leveling and Pre-leveling Reports

Leveling only within available slack means that we are keeping the duration of the project constant. If we look at the both reports we can easily see that duration of the project in each case is the same.

What difference did leveling make? Leveling reduces the amount of overallocation. At the pre-leveling stage resourse B was overallocated for 13 days, after leveling resource B is overallacated for 8 days.

At the end with Leveling only within available slack did not solve overallocation problem due to limited slack time.

Page 119: 136406990 MS Project Step by Step Guide

Rajiv Misra 119

Leveling Not Limited to Available Slack-1

1.Do not check “Level only

within available slack”

2.Select “Level Now”

Page 120: 136406990 MS Project Step by Step Guide

Rajiv Misra 120

Leveling Not Limited to Available Slack-2

Get the project overview report...

Duration of the project is increased

All overallacotion problem is solved.

Page 121: 136406990 MS Project Step by Step Guide

Rajiv Misra 121

Comparison of These Two Leveling Methods

Leveling only within available slack time reduces the overallocation problem but not solve the whole overallocation problem. But on the other hand the project time is kept constant.

The other method solved the overallocation problem completely, but the project duration is prolonged.

Page 122: 136406990 MS Project Step by Step Guide

Rajiv Misra 122

Different types of Tasks can affectTimes and Resource Usage

Page 123: 136406990 MS Project Step by Step Guide

Rajiv Misra 123

Keeping the amount of work constant in effort-driven scheduling can have varying effects on duration and units depending on the task type

Page 124: 136406990 MS Project Step by Step Guide

Rajiv Misra 124

Change these and find out Impact

ie Change duration and Resources to see the impact.

Can cause confusion

Task – Right Click-Task Information -Advanced tab

Check on Task Sheet for Differences

Page 125: 136406990 MS Project Step by Step Guide

Rajiv Misra 125

Fixed Duration Set the task to Fixed Duration if you want the task duration to remain constant, regardless of any change in assignment

units or work for the task. For fixed-duration tasks:

If you revise units, Microsoft Project recalculates work.

If you revise duration in a fixed-duration task, Microsoft Project recalculates work.

If you revise the amount of work, Microsoft Project recalculates the units

Fixed Duration

Page 126: 136406990 MS Project Step by Step Guide

Rajiv Misra 126

Fixed Units Set the task to Fixed Units if you want the number of assignment units to remain constant, regardless of any change in duration or work for the task. This is the

default. For fixed-unit tasks:

If you revise units in a fixed-unit task, Microsoft Project recalculates duration.

If you revise duration, Microsoft Project recalculates work.

If you revise the amount of work, Microsoft Project recalculates the duration.

Fixed Units

Page 127: 136406990 MS Project Step by Step Guide

Rajiv Misra 127

Fixed Work Set the task to Fixed Work if you want the amount of work to remain constant, regardless of any change in duration or

resource assignment units for the task. Because, by definition, fixed-work tasks are effort-driven, the Effort driven check box is

automatically selected for fixed-work tasks.

For fixed-work tasks: If you revise units, Microsoft Project recalculates duration. If you revise duration, Microsoft Project recalculates units.

If you revise the amount of work in a fixed-work task, Microsoft Project recalculates the duration.

Fixed Work

Page 128: 136406990 MS Project Step by Step Guide

Rajiv Misra 128

Resource Management

Page 129: 136406990 MS Project Step by Step Guide

Rajiv Misra 129

Resource Management-1

1.Click on an empty area in the tool bar

2.Select “Resource Management”

Page 130: 136406990 MS Project Step by Step Guide

Rajiv Misra 130

Resource Management-2

Page 131: 136406990 MS Project Step by Step Guide

Rajiv Misra 131

Ways of reducing over-allocations:Delaying a task-1

• Delaying an assigned task until the resource has time to work on it is a simple way to resolve a resource overallocation.

