05 July 2010 EDCM Stakeholder Workshop
Mar 26, 2015
05 July 2010
EDCM Stakeholder Workshop
© 2007 E.ON
Agenda
• Background and timeline• Overview• CDCM / EDCM boundary• Locational charging and FCP• Pricing model• EDCM Prices• Key consultation issues• Future developments
10 April 2023, E.ON, Page 2
Background and timeline
© 2007 E.ON
CDCM
• CDCM jointly developed by DNOs, with stakeholder input
• Implemented April 2010• Covers all LV and HV charges• DNOS working to satisfy condition relating
to treatment of generator dominated areas• In the event, Central Networks required no
derogations• No issues with CDCM billing• Procuring new combined HH/NHH billing
system for 2011
10 April 2023, E.ON, Page 4
© 2007 E.ON
EDCM
• Will cover EHV charges from April 2011 (subject to approval)
• Licence requires EDCM submission by 1 September 2010
• Within EDCM, DNOs have option of either LRIC or FCP• CMG has established three workstreams:
WSA – ‘Network modelling’WSB – ‘Pricing modelling’WSC – ‘Price stability’
• Some stakeholders in workstreams – more welcome!• Project Manager and Technical Consultants in support• See ENA website for info:
http://2010.energynetworks.org/edcm/
10 April 2023, E.ON, Page 5
© 2007 E.ON
Pre-April 2005 generation
• Generation connection rules changed from ‘deep’ to ‘shallowish’ from April 2005
• Pre-April 2005 generation not charged export use of system
• DPCR5 removes dispensation not to charge from April 2010
• CDCM ‘charges’ (credits) HV and LV generation• Ofgem pushing DNOs to implement interim EHV
charging arrangements in 2010/11• Central Networks has proposed modified version
of methodology for post-April 05 generation:No pass through of 80%No £1 per kW incentive£1 per kW O&M (unless paid ‘up front’)No charge where no legal right to charge
10 April 2023, E.ON, Page 6
© 2007 E.ON
EDCM timeline
13 July – Ofgem boundary consultation closes16 July – Joint DNO consultation closes July/August – DNOs consider responses and
modify as neededBy 1 September – DNOs submit EDCM proposals
to Ofgem October/November – Ofgem consultationNovember/December – Authority decisionAssuming no veto:Late December – DNOs’ publish ‘indicative’ tariffsBy 19 February 2011 – Final tariffs confirmed1 April 2011 – EDCM tariffs become effective
10 April 2023, E.ON, Page 7
Overview
© 2007 E.ON
Charging Model Overview (1)
10 April 2023, E.ON, Page 9
© 2007 E.ON
Charging Model Overview (2)
10 April 2023, E.ON, Page 10
© 2007 E.ON
Charging Model Overview (3)
10 April 2023, E.ON, Page 11
© 2007 E.ON
Charging Model Overview (4)
10 April 2023, E.ON, Page 12
EDCM / CDCM Boundary
© 2007 E.ON
The Current Boundary
• CDCM applies to customers supplied at less than 22 kV, except those currently under site-specific arrangements
• If the licence is not changed, EDCM will apply to all customers above 22 kV (class A), and to all HV customers currently under site-specific arrangements (class B)
10 April 2023, E.ON, Page 14
© 2007 E.ON
ENA Boundary Consultation
• WSB has consulted on possible changes to the boundary
• Summary of responses published at http://2010.energynetworks.org/edcm
• The DNOs’ preference was for a 22 kV “raised” boundary
10 April 2023, E.ON, Page 15
© 2007 E.ON
ENA Boundary Consultation – no change assumed!• The prices in the EDCM consultation
document assume no change
• Model includes current site-specific customers
• Any change to the boundary would require re-running the models and could materially affect prices for all customers
10 April 2023, E.ON, Page 16
© 2007 E.ON
Raised Boundary
• Would move class B customers from current site-specific arrangements to the CDCM
• These customers would be removed from the EDCM modelling
• Will affect charges for all demand customers, including class A customers
10 April 2023, E.ON, Page 17
© 2007 E.ON
Lowered Boundary
• Would move some CDCM customers (in class C) from the CDCM to the EDCM
• These customers would be added to the EDCM modelling
• Will affect charges for all demand customers, including class A and B customers
10 April 2023, E.ON, Page 18
© 2007 E.ON
Ofgem’s Consultation
• Ofgem has proposed a number of options
• Some options would combine raising the boundary (excluding some class B customers) and lowering the boundary (including some class C customers)
• Any change would require a modification to the distribution licence conditions
10 April 2023, E.ON, Page 19
© 2007 E.ON
Ofgem’s Impact Assessment
• Implementing any boundary change would involve re-running the whole EDCM model and affect all prices for all EDCM customers
• Illustrative prices that have been published do not apply to all boundary options
• Actual price impact of boundary changes could be quite different
10 April 2023, E.ON, Page 20
© 2007 E.ON
EDCM / CDCM Boundary – Next steps
• The illustrative charges in the EDCM consultation document are likely to change
• These changes will be affected by the outcome of the boundary consultation
• Submission in September will reflect the boundary in the licence at that time
10 April 2023, E.ON, Page 21
Locational charging and FCP
© 2007 E.ON
What is EHV ‘locational’ pricing?
