* Reference Carry Over Work KHAN to perform Turret COW, divided into 2 stages called as Phase 1for work preparation and Phase 2for execution. Project: BP Quad 204 Turret Carry Over Work Phase -1 Project Owner: BP Period: Oct. 2013 ~ Jan. 2014 Peak M/P : 10 <Turret Construction Site in Singapore> Scope of Work: - Site Survey - Preparation of Carry Over Work Packs & Issue of Job Cards (Total 233) (E& I: 109 / Machinery & Hydro: 25 / Pipe & Structure : 99 Packages) - Review & Analyze COW Construction Availability and Reflect to Job Cards - Execute COW at Phase-2 Stage in accordance with Job Cards 1 >> BP Quad 204 Turret Carry Over Work, Phase-1 <Sample of Job Card approved>
10

* Reference Carry Over Work · 2018. 4. 11. · E&I, Painting, Scaffolding, Insulation, Piping 2 May 2016 Dec. 2017 Petronas Carigali UZMA Engineering Petronas Carigali Kinanbalu

Feb 09, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • * Reference –Carry Over Work

    KHAN to perform Turret COW, divided into 2 stages called as “Phase 1” for work preparation and “Phase 2” for execution.

    Project:

    BP Quad 204 Turret Carry Over Work

    Phase -1

    Project Owner: BP

    Period: Oct. 2013 ~ Jan. 2014

    Peak M/P : 10

    Scope of Work:

    - Site Survey

    - Preparation of Carry Over Work Packs & Issue of Job Cards (Total 233)

    (E& I: 109 / Machinery & Hydro: 25 / Pipe & Structure : 99 Packages)

    - Review & Analyze COW Construction Availability and Reflect to Job Cards

    - Execute COW at Phase-2 Stage in accordance with Job Cards

    1

    >> BP Quad 204 Turret Carry Over Work, Phase-1

  • Project:

    BP Quad 204 Turret Carry Over Work, Phase -2

    Project Owner / Client: BP

    EPCI Contractor: HHI

    Period: Feb. 2014 ~ Dec. 2015

    Peak M/P: 150

    Man-hours: 498,456 MH

    Scope of Work:

    - Execution of the Carry-Over Work Packs & Job Cards

    - Additional Work / Changes instructed by Client

    - Discipline: E&I, Pipe & Mech., Structure, Materials

    2

    >> BP Quad 204 Turret Carry Over Work, Phase-2

    * Reference –Carry Over Work

  • Project: Shell Prelude FLNG Turret Carry Over Work

    Project Owner: Shell

    Client : SBM Offshore

    Period: Dec. 2015 ~ June 2017

    Scope of Work:

    - Site Survey

    - Job Card Development

    - Project Completion System

    - Material Preparation

    - Tool & Consumables Preparation

    - Planning / Scheduling / Mobilizing COW in accordance with

    Phase-1

    - Execution of the Carry-Over Work Packs & Job Cards

    >> Shell Prelude FLNG Turret Carry Over Work, Phase-1, 2

    3

    * Reference –Carry Over Work

  • Project: SHELL Prelude FLNG MEG Module Carry Over Work

    Project Owner: SHELL

    Client : Fjords Processing

    Period: Sep. 2015 ~ Dec. 2016

    Peak M/P : 80

    4

    >> Shell Prelude FLNG MEG Module Carry Over Work, Phase-2

    - Insulation

    Scope of Work:

    - Site Survey, Planning, Mobilizing, Materials Management &

    Procurement (for Piping/Instrument/Electrical Equipment Installation)

    - Preparation and Development of Carry Over Work Packs

    - Execution of Carry Over Work Packs

    - E&I: Termination, Instrument and Cable Tray Installation,

    ‘Ex’ Equipment Installation, Inspection, MC, etc.

    - Piping: HT-Package Work - 127 PKGs

    - Structure and Mechanical COW

    - Surface Preparation and Coating (TSA)

    - MC including Specified Testing of all Identified Systems

    * Reference –Carry Over Work

  • Project: Statoil CAT-J Rig Carry Over Work, Phase-2

    Project Owner: Statoil

    Client : KCA DEUTAK

    Period: Mar. 2016 ~ Aug. 2017

    Scope of Work:

    - Job Planning and Manpower Mobilization

    - Material Preparation and Management

    - Coax Cable Installation with CCTV

    - Execution of E&I, Painting, Scaffolding, Insulation, and

    Piping Work

    - All discipline Punches / Changes instructed by Client

    - Accommodation and Cinema Room Setting

    - Sail Away Modification While Traveling

    >> Statoil CAT-J Rig Carry Over Work, Phase-2

    5

    * Reference –Carry Over Work

  • • QA/QC plan

    • HSE plan

    • Progress plan

    • Qualification plan

    • Mobilization plan

    • Job Card creation

    • Capability evaluation

    • Approval by Company

    • Check

    • Tracking for receipt

    • Identification

    • Classification

    • Record

    • Review of drawings / work

    volume / work package etc

    • Analysis of construction

    availability

    PLANNING PLANNING

    PREPARATION

    MATERIAL

    PHASE1

    Project:

