Top Banner
03/26/22 23:40 1 PROJECT TIME PLANNING PROJECT TIME PLANNING Process and Bar Chart Process and Bar Chart Technique Technique
25

12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

Dec 13, 2015

Download

Documents

Bryan Crawford
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:541

PROJECT TIME PLANNING PROJECT TIME PLANNING

Process and Bar Chart TechniqueProcess and Bar Chart Technique

Page 2: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:542

Planning is the process of thinking systematically

about the future in order to decide

what our goalsgoals are, and

howhow we are going to achieve them.

Planning means looking ahead, making

preparations, and deciding the best course of

action.

Planning is the process of thinking systematically

about the future in order to decide

what our goalsgoals are, and

howhow we are going to achieve them.

Planning means looking ahead, making

preparations, and deciding the best course of

action.

Definition of PlanningDefinition of Planning

Page 3: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:543

Dimensions of PlanningDimensions of Planning

Planning can be viewed from following points:

SubjectSubject:- TimeTime Planning, QualityQuality Planning, Financial Financial

Planning, RiskRisk Planning, OrganizationalOrganizational Planning, …….

OrganizationOrganization:- CorporateCorporate Planning, ProjectProject Planning, …

TimeTime:- Long-Rang Long-Rang PlanningPlanning, Short-RangeShort-Range Planning,

WeeklyWeekly Planning, ….

Planning can be viewed from following points:

SubjectSubject:- TimeTime Planning, QualityQuality Planning, Financial Financial

Planning, RiskRisk Planning, OrganizationalOrganizational Planning, …….

OrganizationOrganization:- CorporateCorporate Planning, ProjectProject Planning, …

TimeTime:- Long-Rang Long-Rang PlanningPlanning, Short-RangeShort-Range Planning,

WeeklyWeekly Planning, ….

Page 4: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:544

Why is TimeWhy is Time PlanningPlanning necessary?necessary?

The increasing importance of timely completiontimely completion.

The continuous complexity and growth in the size of the project

generates the necessity for specialization. Specialization may lead

to a breakdown of communications. Time planning must be found

to facilitate communicationsto facilitate communications.

Planning is essential for resource managementresource management and the efficient

and maximum utilization of resourcesutilization of resources.

Planning is basis for evaluating progress, controllingcontrolling the work

and making decisions.

The increasing importance of timely completiontimely completion.

The continuous complexity and growth in the size of the project

generates the necessity for specialization. Specialization may lead

to a breakdown of communications. Time planning must be found

to facilitate communicationsto facilitate communications.

Planning is essential for resource managementresource management and the efficient

and maximum utilization of resourcesutilization of resources.

Planning is basis for evaluating progress, controllingcontrolling the work

and making decisions.

Page 5: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:545

For achieving an increase in productionincrease in production.

FinanciersFinanciers require a workable plan.

Essential in projects when their is transfer of personneltransfer of personnel.

Minimum riskMinimum risk of the problems occurring.

For achieving an increase in productionincrease in production.

FinanciersFinanciers require a workable plan.

Essential in projects when their is transfer of personneltransfer of personnel.

Minimum riskMinimum risk of the problems occurring.

Why is TimeWhy is Time PlanningPlanning necessary?necessary?

Page 6: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:546

WhoWho NeedsNeeds TimeTime Planning?Planning?

Customer/ Client/ Owner

Designer/ Consultant

Project management team (Manager, Engineers)

Cost estimating department

Planning and controlling department

Supervisors, foremen, labors

Supplier

Financiers

Customer/ Client/ Owner

Designer/ Consultant

Project management team (Manager, Engineers)

Cost estimating department

Planning and controlling department

Supervisors, foremen, labors

Supplier

Financiers

Page 7: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:547

Processes of Time PlanningProcesses of Time Planning

1. Visualize and define the activitiesactivities.

2. Sequence the activities (Job LogicLogic).

3. Estimate the activity durationactivity duration.

4.4. ScheduleSchedule the project or phase.

5. Allocate and balance resourcesresources.

1. Visualize and define the activitiesactivities.

2. Sequence the activities (Job LogicLogic).

3. Estimate the activity durationactivity duration.

4.4. ScheduleSchedule the project or phase.

5. Allocate and balance resourcesresources.

Page 8: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:548

Visualize and define the activitiesVisualize and define the activities

1. An activity is a single work step (element)work step (element) that has a recognizable

beginning and end and requires time for its accomplishment.

Activity definition involves identifying and documentingidentifying and documenting the

specific activities that must be performed to produce the

deliverables and sub-deliverables.