• Valuation of spare capacity
• Tariffs vary by point of connection
• Reflects levels of utilisation of network assets
• Benefits:• Connections where there is spare capacity
• Demand-side management
• Price signals to distributed generation
• Economically efficient network reinforcement
10 April 2023, E.ON, Page 23
© 2007 E.ON
Forward Cost Pricing (FCP)
• Network studies• Analysis based on a ‘zonal’ approach (network groups)
• Network resilience over a 10-year period assessed
• Reinforcements due to load AND generation identified – only thermal capacity
considered
• Load and generation treated differently
• Load analysis• ‘Peak’ and ‘Maintenance’ scenarios assessed for each year
• Earliest year in which each asset requires reinforcement identified
• Generation analysis• Single analysis (minimum loads, maximum output from existing generation)
• Hypothetical generators ‘connected’ to test resilience
• Additional generation that can be connected before overloads occur estimated
10 April 2023, E.ON, Page 24
© 2007 E.ON
FCP – distribution network analysis
Demand
Generation
10 April 2023, E.ON, Page 25
Peak Demand Analysis•N-1 contingencies•Diversified winter loads•Winter asset ratings•‘Secure’ generation output
Summer Demand Analysis
•N-2 contingencies•Diversified summer peak loads•Summer asset ratings•‘Secure’ generation output
Reinforcement•Identify reinforcement•Identify timing
Most Onerous Regime
•Identify timingReinforcement
•Identify reinforcement•Identify timing
TSG Analysis•N-1 contingencies•Diversified summer min. loads•Summer asset ratings•Maximum generation output•Test size generator
overload?
Headroom Analysis
•Generator increments•Identify reinforcement
NO
YES
© 2007 E.ON
Typical FCP cost recovery profile
T-10 T-9 T-8 T-7 T-6 T-5 T-4 T-3 T-2 T-1
10 April 2023, E.ON, Page 26
© 2007 E.ON
Derivation of network group prices
10 April 2023, E.ON, Page 27
© 2007 E.ON
Original FCP generation principles
• Prediction of sizes and locations of future connections difficult
• ‘Test size generators’ used to simulate effect of lumpy connections
• ‘Test size generators’ derived from existing plant profile – 85 th percentile
• ‘Connected’ to ‘principal’ substation in each network group
• Headroom assessment pricing• No price if TSG does not cause any overloads
• ‘Incremental’ generator increased until overload – price based on headroom
• Aimed more at assessing fault level costs• Generator driven costs dominated by switchgear (fault level)
10 April 2023, E.ON, Page 28
© 2007 E.ON
Improvements to FCP generation principles
10 April 2023, E.ON, Page 29
Original Methodology Improved Methodology
Size TSGs derived from existing generation plant profile
TSGs derived from existing generation plant profile AND accepted offers
[TSG sizes linked to future connections]
Connection points
TSGs ‘connected’ to ‘principal’ substation
TSGs ‘connected’ to ‘principal’ substation AND network group perimeter
[Circuits explicitly tested]
‘Probabilities’ used in pricing
‘Probability’ derived from total test and forecast generation for each voltage level