• You can add delay to a task or assignment, check the effect on the resource's allocation, and then adjust the delay further if necessary.

• If you want to add delay without changing the finish date of other tasks or the project finish date, review available slack and add delay only within that slack time.

Page 132: 136406990 MS Project Step by Step Guide

Rajiv Misra 132

Ways of reducing over-allocations:Delaying a task-2

1.Double-click on the relationship between activities which you want a delay.

2.Set how many days will you delay.

Page 133: 136406990 MS Project Step by Step Guide

Rajiv Misra 133

Ways of reducing over-allocations:Splitting a task-1

• In addition to reducing over-allocations, splitting a task is useful when you need to interrupt work on a task.

• For example, your project may include a task that requires materials that are ordered but that won't be received for two weeks.

Page 134: 136406990 MS Project Step by Step Guide

Rajiv Misra 134

Ways of reducing over-allocations Spliting a task-2

1.First Click on “Split Task” icon

2. Move pointer on the Gantt Chart view, and

split the task which is needed to be interrupted

Page 135: 136406990 MS Project Step by Step Guide

Rajiv Misra 135

Sharing Resources across projects

Page 136: 136406990 MS Project Step by Step Guide

Rajiv Misra 136

Create a project and only model allResources in that project which arecommon. (say Common_Resource)

(For other projects that shall use thecommon resources

Tools – Resources – Share Resources-Select the name as Common_Resource

Page 137: 136406990 MS Project Step by Step Guide

Rajiv Misra 137

Page 138: 136406990 MS Project Step by Step Guide

Rajiv Misra 138

Common ResourcesFile Name

Page 139: 136406990 MS Project Step by Step Guide

Rajiv Misra 139

PERT Calculations

Page 140: 136406990 MS Project Step by Step Guide

Rajiv Misra 140

For PERT CalculationsView – Tool Bars – PERT Analysis

Page 141: 136406990 MS Project Step by Step Guide

Rajiv Misra 141

PERT Tool Bar

Enter PERT Durations (Opt/Pess/Likely) and Calculate PERTYou can view all 3 Gantt – Opt/Pess/ Likely

PERT Calculate

Button

Important- Press to see results

Page 142: 136406990 MS Project Step by Step Guide

Rajiv Misra 142

Base Lines

Page 143: 136406990 MS Project Step by Step Guide

Rajiv Misra 143

If “Save with a baseline option” does not appear,Base Line means the details of the Previous Version

of the Plan

1.Choose “Tools”

2.Select “Tracking”

3.Click on “SaveBaseline...”

Page 144: 136406990 MS Project Step by Step Guide

Rajiv Misra 144

Tracking and Costing

Page 145: 136406990 MS Project Step by Step Guide

Rajiv Misra 145

Display the Tool Bar for TrackingView – Tool Bars - Tracking

3 Activities A, B and C Duration 6,4,4.A & B FS relation.

All use resource AR. Cost per hour of AR = 10/hr (Resource Sheet)

Page 146: 136406990 MS Project Step by Step Guide

Rajiv Misra 146

Set the OptionsTools – Options - Calculations

Page 147: 136406990 MS Project Step by Step Guide

Rajiv Misra 147

Create a Network as below

3 Activities A, B and C Duration 6,4,4.A & B FS relation.

All use resource AR. Cost per hour of AR = 10/hr (Resource Sheet)

Page 148: 136406990 MS Project Step by Step Guide

Rajiv Misra 148

Update the Task Status using the buttonson the Tool Bar (0-100% buttons)

or Task Update Button (or Tools – Tracking)

3 Activities A, B and C Duration 6,4,4.A & B FS relation.

All use resource AR. Cost per hour of AR = 10/hr (Resource Sheet)

Buttons forTask Status

Page 149: 136406990 MS Project Step by Step Guide

Rajiv Misra 149

Update Tasks and Add Progress Lines (Button onTool Bar or Tools – Tracking – Progress Lines)

Page 150: 136406990 MS Project Step by Step Guide

Rajiv Misra 150

Task Updated and Progress Lines Added

Black bars Indicate Progress

Progress Line (Line to left indicates Slow Progress, to Right Ahead of Schedule)

Page 151: 136406990 MS Project Step by Step Guide

Rajiv Misra 151

Update Project based on Actual Status

Menu Tools – Tracking – Update Project

Page 152: 136406990 MS Project Step by Step Guide

Rajiv Misra 152

Update Project based on Actual Status

Menu Tools – Tracking – Update Project

Select this button.