    INPEX Ichthys FPSO Turret Integration Work Phase-1

    Project Owner: INPEX

    EPCI Contractor: DSME

    Period: Aug. 2014 ~ May 2015

    Scope of Work

    - Site Survey

    - Preparation of Carry Over Work Packs & Job Cards

    - Issue of Management Deliverables required for Phase-2

    6

    >> INPEX Ichthys FPSO Turret Carry Over Work, Phase-1

    * Reference –Carry Over Work

  • Project:

    INPEX Ichthys FPSO Turret Carry Over Work

    Project Owner: INPEX

    Client : SBM Offshore

    Period: Dec. 2015 ~ July 2017

    Scope of Work :

    - Supply of Nylon Pads (material, fabrication & installation)

    - HVAC Ducting Fabrication

    - Site Queries

    1. Handrail Modification

    2. Cable Gland Replacement

    3. Pad Eyes Load Test & NDT Inspection

    4. Material Supply of PDZT Bracket / Transfer Rail /

    Utility Station / T-Guard

    7

    >> INPEX Ichthys FPSO Turret Carry Over Work, Phase-2

    * Reference –Carry Over Work

  • * Reference –Carry Over Work

    Project: BP Quad 204 Water Injection Pump Skids Carry Over Work

    Project Owner: BP

    Period: May 2013 ~ June 2013

    Total Man-hour: 1,765 MH

    Pump Skid Weight: Approx. 70 Ton

    Peak M/P: 35

    Scope of Work:

    - Loading / Unloading - Installation / Assembly Work

    - E&I - Piping

    - Machinery - Punch Clear

    - Fabrication (Outfitting)

    8

    >> BP Quad 204 Injection Skids Carry Over Work

  • 9

    NO.PERIOD

    OWNER CLIENT PROJECT NAME SCOPE OF WORKSTART DELIVERY

    1 Feb. 2016 Jan. 2018 Statoil TechnipMartin Linge

    Carry Over Work Phase-2

    Site Survey, Planning, Mobilization, Materials

    Management & Procurement

    E&I, Painting, Scaffolding, Insulation, Piping

    2 May 2016 Dec. 2017Petronas

    Carigali

    UZMA

    Engineering

    Petronas Carigali

    Kinanbalu NAG Phase-II

    Gas Compressor Module

    Carry Over Work

    Job Card Development, Reviewing of Detail Design

    & Shop Drawing / As-Built Drawing, Onshore

    Fabrication, Procurement & Logistics for Installation

    Works

    3 Feb. 2017 Aug. 2017 StatoilKCA

    DEUTAK

    Statoil CAT-J Carry Over

    Work Phase-2

    Site Survey, Planning, Mobilization, Materials

    Management & Procurement

    E&I, Painting, Scaffolding, Insulation, Piping

    4 Aug. 2014 July 2017 INPEXSBM

    Offshore

    INPEX Ichthys FPSO

    Turret Carry Over Work

    Phase-1, 2

    Phase-1 : Work Pack & Job Card Preparation

    Phase-2 : Supply of Nylon Pads, HVAC Ducting

    Fabrication, Site Queries

    5 Dec. 2015 June 2017 SHELLSBM

    Offshore

    SHELL Prelude FLNG

    Turret Carry Over Work

    Phase-1, 2

    Phase-1 : Job Card Development, Project

    Completion System, Material Preparation

    Phase-2 : Execution of Work Pack & Job Card

    (Planning / Scheduling / Mobilizing)

    6 Sep. 2015 Dec. 2016 SHELL Technip

    SHELL Prelude FLNG

    MEG Module Carry Over

    Work Phase-2

    Site Survey, Planning, Mobilizing, Materials

    Management & Procurement

    Work Pack Development and Execution of

    Carry Over Work Packs

    7 July 2014 May 2016 BP HHIBP Clair Ridge Topside

    Module Construction Work

    FPSO & Platform Construction Work in E&I,

    Pipe, Mech., Structure, Paint, Scaffolding,

    HVAC

    * Reference –Carry Over Work

  • 10

    NO.PERIOD

    OWNER CLIENT PROJECT NAME SCOPE OF WORKSTART DELIVERY

    8 Oct. 2013 Dec. 2015 BP HHIBP Quad 204 Turret Carry

    Over Work, Phase -1, 2

    Phase-1 : Site Survey, Work Pack

    Preparation, Job Card Issue

    Phase-2 : Execution of Work Pack & Job Card

    9 May 2013 June 2013 BP BP

    BP Quad 204 Water

    Injection Pump Skids Carry

    Over Work

    Loading / Unloading, Installation / Assembly

    Work, E&I, Piping, Machinery, Punch Clear,

    Fabrication(Outfitting)

    * Reference –Carry Over Work