‘Probability’ extended to incorporate multiple tests in each network group
[Recognition that an asset may be overloaded by multiple tests within same network group]
© 2007 E.ON
‘Test Size Generator’ size profiles
10 April 2023, E.ON, Page 30
Original Methodology Improved Methodology
Voltage(kV)
CN East CN West Voltage(kV)
Substation
Circuit
132 333 88 132 100 100
33 23 46 33 51 23
11 4 6 11 6
© 2007 E.ON
TSG connection point – original methodology
10 April 2023, E.ON, Page 31
© 2007 E.ON
TSG connection points – improved methodology
10 April 2023, E.ON, Page 32
© 2007 E.ON
Central Networks’ FCP outputs
• All prices indexed against estimated reinforcement costs
• Reinforcements validated against our 10-year network plan and ‘watch’ list
10 April 2023, E.ON, Page 33
© 2007 E.ON
‘Locational’ prices for selected 132kV network groups
10 April 2023, E.ON, Page 34
Willington:L: £1.54G: £0.00
Ratcliffe-on-Soar:L: £3.41G: £0.00
Drakelow:L: £0.00G: £0.00
Enderby:L: £0.00G: £0.91
© 2007 E.ON
‘Locational’ prices for selected 33kV network groups
10 April 2023, E.ON, Page 35
Willington:L: £1.54G: £0.00
Drakelow:L: £0.00G: £0.00
Burton:L: £0.00G: £1.71
Burton South:L: £0.00G: £0.00Gresley:L: £0.00G: £1.63
Heanor:L: £1.58G: £1.61
Stanton:L: £1.54G: £1.25
Spondon:L: £1.54G: £0.49
Derby:L: £5.18G: £0.71
Derby South:L: £1.78G: £0.00Uttoxeter:L: £5.13G: £1.73
Pricing model
© 2007 E.ON
Key Inputs
• Customer dataset• Capacity, peak-time consumption, generated units forecast, etc.
• FCP or LRIC dataset• Charge 1, charge 2, gross kW and kVAr flows in maximum and minimum demand scenarios
• DNO data: revenue, CDCM model assets, …
10 April 2023, E.ON, Page 37
© 2007 E.ON
Overview of the application of charge 1 and charge 2
10 April 2023, E.ON, Page 38
Charge 1 Charge 2
Import MPAN
Charge to import capacity or peak-time demand
Billed as p/kVA/day
Nothing
Export MPAN
Generation credit based on F factor
Billed as p/kWh
Export capacity charge
Billed as p/kVA/day
© 2007 E.ON
Component of Demand Tariffs
10 April 2023, E.ON, Page 39
Component Driver Applied by
Sole use Sole use asset MEAV
Fixed charge
Charge 1 Capacity/peak-time consumption
Capacity charge
Exit Peak-time consumption
Capacity charge
Scaling – peak-time
Peak-time consumption
Capacity charge
Scaling – capacity
Capacity Capacity charge
© 2007 E.ON
Breakdown of Demand Tariffs – By DNO
10 April 2023, E.ON, Page 40
(£5m) £5m £15m £25m £35m
CE NEDL
CE YEDL
CN East
CN West
EDFEN EPN
EDFEN LPN
EDFEN SPN
ENW FCP
ENW LRIC
SPEN SPD
SPEND SPM
SSEPD SEPD
SSEPD SHEPD
WPD Wales FCP
WPD Wales LRIC
WPD West FCP
WPD West LRIC
Sole use assets
Charge 1
Transmission exit
Scaling: peak-time consumption
Scaling: capacity
© 2007 E.ON
Component of Generation Tariffs
10 April 2023, E.ON, Page 41
Component Driver Applied by
Sole use if applicable
Sole use asset MEAV
Fixed charge
Charge 1 Units exported
Unit credit
Exit (non generation dominated)
Units exported
Unit credit
Exit (generation dominated)
Capacity Capacity charge
Charge 2 Capacity Capacity charge
© 2007 E.ON
Breakdown of Generation Charges & Credits – By DNO
10 April 2023, E.ON, Page 42