Put date based on Date till Status got

Page 153: 136406990 MS Project Step by Step Guide

Rajiv Misra 153

Updated Project based on Actual Status

Menu Tools – Tracking – Update Project

Dotted line indicates Delay

Page 154: 136406990 MS Project Step by Step Guide

Rajiv Misra 154

Update the Progress of the Project-1

1.Select the activity that you will update

2. From “Tools” select “Tracking” 4.Update Tasks...

Page 155: 136406990 MS Project Step by Step Guide

Rajiv Misra 155

Update the Progress of the Project-2

Change the durations using the data provided in the Excel file.

Note: Although we changed the actual and remaining durations, baseline dates are not affected by changes you made.

Page 156: 136406990 MS Project Step by Step Guide

Rajiv Misra 156

Update the Progress of the Project-3

If a number of tasks started and finished on time, you can set the actual finish information for all those tasks at once. Procedure as follows;

Select the tasks that you want to update (press CTRL key and click on Task Name).

Page 157: 136406990 MS Project Step by Step Guide

Rajiv Misra 157

Update the Progress of the Project-4

1.Go to “Tool” bar

2.Choose “Update Project...”

2.Select “Tracking”

Page 158: 136406990 MS Project Step by Step Guide

Rajiv Misra 158

Update the Progress of the Project-5

Choose “selected tasks” then click “OK”

Page 159: 136406990 MS Project Step by Step Guide

Rajiv Misra 159

Seeing the Effects of Update-1

1.Go to “View”

2.Click “More Views”

3.Select

“Tracking Gantt”

Page 160: 136406990 MS Project Step by Step Guide

Rajiv Misra 160

Seeing the Effects of Update-2

Dark Blue Bar shows the completion percentage of the tasks.

Light Blue Bar shows the remaining percentage of the tasks.

Gray Bar shows the base line of the tasks.

Page 161: 136406990 MS Project Step by Step Guide

Rajiv Misra 161

Seeing the Effects of Update on Critical Path

Select “Critical”

As you can see Tracking Gantt Chart does not show the completed tasks on the critical path. Therefore we have only

remaining critical activities as indicated by the Red Bar.

Page 162: 136406990 MS Project Step by Step Guide

Rajiv Misra 162

Costing – Earned Value Management

Page 163: 136406990 MS Project Step by Step Guide

Rajiv Misra 163

Step 1

Create a Network with one Task A Duration 10Resource ARSet Std Rate for Resource as 10/hr (View-Resource Sheet)

Step 2Set the Status Date appropriately (Project – Project Information)

Step 3Save the Base Line (Tools – Tracking – Save Base Line)

Page 164: 136406990 MS Project Step by Step Guide

Rajiv Misra 164

Set the Tables to Earned ValueView – Tables – More Tables – Earned

Value

EVM terms

Page 165: 136406990 MS Project Step by Step Guide

Rajiv Misra 165

Update Actual Costs Set Table to Cost (View – Table – Cost)

Enter Actual Costs

Page 166: 136406990 MS Project Step by Step Guide

Rajiv Misra 166

To see the BCWP/ACWPSet the Tables to Earned Value

View – Tables – More Tables – Earned ValueUpdate the Progress of the job also (for BCWP)

EVM terms Now

BCWS and ACWP also appear Black bar showing Progress

Page 167: 136406990 MS Project Step by Step Guide

Rajiv Misra 167

Earned Value Analysis Report-1

What is earned value analysis?Earned value analysis is a method for measuring project performance. It indicates how much of the budget should have been spent, in view of the amount of work done so far, and the baseline cost for the task, assignment, or resource. Earned value is also referred to as budgeted cost of work performed (BCWP).