2. The technique of decompositiondecomposition (Work BreakdownWork Breakdown) may be

used in defining activities. Decomposition involves subdividing

project work packages into smaller, more manageable

components to provide better management control.

3. The output from activity definition is the activity listactivity list.

4. The Level of detailLevel of detail of the plan should be considered in this phase.

1. An activity is a single work step (element)work step (element) that has a recognizable

beginning and end and requires time for its accomplishment.

Activity definition involves identifying and documentingidentifying and documenting the

specific activities that must be performed to produce the

deliverables and sub-deliverables.

2. The technique of decompositiondecomposition (Work BreakdownWork Breakdown) may be

used in defining activities. Decomposition involves subdividing

project work packages into smaller, more manageable

components to provide better management control.

3. The output from activity definition is the activity listactivity list.

4. The Level of detailLevel of detail of the plan should be considered in this phase.

Page 9: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:549

Visualize and define the activitiesVisualize and define the activities

Case Study: Install a new machineCase Study: Install a new machine

Activity Code

Activity Description Depends on

Level Duration(day)

Inspect the machine after installation

Hire the operator

Install the new machine

Inspect and store the machine after delivery

Hire labor to install the new machine

Train the operator

Order and deliver the new machine

Page 10: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:5410

Sequence the activitiesSequence the activities

1. Sequence the activities or job logic refers to identifying and documenting identifying and documenting interactivity logical relationshipsinteractivity logical relationships, i.e. determined orderorder in which the activities are to be accomplished in the project.

2. Job plan must reflect the practical restraints or limitations that apply to

most job activities. The types of restraints are:

Mandatory dependencies or hard logic (natural dependency),

Preferred logic (Discretionary dependencies),

External dependencies,

Resource restraints and

Safety restraints.

3.3. Predecessor activitiesPredecessor activities mean coming before, while successor successor

activitiesactivities mean coming after.

4.4. OverlapOverlap the activities to reduce the project time.

1. Sequence the activities or job logic refers to identifying and documenting identifying and documenting interactivity logical relationshipsinteractivity logical relationships, i.e. determined orderorder in which the activities are to be accomplished in the project.

2. Job plan must reflect the practical restraints or limitations that apply to

most job activities. The types of restraints are:

Mandatory dependencies or hard logic (natural dependency),

Preferred logic (Discretionary dependencies),

External dependencies,

Resource restraints and

Safety restraints.

3.3. Predecessor activitiesPredecessor activities mean coming before, while successor successor

activitiesactivities mean coming after.

4.4. OverlapOverlap the activities to reduce the project time.

Page 11: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:5411

Case Study: Install a new machineCase Study: Install a new machine

Activity Code

Activity Description Depends on

Level Duration(day)

100 Inspect the machine after installation 300 4

200 Hire the operator None 1

300 Install the new machine 500, 400 3

400 Inspect and store the machine after delivery 700 2

500 Hire labor to install the new machine None 1

600 Train the operator 200, 300 4

700 Order and deliver the new machine None 1

Sequence the activitiesSequence the activities

Page 12: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:5412

Estimate the activity durationEstimate the activity duration

1. Select the time unittime unit (week, day,..) to be used.

2. Use one of the following tools and techniques for estimating the activity duration:

• Expert judgmentExpert judgment

• QuantitativelyQuantitatively based durations • Duration of activity (D)

= Quantity of work / [Production rate of a crew or equipment * No. of crews].

Where production rate = Quantity produced in unit of time

• Duration of activity (D)

= Quantity of work * Unit rate productivity of a crew or equipmentWhere unit rate productivity = Time needs to produce one unit of output

1. Select the time unittime unit (week, day,..) to be used.

2. Use one of the following tools and techniques for estimating the activity duration:

• Expert judgmentExpert judgment

• QuantitativelyQuantitatively based durations • Duration of activity (D)

= Quantity of work / [Production rate of a crew or equipment * No. of crews].

Where production rate = Quantity produced in unit of time

• Duration of activity (D)

= Quantity of work * Unit rate productivity of a crew or equipmentWhere unit rate productivity = Time needs to produce one unit of output

Page 13: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:5413

Case Study: Install a new machineCase Study: Install a new machine

Activity Code

Activity Description Depends on

Level Duration(day)

100 Inspect the machine after installation 300 4 1

200 Hire the operator None 1 25

300 Install the new machine 500, 400 3 2

400 Inspect and store the machine after delivery 700 2 1

500 Hire labor to install the new machine None 1 20

600 Train the operator 200, 300 4 3

700 Order and deliver the new machine None 1 30

Estimate the activity durationEstimate the activity duration

Page 14: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:5414

Schedule the Project or PhaseSchedule the Project or Phase

SchedulingScheduling is the determination of the project time and the timing of the activities comprising the project.