(£5m) £5m £15m £25m £35m
CE NEDL
CE YEDL
CN East
CN West
EDFEN EPN
EDFEN LPN
EDFEN SPN
ENW FCP
ENW LRIC
SPEN SPD
SPEND SPM
SSEPD SEPD
SSEPD SHEPD
WPD Wales FCP
WPD Wales LRIC
WPD West FCP
WPD West LRIC
Charge 1 credits
Transmission exit credits
Charge 2 charges
Transmission exit charges
© 2007 E.ON
Charging Model Overview (1)
10 April 2023, E.ON, Page 43
© 2007 E.ON
Charge 1 - Demand
• Charge 1 comes from the load flow modelling
• Applied to agreed capacity for network group to which customer is connected
• Applied to demand at time of peak for parent or grandparent groups
• Note: for CN ‘time of peak’ or ‘super red’ time band is 16.00 to 19.00, Mon-Fri, Nov-Feb
10 April 2023, E.ON, Page 44
© 2007 E.ON
Worked Example – Charge 1 Demand
• Location – Derby South BSP• FCP charge 1: £0.24/kVA/yr• Applied to Agreed Capacity: 27,000 kVA• Charge: 27,000 x £0.24 = c. £6,000
• Parent Location – Willington GSP• FCP charge 1: £1.54/kVA/yr• Applied to Peak Time Consumption: c. 15,000 kVA
• Charge: 15,500 x £1.54 = c. £23,000
• Applied as a charge to agreed capacity• Charge = (£0.24 + 1.54*15000/27000) = £1.10/kVA/yr
• £1.10/kVA/yr = 0.3p/kVa/day 10 April 2023, E.ON, Page 45
© 2007 E.ON
Charge 1 - Generation
• Charge 1 comes from the load flow modelling
• Credit (p/kWh) if generator supports the network
• Intermittent generation deemed not to support
• Applied throughout the year (not in super red)
10 April 2023, E.ON, Page 46
© 2007 E.ON
Worked Example – Charge 1 Generation
• Location – Derby South BSP• FCP demand charge 1: £0.24/kVA/yr• Convert to generation credit:
• Non Intermittent: 0.24 x 100 / 8760 x 1 = 0.0027p/kWh
• Intermittent: 0.24 x 100 / 8760 x 0 = 0.0000p/kWh• Applied to Output (kWh): 290,000,000 kWh• Credit: 290,000,000 x 0.0027p = c. £8,000
• Parent Location – Willington GSP• FCP charge 1: £1.54/kVA/yr• Convert to generation credit:
• Non Intermittent: 1.54 x 100 / 8760 x 1 = 0.0176p/kWh
• Intermittent: 1.54 x 100 / 8760 x 0 = 0.0000p/kWh• Applied to Output (kWh): 290,000,000 kWh• Credit: 290,000,000 x 0.0176p = c. £50,000
10 April 2023, E.ON, Page 47
© 2007 E.ON
Charge 2 - Generation
• Charge 2 comes from the load flow modelling
• Applied to agreed capacity for network group to which customer is connected
• Applied to agreed capacity for parent or grandparent groups
10 April 2023, E.ON, Page 48
© 2007 E.ON
Worked Example – Charge 2 Generation
• Location – Stony Stratford BSP• FCP charge 2: £1.81/kVA/yr• Applied to Agreed Export Capacity: 15,000 kVA• Charge: 15,000 x £1.81 = c. £27,000
• Parent Location – East Claydon GSP• FCP charge 1: £0.00/kVA/yr• Applied to Agreed Export Capacity: 15,000 kVA• Charge: 15,000 x £0.00 = c. £0
• Applied as a charge to agreed capacity• Charge = (£1.81 + £0.00) = £1.81/kVA/yr• £1.81/kVA/yr = 0.5p/kVa/day
10 April 2023, E.ON, Page 49
© 2007 E.ON
Charging Model Overview (2)
10 April 2023, E.ON, Page 50
© 2007 E.ON
Demand Tariffs
• Sole use asset charge• Fixed charge (p/day)• Proportional to modern equivalent asset value
• Based on direct costs only
• Transmission exit• All expressed as capacity charges (p/kVA/day)