In our example we use the beginning of each month as a control date for the earned value analysis.

Page 168: 136406990 MS Project Step by Step Guide

Rajiv Misra 168

Earned Value Analysis Report-2

1. From “Project” select “Project Information” 2.Set “Status date” to 5/1/2002

Page 169: 136406990 MS Project Step by Step Guide

Rajiv Misra 169

Earned Value Analysis Report-3

1.Select

“View”

2.Choose

“Report”3.Click on “Costs...”

4.Click “Select”

Page 170: 136406990 MS Project Step by Step Guide

Rajiv Misra 170

Earned Value Analysis Report-4

1.Select “Earned Value” 2.Click on “Select”

Page 171: 136406990 MS Project Step by Step Guide

Rajiv Misra 171

Fields in the Earned Value Table

Field Description

BCWS Budgeted cost of work scheduled, through the project status date

BCWP Budgeted cost of work performed, through the project status date

ACWP Actual cost of work performed, through the project status date

SV Earned value schedule variance, through the project status date

CV Earned value cost variance, through the project status date

BAC Budgeted at completion (the baseline cost of the task/project)

EAC Estimate at completion, (estimated cost of the task/project)

VAC Variance at completion, (=BAC – EAC)

Page 172: 136406990 MS Project Step by Step Guide

Rajiv Misra 172

Earned Value Analysis Report-5-1

Cost calculations for activity 5:Uses 100% of resource B whose fixed cost is $450 & variable cost is $12/hr.BCWS = 450 + 13 (12*8) = $1698 BCWP = 450 + 13 (12*8)*(13/14) = $1608.86

Page 173: 136406990 MS Project Step by Step Guide

Rajiv Misra 173

Earned Value Analysis Report-5-2

•If BCWS is larger than BCWP, then that task is behind schedule. Hence there is a negative schedule variance.

•Total ACWP is larger than BCWP; that is money spent on tasks performed has been larger than the budgeted amount.

Page 174: 136406990 MS Project Step by Step Guide

Rajiv Misra 174

Earned Value Analysis Report-5-3

• EAC for activities that are not yet started (7, 8, 9, and 11) is set equal to BAC.

• It is presumed that the fact that there has been deviations in the started activities does not necessarily mean that there will be deviations in the future activities.

•EAC for activity 5 is calculated as follows: 450 + 14(12*8) = $1794

Page 175: 136406990 MS Project Step by Step Guide

Rajiv Misra 175

Monthly Cost Schedule Report-1

1.Select “View”

2.Choose “Report”

Page 176: 136406990 MS Project Step by Step Guide

Rajiv Misra 176

Monthly Cost Schedule Report-2

1.Choose “Cost”

2.Click on “Select”

3.Select “CashFlow”

4. Click on “Edit” icon.

Page 177: 136406990 MS Project Step by Step Guide

Rajiv Misra 177

Monthly Cost Schedule Report-3

You can change the format and details of cost schedule report by changing the items within “Crosstab Report” view. For the monthly cost report change the time unit to months.

1.Select “Definition”

2.Select “Month”

3.Click “OK”

Page 178: 136406990 MS Project Step by Step Guide

Rajiv Misra 178

Monthly Cost Schedule Report-4

Click on “Select” icon.

Page 179: 136406990 MS Project Step by Step Guide

Rajiv Misra 179

Monthly Cost Schedule Report-5

Monthly Cost Schedule Report

Page 180: 136406990 MS Project Step by Step Guide

Rajiv Misra 180

Save as your project as <username>-Part4-1