In scheduling we consider the questions of

• how long the project is expected to take and

• when each activity may be scheduled (started and ended)

To schedule the project, the planner needs a Time Time Planning TechniquePlanning Technique.

SchedulingScheduling is the determination of the project time and the timing of the activities comprising the project.

In scheduling we consider the questions of

• how long the project is expected to take and

• when each activity may be scheduled (started and ended)

To schedule the project, the planner needs a Time Time Planning TechniquePlanning Technique.

Page 15: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:5415

Time Planning Techniques

Practically every project is sufficiently complex that its

breakdown and its inner relationships must be recorded

on paper or other media, and not only in the head of the

planner.

Therefore as a plan is formulated some type of "paper paper

modelmodel" of the project should be developed to

communicate results of the plan to others and to serve

as a basis for evaluating progress and controlling the

work.

Practically every project is sufficiently complex that its

breakdown and its inner relationships must be recorded

on paper or other media, and not only in the head of the

planner.

Therefore as a plan is formulated some type of "paper paper

modelmodel" of the project should be developed to

communicate results of the plan to others and to serve

as a basis for evaluating progress and controlling the

work.

Page 16: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:5416

Bar Charts and Linked Bar Charts;Bar Charts and Linked Bar Charts;

Network Model (Analysis), either Network Model (Analysis), either

Activity on arrow (AOA), Activity on arrow (AOA),

Activity on node (AON),Activity on node (AON),

Precedence DiagramPrecedence Diagram

Line of Balance;Line of Balance;

Time-location Diagram.Time-location Diagram.

Bar Charts and Linked Bar Charts;Bar Charts and Linked Bar Charts;

Network Model (Analysis), either Network Model (Analysis), either

Activity on arrow (AOA), Activity on arrow (AOA),

Activity on node (AON),Activity on node (AON),

Precedence DiagramPrecedence Diagram

Line of Balance;Line of Balance;

Time-location Diagram.Time-location Diagram.

Time Planning Techniques

Page 17: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:5417

BAR CHARTBAR CHART

During World War 1, Henry GanttGantt developed the Bar

chart planning technique.

A bar chart graphically describes a project

consisting of well-defined activities, the completion

of which marks its end.

An activity is a task whose performance contributes

to completion of the overall project.

During World War 1, Henry GanttGantt developed the Bar

chart planning technique.

A bar chart graphically describes a project

consisting of well-defined activities, the completion

of which marks its end.

An activity is a task whose performance contributes

to completion of the overall project.

Page 18: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:5418

All activities are listed in a column at the left side of

the diagram.

A horizontal time scale extends to the right of the

list.

A bar presenting each activity is drawn between its

corresponding scheduled start and finish times.

All activities are listed in a column at the left side of

the diagram.

A horizontal time scale extends to the right of the

list.

A bar presenting each activity is drawn between its

corresponding scheduled start and finish times.

BAR CHART

Page 19: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:5419

Case study

Page 20: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:5420

Case study

Page 21: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:5421

Preparing a Bar Chart

Page 22: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:5422

Uses of Bar Chart Planning TechniqueUses of Bar Chart Planning Technique

Showing the order of the different activities

Showing when operations should start and finish

Checking what labor or equipment are needed and when

Checking out delivery dates for materials

Explaining to everyone concerned what is due to happen and

when

Forecasting cash flow

During execution, the chart used to control the work

Showing the order of the different activities

Showing when operations should start and finish

Checking what labor or equipment are needed and when

Checking out delivery dates for materials

Explaining to everyone concerned what is due to happen and

when

Forecasting cash flow

During execution, the chart used to control the work

Page 23: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:5423

Advantages of Bar Chart

Simple graphical form

Easy understood for all levels of management

Good form of communication.

Simple graphical form

Easy understood for all levels of management

Good form of communication.

Page 24: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:5424

Limitations of Bar Chart

Very cumbersome as the number of activities,

increases

Logic is not expressed in the diagram

Difficult to use it for forecasting the effects of

changes, It is therefore limited as control tool

No indication where management attention should

be focused

Ineffective for project shortening

Very cumbersome as the number of activities,

increases

Logic is not expressed in the diagram

Difficult to use it for forecasting the effects of

changes, It is therefore limited as control tool

No indication where management attention should

be focused

Ineffective for project shortening

Page 25: 12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.

04/18/23 17:5425

Logic is not represented in the Bar ChartLogic is not represented in the Bar Chart

A

B

C

D

E

F

G

H

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14Timedays

Act

ivit

ies