• Charge rate reflects peak-time consumption
10 April 2023, E.ON, Page 51
© 2007 E.ON
Charging Model Overview (3)
10 April 2023, E.ON, Page 52
© 2007 E.ON
Demand Scaling (1)
1. Apportion allowed revenue between voltage levels on basis of MEAVs
2. Split EHV portions (and cost of generation credits) between EDCM customers and CDCM customers on basis of demand
• At voltage level of connection use agreed capacity for EDCM customers
• At higher voltage levels use demand at peakThis gives the EDCM Demand pot
3. Subtract demand charge 1, sole use, transmission exit and add back generation credits to give required scaling amount
10 April 2023, E.ON, Page 53
© 2007 E.ON
Demand Scaling (2)
4. Required scaling amount divided by sum of agreed capacities and estimated peak time consumption of all EDCM demand customers giving a single £/kVA/year fixed adder
5. Fixed adder applied to agreed capacity and estimated peak time consumption of each EDCM user.
Between 2 otherwise identical customers:• The one with the higher agreed capacity will pay
more in scaling• The one with the highest peak time consumption
will pay more in scaling
10 April 2023, E.ON, Page 54
© 2007 E.ON
Demand Scaling – IllustrationScaling Revenue Required: £60,000
10 April 2023, E.ON, Page 55
Ben Nevis Snowdon
Forecast Agreed Capacity 20,000 20,000
Historic Peak time consumption as a proportion of agreed capacity
18,000 2,000
Scaler calculation 60,000 / (20,000 + 18,000 + 20,000 + 2,000)
= £1/kVA/yr
Scaler £1/kVa/yr £1/kVA/yr
Scaling calculation 1 x (20,000 + 0.9 x 20,000)
1 x (20,000 + 0.1 x 20,000)
Scaling allocation £38,000 £22,000
© 2007 E.ON
Demand Scaling Options vs current demand charges
10 April 2023, E.ON, Page 56
Current demand charges£ million
Option 14 demand charges£ million
Option 3 demand charges£ million
Option 12 demand charges£ million
Option 15 demand charges£ million
CE NEDL 4.6 5.5 No data 2.1 6.1CE YEDL 4.4 4.8 No data 1.8 4.2CN East 5.5 3.5 2.8 2.0 3.0CN West 1.7 2.1 1.0 1.2 1.7EDFEN EPN 6.5 6.4 1.3 2.6 5.0EDFEN LPN 5.4 10.4 2.2 5.3 8.3EDFEN SPN 10.8 8.2 1.9 2.3 4.5
ENW 6.7 3.8FCP: 3.7
LRIC: 1.81.4 2.5
SPEN SPD 4.8 4.3 3.7 1.8 3.9SPEN SPM 8.2 9.0 8.8 4.7 7.5SSEPD SEPD 14.7 13.1 15.7 9.3 9.5SSEPD SHEPD 1.8 1.1 4.0 0.7 0.8
WPD Wales 9.8 15.6FCP: 10.2LRIC: 8.4
6.7 14.1
WPD West 1.6 2.1FCP: 1.8
LRIC: 1.41.3 1.7
Total 86.3 90.0 43.0 72.9
© 2007 E.ON
Generation Scaling
• No scaling applied to Generation Credits
• Currently proposed no scaling applied to Generation Charges, but options being discussed:• Add £1/kW/yr to cover O&M• calculate scaler for post 2005 DG targeting
post 2005 DG allowed revenue and apply scaler to all DG
10 April 2023, E.ON, Page 57
© 2007 E.ON
Charging Model Overview (4)
10 April 2023, E.ON, Page 58
EDCM prices
© 2007 E.ON
CNE tariff Movements
10 April 2023, E.ON, Page 60
© 2007 E.ON
CNE tariff Movements
10 April 2023, E.ON, Page 61
© 2007 E.ON
Component of Demand Tariffs
10 April 2023, E.ON, Page 62
Component Driver Applied by
Sole use Sole use asset MEAV
Fixed charge
Charge 1 Capacity/peak-time consumption
Capacity charge
Exit Peak-time consumption
Capacity charge
Scaling – peak-time
Peak-time consumption
Capacity charge
Scaling – capacity
Capacity Capacity charge
© 2007 E.ON
Breakdown of Demand Tariffs – By DNO
10 April 2023, E.ON, Page 63
(£5m) £5m £15m £25m £35m
CE NEDL
CE YEDL
CN East
CN West
EDFEN EPN
EDFEN LPN
EDFEN SPN
ENW FCP
ENW LRIC
SPEN SPD
SPEND SPM
SSEPD SEPD
SSEPD SHEPD
WPD Wales FCP
WPD Wales LRIC
WPD West FCP
WPD West LRIC
Sole use assets
Charge 1
Transmission exit
Scaling: peak-time consumption
Scaling: capacity
© 2007 E.ON
Breakdown of Demand Tariffs – By Customer - CNE
10 April 2023, E.ON, Page 64
© 2007 E.ON
Breakdown of Demand Tariffs – By Customer - CNW
10 April 2023, E.ON, Page 65
© 2007 E.ON
Component of Generation Tariffs
10 April 2023, E.ON, Page 66
Component Driver Applied by
Sole use if applicable
Sole use asset MEAV
Fixed charge
Charge 1 Units exported
Unit credit
Exit (non generation dominated)
Units exported
Unit credit
Exit (generation dominated)
Capacity Capacity charge
Charge 2 Capacity Capacity charge
© 2007 E.ON
Breakdown of Generation Charges & Credits – By DNO
10 April 2023, E.ON, Page 67
(£5m) £5m £15m £25m £35m
CE NEDL
CE YEDL
CN East
CN West
EDFEN EPN
EDFEN LPN
EDFEN SPN
ENW FCP
ENW LRIC
SPEN SPD
SPEND SPM
SSEPD SEPD
SSEPD SHEPD
WPD Wales FCP
WPD Wales LRIC
WPD West FCP
WPD West LRIC
Charge 1 credits
Transmission exit credits
Charge 2 charges
Transmission exit charges
© 2007 E.ON
Breakdown of Generation Tariffs – By Customer - CNE
10 April 2023, E.ON, Page 68
© 2007 E.ON
Breakdown of Generation Tariffs – By Customer – CNW
10 April 2023, E.ON, Page 69
© 2007 E.ON
Importance of Demand Profile
10 April 2023, E.ON, Page 70
0
2,000
4,000
6,000
8,000
10,000
12,000
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47
Demand profile - cust 1
0
2,000
4,000
6,000
8,000
10,000
12,000
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47
Demand Profile - cust 2
Illustrative Charges: Cust 1: £200,000 Cust 2: £200,000
Charges if same profile as cust 2: Charges if same profile as cust 1:Cust 1: £270,000 Cust 2: £140,000
Key consultation issues
© 2007 E.ON
Key consultation issues
• Power flow modelling• Pre-April 2005 generation• Charge 1 for demand• Demand/generation side management• Generation credits• Generation charges• No demand credits• Negative charges• Transmission exit charges• Sole use asset charges• Generation scaling• Demand scaling options• Tariff components• Interconnected networks• Volatility
10 April 2023, E.ON, Page 72
Future developments
© 2007 E.ON
Future Developments
• The Distribution Charging Methodology Forum will be the place where ideas relating to charging are discussed and developed
• Changes arising from this will become the subjects of formal modification proposals under DCUSA governance
• DCUSA parties can raise modification proposals• Other materially affected parties can also raise
modification proposals, with the Authority’s approval
• The future of charging is in your hands!
10 April 2023, E.ON, Page 74
05 July 2010
EDCM Stakeholder Workshop
Thank You – Safe Journey Home!